Pennsylvania now has a running public count of data center projects passing through state environmental permitting, and most of them have not started the process. The Department of Environmental Protection's Data Center Permit Tracker lists 78 projects statewide, all classified as type "Data Center." According to the tracker's project file, read by DataCenterFeed on Nov. 28, 2026, 51 are marked "Proposed (No Applications Received)," 24 are "Under Review," and 3 show "DEP Review Complete."
The tracker separates two questions that tend to get blurred in local debates: how many projects have been announced or identified, and how many have actually filed paperwork with the state. Going by DEP's own data, about two-thirds of the listed projects have not reached the second stage.
What the Tracker Counts
DEP publishes the tracker as two downloadable data files. The first has one row per project. The second has one row per individual authorization, meaning a specific permit, plan approval or registration tied to a project ID. The project file has no snapshot date.
The permit-level file has 419 authorization rows. Their status, according to the file:
- Not Yet Submitted: 290
- Issued: 83
- Pending: 41
- Received: 2
- On Hold: 1
- Returned: 1
- Withdrawn: 1
Most of the rows sit in the "Not Yet Submitted" column, including rows for projects still in the proposed stage. By DataCenterFeed's count from the file, 27 projects have at least one authorization at a status other than Not Yet Submitted.
The largest authorization categories in the file are:
- Erosion and Sediment Control: 99
- Water Obstructions and Encroachments: 79
- Air Quality: 72
- Storage Tanks: 71
- Clean Water: 32
- Act 537 sewage planning: 26
- NPDES: 8
- Safe Drinking Water: 4
Of the 72 Air Quality rows in the file, 9 are issued, 7 are pending and 56 are not yet submitted. The counts of Air Quality and Storage Tanks authorizations come from DEP's file; the tracker does not say what any individual authorization is for.
Where the Projects Are
The projects are concentrated in one part of the state. DEP's project file assigns 42 of the 78 to its Northeast Region. Southeast and Southwest have 11 each, Southcentral has 7, Northcentral has 4 and Northwest has 3.
Two Northeast counties account for more than a third of the statewide list. Luzerne County has 15 projects and Lackawanna County has 12. Montgomery County has 6 and Beaver County has 4.
The three projects marked DEP Review Complete are:
- an Amazon Web Services Phase 1 project in Salem Township, Luzerne County;
- an Amazon Web Services Phase 1 project in Falls Township, Bucks County; and
- Keystone Connect, a TECfusions project in Westmoreland County.
The 24 projects under review include Project Hazelnut (NorthPoint) in Hazle Township, QTS Salem, Project Boson in Archbald, and Project Atlas in South Whitehall Township, Lehigh County.
Project Atlas: Two Tracks at Once
Project Atlas shows how state and local review run on separate timelines. In DEP's tracker, the project is listed under Edged US / CDE Acquisitions with coordinated permit ID DC39-001 and a status of Under Review.
LehighValleyNews.com reported in December 2025 that the Lehigh Valley Planning Commission had accepted plans for Atlas Industrial: six buildings and an electric substation totaling 5.1 million square feet at 2493 N. Cedar Crest Blvd. in South Whitehall Township, across the street from Parkland High School. According to that report, the regional commission had accepted the plans but had not yet conducted a thorough review.
On the state side, US Data Center Projects reported on Nov. 24, 2026 that DEP held a public hearing and consultation on the project's environmental permit applications, at Cedar Crest College. The department will consider the comments it received as part of its assessment, and the report says the applications remain under review with no permit decision yet. The article did not give the hearing date.
Zoning, land development and site plan approval stay with the township and run in parallel with the state process. A DEP permit does not settle the local questions, and a township approval does not replace DEP's environmental authorizations. In DEP's terms, a project can be "under review" while the municipal process is still open.
How to Read the Numbers
A few cautions follow from how the tracker is built:
- Proposed does not mean filed. The 51 projects in the "Proposed (No Applications Received)" category have not submitted applications to DEP, according to the tracker.
- Issued authorizations are not project approvals. The 83 issued rows are individual permits across many categories. One project can need several, and an issued erosion control permit does not mean a campus has every permit it needs.
- Review Complete is a DEP status. It describes the state environmental review. It says nothing about local land use approvals, utility interconnection or construction.
- The data is a snapshot. The project file has no date of its own, so the counts may change when DEP updates it.
What Happens Next
For Project Atlas, US Data Center Projects reports that the South Whitehall Township planning commission is expected to review the plans again at its Jan. 13 meeting, and that the township has until Feb. 28 to act. DEP will consider the comments from its public hearing in its assessment of the project's environmental permit applications. No decision date has been reported.
Statewide, the tracker's status columns will show which projects move from proposed to filed and from pending to issued as DEP updates the data.
Sources
- Pennsylvania DEP Data Center Permit Tracker, project tracking file (gis.dep.pa.gov), read Nov. 28, 2026
- Pennsylvania DEP Data Center Permit Tracker, permit-level file (gis.dep.pa.gov), read Nov. 28, 2026
- Pennsylvania DEP weighs Project Atlas permits after public hearing in South Whitehall (US Data Center Projects, Nov. 24, 2026)
- 5.1 million-square-foot Atlas Industrial data center could be built across from Parkland High School (LehighValleyNews.com, Dec. 17, 2025)