Applied Digital made two announcements on the morning of Nov. 23, 2026, fifteen minutes apart. At 7:45 a.m. EST the company said it had closed a $300 million senior secured bridge facility for Delta Forge 1, its AI Factory campus in Louisiana. At 8:00 a.m. it announced a new 18-year lease for 150 megawatts of critical IT capacity with what it called a tier-one investment-grade hyperscaler.

The two releases cover different stages of the business. The lease adds contracted revenue, with delivery of the capacity expected to begin in the first half of 2028. The bridge loan funds construction that is already underway. Each comes with conditions that the company spelled out in its own announcements.

The Lease: What Was Disclosed

According to the company's release, the lease covers 150 MW of critical IT load over an 18-year base term. Applied Digital puts base-term contracted revenue at about $5.4 billion. If the tenant exercises every renewal option, the total term would reach 33 years and contracted revenue about $12.7 billion. The company said the lease carries "higher pricing" than its earlier leases. It did not give a per-megawatt rate or any other pricing figure.

The company said delivery is expected to begin in the first half of calendar 2028. That timing depends on development milestones, utility arrangements and regulatory approvals.

Applied Digital also gave updated portfolio totals. The company said:

  • total base-term contracted lease revenue now exceeds $41 billion, or about $100 billion if all renewals are exercised;
  • the portfolio includes more than 1.6 GW of contracted critical IT load and 2.2 GW of grid-connected peak load;
  • about 75% of base-term contracted revenue comes from investment-grade tenants.

What Was Not Disclosed

The release does not name the tenant or say which campus will host the 150 MW. The company has not published the lease itself. Mugglehead's coverage noted these gaps. It also reported that the release does not say whether the tenant must pay for all 150 MW whether or not it uses them, and that it does not say when the lease commences or when the first payment is due.

Mugglehead's writer divided the base-term value by the term length and arrived at an average of about US$300 million a year over 18 years. That figure is the outlet's own calculation. Applied Digital did not state it, and without a payment schedule there is no way to know how revenue will be spread across the term. Mugglehead also noted that Applied Digital lists the signing and regulatory approval of power supply agreements among its general risks, and that the release does not say whether either step is required for this lease to take effect. The outlet added that the company did not give a dollar figure for the project financing it expects to raise.

Mugglehead reported that Applied Digital shares rose about 27% to US$14.59 as of 10:37 a.m. EST on Monday.

How the Company Says It Will Pay for the Buildout

In the lease release, CFO Saidal Mohmand described the financing plan in stages. The company first puts in equity from its own balance sheet and from its $5 billion programmatic equity partnership with Macquarie Asset Management. Project financing comes after that. Mohmand said the remaining project financing for Delta Forge 1 and Polaris Forge 3 is expected in the first calendar quarter of 2027, and for Delta Forge 2 in the second quarter of 2027.

The Form 10-Q for the quarter ended Aug. 31, 2026, signed Oct. 7, reports net cash provided by financing activities of $1.5 billion in that quarter.

The Bridge Loan for Delta Forge 1

The company describes the $300 million facility as a delayed-draw term loan. It matures in 364 days and carries interest at SOFR plus 300 basis points. The money is for development and construction at Delta Forge 1, which the company says is backed by a lease with a U.S. tier-one investment-grade hyperscaler. The release does not say whether that is the same tenant as the new 150-MW lease.

According to the release, draws are subject to meeting certain conditions, including but not limited to:

  • construction milestones;
  • regulatory approvals, including state commission approval of electrical rates;
  • lender consents;
  • certain financial covenants.

The loan is secured by the assets of the project and can be prepaid at any time without premium. Applied Digital said it expects to seek additional financing to fund completion of construction. The release presents the facility as a bridge, which fits Mohmand's statement that Delta Forge 1 project financing is expected in the first calendar quarter of 2027.

One of the stated draw conditions is state commission approval of electrical rates, which makes the regulatory step relevant to the surrounding area. The release does not say which commission or what rates are involved.

Where the Portfolio Stands

The Form 10-Q, signed Oct. 7, describes the status of each campus. These figures come from the filing and predate the Nov. 23 lease:

  • Delta Forge 1: two buildings totaling 300 MW under construction. Initial ready-for-service is expected in the first half of calendar 2027, with full capacity in early 2028.
  • Polaris Forge 3: two buildings totaling 300 MW. Initial ready-for-service is expected in the second half of 2027, with full capacity in the second half of 2028. The filing describes a power agreement for capacity and energy from a natural gas-fired generation facility of about 1,200 MW to be developed by Base Electron in North Dakota.
  • Polaris Forge 2: two buildings totaling 300 MW. Initial ready-for-service is expected in the second half of 2026, with full capacity in early 2027.
  • Delta Forge 2: a June 5, 2026 lease for 210 MW with a term of about 15 years and three five-year renewal options, with expected delivery in the first half of calendar 2028.

None of these sources links the new 150-MW lease to any of these campuses. The lease release says only that delivery begins in the first half of 2028, a period that also appears in the 10-Q for Delta Forge 2 delivery. Matching timelines doesn't establish a site, and DataCenterFeed is not assigning the lease to one.

What Happens Next

The company and its filings name these next steps:

  • Bridge draws at Delta Forge 1: draws are subject to conditions that include construction milestones and state commission approval of electrical rates, according to the bridge release. The facility has a 364-day maturity from the Nov. 23 closing announcement.
  • First quarter of calendar 2027: Mohmand said remaining project financing for Delta Forge 1 and Polaris Forge 3 is expected.
  • First half of calendar 2027: initial ready-for-service at Delta Forge 1, according to the 10-Q.
  • Second quarter of 2027: project financing for Delta Forge 2 is expected, per the CFO.
  • First half of calendar 2028: delivery under the new 150-MW lease is expected to begin, subject to development milestones, utility arrangements and regulatory approvals.

Applied Digital has not given a date for naming the tenant or the host campus.