Oracle said on Nov. 20 that it has secured the money it needs to fulfill its infrastructure contract with OpenAI, according to Infraday's report on the company's statement. Oracle also gave construction updates on its two large Texas campuses: the Abilene site is nearly complete, and the Shackelford County site has all of its permits.
Oracle pointed to its final capital raise earlier in November and said the vendor financing it outlined to investors is in place. Infraday reported that Oracle said it could fulfill the contract even if ongoing talks with equipment vendors produce no further agreements. DataCenterFeed could not load Oracle's newsroom page for the statement, so the statement's own wording is not quoted here and its details are described as Infraday reported them.
The Money: What Was Raised, and What Wasn't Said
Infraday reported that on Nov. 2 Oracle priced about $10 billion of common stock and $10 billion of senior notes, and that the $20 billion figure describes financing for Oracle as a company. Oracle's Form 8-K confirms both pieces.
A Form 8-K filed in November 2026 (Item 8.01) says Oracle signed an underwriting agreement on Nov. 2 with BofA Securities, Inc., as representative of the underwriters, to sell 86,206,897 shares of common stock, under the heading "Issuance of $10 Billion of Common Stock." The offering closed Nov. 4 under Oracle's automatic shelf registration on Form S-3 (File No. 333-299752).
The same filing describes a separate "$10 Billion Aggregate Principal Amount of Notes" issuance, completed Nov. 4 in five tranches: $2.0 billion of 7.000% notes due 2029, $1.75 billion of 7.450% notes due 2031, $2.25 billion of 7.850% notes due 2033, $2.5 billion of 8.000% notes due 2037 and $1.5 billion of 8.650% notes due 2046. Those tranches add up to $10 billion.
The 8-K says the net proceeds of the offerings will be used for "general corporate purposes, which may include capital expenditures, repayment of indebtedness, future investments or acquisitions and payment of cash dividends on or repurchases of Common Stock." Infraday likewise reported that Oracle did not say how much of the raise it would spend at either Texas campus.
Abilene: Nearly Complete
According to Infraday, Oracle described the Abilene campus as nearly complete. Infraday reported that the site already runs AI workloads, that its eight buildings span 4 million square feet, and that it draws power from the Texas grid, with natural gas turbines for backup. Infraday added that the mix of operating equipment and ongoing construction reflects how the partners have brought the campus online in phases.
Infraday placed both campuses in the context of the agreement OpenAI announced with Oracle in July 2025 to develop another 4.5 gigawatts of Stargate data center capacity beyond the original Abilene project. Infraday noted that figure measures planned capacity across sites. It did not give a megawatt figure for either campus.
Shackelford County: Fully Permitted, Racks Next
Infraday reported that Oracle said it has all the permits for its next gigawatt-scale campus in Shackelford County, and that Oracle expects to hand over NVIDIA Vera Rubin server racks there in the coming weeks. Infraday said Oracle has not given a date for the full campus to enter service.
Oracle's Shackelford County project page, read here through an Internet Archive snapshot captured Oct. 5, 2026, says the campus will include 10 buildings on 1,200 acres, encompassing 3.7 million square feet. Infraday reported the same building count and acreage.
The project page says the campus will rely on its own onsite power system, a microgrid built using "ultra low emission, reciprocating engines." Infraday also described an on-site microgrid. Abilene works differently: by Infraday's account, it draws power from the Texas grid and uses gas turbines only as backup.
The project page says the campus uses a one-time fill, closed-loop, non-evaporative liquid cooling system that "significantly reduces water consumption." The page gives no water-consumption figure. Water use is often a first question for local officials and residents in rural West Texas, so the absence of a number is worth noting.
The same project page projects the local effects:
- More than 5,000 construction jobs
- More than 1,600 ongoing project-supported jobs once construction is completed
- More than $100 million in local county tax revenue
These are Oracle's projections. The page does not say over what period the tax revenue would be collected or how the job counts were calculated. The page also says Oracle will fund college scholarships for Shackelford County students annually throughout the project's lifespan. None of the sources reviewed for this article said whether any local tax abatement or incentive agreement applies to the campus. The snapshot's page footer says its information is current as of January 2026, so these figures may predate the November statement.
Reading the Statement
As Infraday relays it, the statement makes four separate claims, and each rests on different evidence:
- Funding: Oracle says it has the money for the OpenAI contract. The $10 billion common-stock sale and the $10 billion notes issuance are both documented in the 8-K. The vendor financing is described only through Oracle's own statement as reported by Infraday, and DataCenterFeed did not see its terms.
- Abilene: Described as nearly complete. No completion date was reported.
- Shackelford: Described as fully permitted. Infraday did not list the specific permits or the agencies that issued them.
- Hardware: The Vera Rubin rack handover is described as expected in the coming weeks. No specific date was reported.
Oracle did not say how the roughly $20 billion raised in November, or its vendor financing, would be divided between Abilene, Shackelford and its other commitments.
What Happens Next
The next milestone Oracle has identified, per Infraday, is the handover of NVIDIA Vera Rubin racks at the Shackelford County site, which it expects in the coming weeks. Infraday also reported that Oracle describes Abilene as nearly complete. Oracle has not given a date for the remaining Abilene work or for the full Shackelford campus to enter service.