The Westlake Town Council on Nov. 12 approved a development agreement with Circle T Owner, LP for a data center campus on the town's border with Keller. The developer is associated with PowerHouse Data Centers. The vote came after a stall that began when a temporary restraining order blocked an August vote, according to the Fort Worth Report. At the same special-called meeting, the council approved a settlement among Westlake, the City of Keller, the developer and adjacent residents.

The agreement adds physical buffers, a cap on cooling-water use and a condition that ties the project's certificate of occupancy to a state-level audit of data centers ordered by the Governor. Each of these appears in the town's agenda packet for the meeting.

The Site and the Dispute

According to the town's agenda packet (Item E.1, Resolution 26-36), the tract covers about 87.96 acres at the northeast corner of U.S. 377 and Westport Parkway. The Fort Worth Report describes it as an 88-acre project about 500 feet from Keller backyards. The packet says the Planning and Zoning Commission approved the site plan with conditions on Aug. 4, 2026, and that the development agreement was tabled on Aug. 17, 2026.

The Dallas Morning News reports that a homeowners association and several individuals filed a lawsuit in August, and that the City of Keller later joined the case as an intervenor. Online court records show the case marked closed on Nov. 6, the paper reports.

How the Council Voted

The vote count on the development agreement is reported two ways. The Fort Worth Report reports a 5-1 vote. The Dallas Morning News reports 4-1, with Council Member Michael Yackira dissenting. The paper says his concerns were about electric bills and whether the project fits the town's plans. The agenda packet covers staff reports only and gives no vote totals. Formal minutes had not been posted when this article was written, and the count should be checked against them once they are available.

The Fort Worth Report says the settlement passed unanimously in Westlake, and that Keller's council had unanimously approved it the week before. The Dallas Morning News gives the Keller approval date as Nov. 5. According to the Fort Worth Report, Mayor Kim Greaves thanked PowerHouse for its work with homeowners and Keller leadership.

What the Agreement Requires

The agenda packet lists the main revisions made to the agreement since August. They fall into four groups.

Screening and berm. The packet calls for a 10-foot berm along the southern property line, the boundary with Keller. It also requires continuous evergreen and hardwood screening, with trees at least 3 inches in caliper at the time of planting.

Noise reporting. A qualified professional must prepare quarterly noise reports for one year. Reporting starts within 180 days after the final building is completed, according to the packet. The Fort Worth Report says the separate settlement sets noise limits and site screening requirements and includes $1.8 million to support monitoring the project.

Water. The packet says the cooling system must be designed for an annual water usage effectiveness (WUE) of no more than 0.25 liters per kilowatt-hour, measured as a long-term average. WUE is the water a facility consumes divided by the energy delivered to IT equipment. The packet does not name the cooling technology.

Infrastructure payment. The developer will make a one-time contribution of up to $914,000 to upgrade piping at the town's pump station, due within 30 days after the agreement is signed, according to the packet.

The Governor's-Audit Condition

The agenda packet ties the certificate of occupancy to compliance with the Governor's data center audit directive, described in the packet as based on a press release issued Aug. 3, 2026. The Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) are to carry out the audit. The packet says that if the developer cannot obtain documentation of compliance from the PUCT and ERCOT, the Town Manager may ask the developer to repurpose the buildings for another allowed use.

This makes the PUCT and ERCOT process part of the project's local approval path. The packet does not say how long that review will take or what it will cover.

Revenue and the Settlement Package

Town officials estimate the project will bring Westlake about $5 million a year for the first 10 years, rising to about $7 million after that, according to the Dallas Morning News. The Fort Worth Report gives the same figures, citing town estimates. The packet does not break down how those figures were calculated.

Item D.1 of the agenda (Resolution 26-35) authorized the settlement agreements with the Keller parties, a mutual aid agreement with Keller and an agreement with the developer for payment of the town's attorneys' fees and public relations fees, according to the packet. The Fort Worth Report's account of Keller's terms includes $1.8 million to support monitoring. The full settlement text was not among the sources reviewed for this article.

What Happens Next

Under the terms in the agenda packet, the developer's pump station contribution of up to $914,000 is due within 30 days of the agreement being signed. Quarterly noise reporting begins within 180 days after the final building is completed. The certificate of occupancy cannot be issued until the developer provides documentation of compliance with the Governor's Aug. 3 audit directive, carried out by the PUCT and ERCOT. Once Westlake posts the formal minutes of the Nov. 12 meeting, they will settle the recorded vote on the development agreement.

Sources