The Tennessee Valley Authority has disclosed an agreement under a new charge aimed at large data center loads. The customer has agreed to pay a total of $1.7 billion for the capacity it asked TVA to reserve. TVA disclosed the deal in the subsequent-events note of its annual report on Form 10-K for the fiscal year ended Sept. 30, 2026. The filing does not name the customer or say how many megawatts the customer requested.

The agreement is an early public sign of how the federal utility's revised wholesale rate structure works in practice. TVA's board approved that structure in August, and it took effect on Oct. 1.

What the Filing Says

According to Note 26 of the 10-K, TVA set up a Capacity Commitment Charge (CCC), effective Oct. 1, 2026, for new and expanding data center loads above 5 MW. The note says TVA entered into a CCC agreement on Nov. 10, 2026, and is entitled to aggregate payments of $1.7 billion under it.

The 10-K lays out the payment schedule. An initial payment of $31 million is due when the agreement is signed, and the remaining balance is due over 59 subsequent installments. The filing says the rate is approximately $1.5 million per MW of requested capacity above 5 MW. It describes that price as current cohort-based pricing methodology that may be revised for future customer cohorts. In other words, later data center customers may not pay the same rate per megawatt.

The filing also covers accounting. TVA says it expects to record the initial payment as an account receivable and a corresponding regulatory liability in November 2026. It says the classification of that liability depends on the amortization period, which TVA is still evaluating.

EDGAR lists the 10-K as filed on Nov. 13, 2026, and the auditor's report inside it is dated Nov. 12. Utility Dive, which reported the deal on Nov. 24, said TVA disclosed it in a Nov. 12 SEC filing. This article uses the EDGAR filing record.

Where the Charge Came From

The CCC is one piece of a broader rate change. On Aug. 20, TVA announced that its board had approved changes to the wholesale rate structure. In its news release, TVA said the changes are meant to protect residential and manufacturing customers from subsidizing the expenses associated with data center growth. The release tied the changes to TVA's recent signing of the Ratepayer Protection Pledge. The 10-K also describes the rate changes as aligned with that pledge.

The 10-K says the changes took effect Oct. 1, 2026, and will be phased in through 2029. Utility Dive reported that the phase-in applies to existing customers, citing earlier reporting by the Nashville Scene.

The board took several other actions at the same August meeting, according to TVA's release:

  • It approved the recommendations in TVA's 2026 Integrated Resource Plan. TVA's release says the plan suggests the region will need 11 to 32 GW of additional generation capacity between now and 2040.
  • It approved TVA's fiscal 2027 budget. The release says more than $13 billion is planned through fiscal 2029 to maintain reliability and expand capacity.

The release quoted Mike Skaggs, then TVA's interim president and CEO, and board chair Mitch Graves. Utility Dive reported that Skaggs was named permanent CEO after a Nov. 10 board meeting, the same day the CCC agreement was signed. Utility Dive also reported that on TVA's Nov. 13 earnings call, Skaggs said the data center rate change has supported the utility's investments, including extending the lives of existing nuclear units.

Generation Projects Around the Charge

The CCC arrives alongside a large generation buildout that TVA describes in its own filings and that trade press has reported on. Neither the filing nor Utility Dive ties the $1.7 billion agreement to a specific project.

Kingston. The 10-K says TVA is constructing the 1,500 MW Kingston Gas Plant, a combined cycle and aeroderivative plant expected to be operational by the end of calendar 2028. According to the filing, TVA had spent $2.4 billion on the project as of Sept. 30, 2026, and expects to spend an additional $432 million through calendar 2028.

New gas approved in August. Utility Dive reported that TVA's filing says the board approved 1.5 GW of new natural gas generation in August, "targeted to be online in 2032." Per the filing as quoted by Utility Dive, TVA had spent $463 million as of Sept. 30 on long-lead-time equipment from previously approved projects that will now be used for it, and could spend up to an additional $3.1 billion on the project. Utility Dive identified the previously approved project as TVA's defunct Middle Tennessee Energy Solution project. Utility Dive also cited $13 billion in planned capital investment over the next three years, in line with the figure in TVA's August release.

Clinch River. The 10-K says the Nuclear Regulatory Commission approved the construction permit application for a BWRX-300 small modular reactor at TVA's Clinch River Site in Oak Ridge, Tennessee, in September 2026. TVA says in the filing that it has not yet decided whether to construct a reactor at the site.

What Is Not Disclosed

The 10-K does not name the customer. It also does not state the capacity the customer requested, where the load would connect, or when it would start drawing power. The filing gives a per-MW rate and an aggregate payment figure. It does not say how those translate into a specific megawatt total for this agreement, and readers should not assume one. Utility Dive's report also does not identify the customer.

The filing calls the $1.5 million-per-MW figure current cohort-based pricing that may be revised for future cohorts. For local officials and developers weighing projects in the Tennessee Valley, that means this agreement reflects what one customer agreed to under TVA's current terms. The filing does not describe it as a fixed price for later customers.

What Happens Next

The steps on the record come from TVA's filings and Utility Dive's report:

  • November 2026 accounting entry. TVA says in the 10-K that it expects to record the $31 million initial payment as an account receivable and a corresponding regulatory liability in November 2026. It is still evaluating the amortization period.
  • Remaining payments. The remaining balance of the $1.7 billion is due over 59 subsequent installments after the initial payment, according to the filing.
  • Future cohorts. The filing says the current per-MW price reflects cohort-based pricing methodology that may be revised for future customer cohorts.
  • Rate phase-in. The revised wholesale rate structure that took effect Oct. 1, 2026, will be phased in through 2029, according to the 10-K.
  • Generation milestones. TVA expects Kingston to be operational by the end of calendar 2028, according to the 10-K. The filing, as quoted by Utility Dive, targets 2032 for the 1.5 GW gas generation approved in August. TVA has not decided whether to build a reactor at Clinch River.