Amazon Web Services and Northern Indiana Public Service Co. (NIPSCO) officials held a groundbreaking for Project Rise, a $7 billion data center campus in Wheatfield in Jasper County, Indiana, according to a Nov. 16 MLQ.ai report that draws on coverage from the Times of Northwest Indiana, Inside INdiana Business, Northwest Indiana Business Magazine, InkFreeNews and Utility Dive. That report dates the ceremony to Thursday, Nov. 12. The MLQ.ai report itself was published on Nov. 16, so readers may see either date tied to the groundbreaking.
The campus is near NIPSCO's R.M. Schahfer Generating Station, and the utility side of the deal is moving through regulatory review. Parent company NiSource's quarterly filing with the Securities and Exchange Commission shows how far the regulatory work has come and what is still pending. Indiana regulators have approved the core Amazon power contract. A contract amendment and federal approvals of the affiliate deals behind the generation are still open, and the generation affiliate has now signed a large battery storage agreement.
The Campus
According to the MLQ.ai report, Project Rise covers 304 acres that NIPSCO owned near the Schahfer station. Speakers at the event included AWS economic development principal Scott Eckhardt and Rick Calinski, NIPSCO's director of public affairs and economic development, the report said. Jasper County officials approved the development agreements in June, according to the report.
The aggregated report, citing Northwest Indiana Business Magazine, puts employment at about 250 jobs. It describes Project Rise as separate from Amazon's $11 billion campus in New Carlisle, St. Joseph County, which broke ground in 2024.
For cooling, the report says the data centers will mostly use outside air, with water-based cooling needed about 2% of the year. According to the same report, AWS will pay for the campus's water and wastewater infrastructure, including $25 million to extend public water service in Wheatfield Township.
Local Tax Figures Differ by Outlet
The local fiscal numbers depend on which outlet is cited. MLQ.ai, citing Northwest Indiana Business Magazine, reports that Amazon paid $98 million to the county in advance. It also reports that county revenue from the site would rise from about $70,000 a year in property taxes today to more than $20 million a year over 10 years. MLQ.ai separately cites InkFreeNews putting the annual payments at $23 million for 10 years, and says local officials estimate more than $1 billion in tax revenue over 15 years. DataCenterFeed has not reviewed the county's development agreements directly, and the outlets' figures have not been reconciled in the coverage we read.
The Power Arrangement Behind the Site
The utility structure dates to late 2025. Utility Dive reported in November 2025 that NIPSCO and a NiSource affiliate known as GenCo planned up to 3 GW of gas generation and battery storage for planned Amazon data centers in northern Indiana. According to that report, the companies expected to spend about $7 billion on generation and transmission, to be paid for by Amazon. NIPSCO would begin providing power and capacity to the Amazon data centers by Jan. 1, 2027, with deliveries climbing up to 2.4 GW by the end of 2032, according to NIPSCO president Vincent Parisi in an Indiana Utility Regulatory Commission (IURC) filing. Utility Dive reported that the plan included 2.6 GW of gas generation at the Schahfer site. It also reported that the contract gives Amazon a one-time option, by March 31, 2029, to reduce its total capacity by 1,200 MW, according to NIPSCO.
The same report said NIPSCO expects its 15-year deal with Amazon to produce about $1 billion in savings for ratepayers, according to a Nov. 7, 2025 filing by NIPSCO and NIPSCO Generation at the IURC. It noted that the Citizens Action Coalition was reviewing the proposal and had raised concerns about emissions and affordability. Those figures come from the 2025 filings and may not reflect later changes.
MLQ.ai's groundbreaking report adds that NIPSCO is also building a 400 MW gas peaker plant at Schahfer. It cites construction and financing costs of $643.7 million in testimony to Indiana's consumer counselor.
What the 10-Q Says
NiSource's Form 10-Q for the quarter ended Sept. 30, 2026, signed Oct. 28, sets out the regulatory record. The filing does not name the Wheatfield campus.
- State approval. In November 2025, NIPSCO and GenCo asked the IURC to approve the contract with Amazon Data Services (ADS), a related power purchase agreement between NIPSCO and GenCo, and an alternative regulatory plan. The commission issued an order in June 2026 fully approving a stipulation and settlement agreement filed by NIPSCO, GenCo, the Indiana Office of Utility Consumer Counselor and the NIPSCO Industrial Group.
- A separate hyperscaler contract. The IURC approved a separate retail special contract between NIPSCO and a wholly owned subsidiary of Alphabet in July 2026, as filed and without change, according to the filing.
- Amendment for more service. In July 2026, NIPSCO and GenCo applied to the IURC for an amendment to the ADS contract covering incremental service. NiSource expects an IURC order in the fourth quarter of 2026.
- Federal approvals. In August 2026, NIPSCO and GenCo filed applications with the Federal Energy Regulatory Commission (FERC) seeking authorization for affiliate transactions between GenCo and NIPSCO to serve ADS and Alphabet. NiSource expects FERC orders in the fourth quarter of 2026.
- Battery storage. In October 2026, GenCo entered into what the filing calls the AGP Tolling Agreement. It covers a 600 MWac / 2,400 MWh battery energy storage system, for approximately $2.2 billion over an approximately 20.5-year delivery term. Commercial operation of the first phase is expected by Dec. 1, 2027.
- Capacity deal. The filing says GenCo has entered into a capacity agreement for 2028 through 2040 for approximately $1.1 billion, subject to regulatory approval. It also describes a 167 MW Tipton battery storage project expected to be completed in 2028.
The filing also shows GenCo growing quickly on NiSource's books. NiSource reports GenCo as a variable interest entity. Its net property, plant and equipment was $634.8 million at Sept. 30, 2026, up from $39.7 million at Dec. 31, 2025. In October 2025, Blackstone investors received a 19.9% equity interest in Generation Holdings II, the sole owner of GenCo, in exchange for $35.2 million in cash contributions, according to the 10-Q. NiSource said it began recording GenCo revenue in the third quarter of 2026.
Why the Structure Matters
The arrangement places new generation for a large customer in a separate affiliate, GenCo. Utility Dive reported in 2025 that GenCo would own and operate power plants for large-load customers and that Amazon would pay for the generation and transmission. The 10-Q says the IURC's June 2026 order fully approved a settlement agreement that included the state consumer counselor and an industrial customer group, among others. The FERC applications cover affiliate transactions between GenCo and NIPSCO.
For residents and local officials, the pending items in the record are the incremental ADS service before the IURC and the federal affiliate approvals. The 10-Q does not say whether either is contested.
What Happens Next
According to NiSource's 10-Q, the IURC is expected to rule in the fourth quarter of 2026 on the July 2026 amendment to the Amazon Data Services contract for incremental service. FERC orders on the August 2026 affiliate-transaction applications for GenCo-NIPSCO deals serving ADS and Alphabet are also expected in the fourth quarter of 2026. The GenCo capacity agreement for 2028 through 2040 remains subject to regulatory approval. The first phase of the 600 MWac battery system under the AGP Tolling Agreement is expected to reach commercial operation by Dec. 1, 2027. Under the 2025 filings Utility Dive reported, power deliveries to Amazon are scheduled to begin by Jan. 1, 2027.