Blackstone Digital Infrastructure Trust Inc. (NYSE: BXDC) has made its first investment. The company plans to buy a controlling stake in two Amazon Web Services data center campuses, one in northern Indiana and one in Mississippi. A Form 8-K filed with the Securities and Exchange Commission on Nov. 16, 2026 values them at about $5.0 billion.

According to the filing, two BXDC subsidiaries, Jade IN Member LLC and Jade MS Member LLC, signed a contribution agreement on Nov. 11, 2026 with Jade SMIN LLC and Jade SMMS LLC, which are affiliates of Amazon Data Services, Inc. Under the agreement BXDC would acquire a 75.1% controlling interest in two limited liability companies that own the campuses. The 8-K puts their aggregate gross value at $5.0 billion, at a 7.0% initial capitalization rate.

BXDC's press release, filed as Exhibit 99.1, calls the deal the company's "inaugural investment" and rounds the stake to 75%, with AWS keeping 25%. The 8-K gives the exact split as 75.1% and 24.9%. Financial News also reported that BXDC had made no investments before this agreement.

What BXDC Is Buying

The 8-K says the portfolio has 13 data centers with 647 MW of aggregate IT power. One campus has nine buildings in northern Indiana, which the 8-K places in the greater Chicago data center market. The other campus has four buildings in Mississippi. The press release describes all 13 as newly constructed "powered shells." The term generally means a building with power and structure delivered, while the tenant installs its own computing and cooling fit-out.

The filing does not give the specific sites, counties or municipalities of either campus. It does not give acreage, square footage or water use either, and neither does the press release. BXDC's CEO, Nick Pell, identified the locations as northern Indiana and Mississippi, the Irish Times reported. No more specific location was given.

How the Leases Work

According to the 8-K, the AWS-affiliated contributors keep a 24.9% interest and receive a cash distribution. The portfolio is 100% leased to the Amazon Data Services tenant on triple-net leases guaranteed by Amazon.com, Inc. Under a triple-net lease, the tenant generally pays property taxes, insurance and maintenance on top of rent.

The 8-K gives these lease terms:

  • A weighted average initial term of 12 years, or 32 years if all extensions are exercised.
  • Rent that rises 2.75% each year.
  • A guarantee of the tenant's payment obligations by Amazon.com, Inc.

The press release and the Irish Times report give the same terms: an initial term of 12 years, extendable to 32.

How the $5 Billion Is Funded

The 8-K divides the $5.0 billion valuation into three parts:

  • About $1.9 billion in cash from BXDC. The money comes from the proceeds of its initial public offering and pays for the 75.1% stake.
  • About $0.6 billion of equity kept by the Amazon affiliates. This is their 24.9% interest.
  • About $2.5 billion of new non-recourse mortgage loans. The filing says debt commitment letters are in place.

Non-recourse mortgage debt is secured by the properties themselves. In general, lenders can take the collateral if the loans go unpaid, but they cannot pursue the borrower's other assets. The 8-K does not name the lenders or give the loan terms.

Financial News pointed out that the $1.9 billion figure comes from the 8-K and the 7.0% cap rate from the press release. In the release, Pell called the assets "an attractive match for the deployment of our IPO proceeds." The financial advisors named in the release were Morgan Stanley, CBRE Capital Markets, Citi, Goldman Sachs, J.P. Morgan and Wells Fargo Bank, N.A., and Simpson Thacher & Bartlett LLP is legal advisor to Blackstone.

Why the Structure Matters Beyond Wall Street

Financial News described the arrangement as a sale-leaseback; the press release says AWS will lease back 100% of the portfolio and keep a 25% interest in the joint ventures. In practical terms, the Amazon affiliates contribute the properties to the joint ventures, keep a minority stake and stay on as the long-term tenant. The leases run an initial 12 years on a weighted-average basis, and 32 years if fully extended.

For the communities that host the campuses, the change is in who owns the real estate: majority ownership would move to a publicly traded company, BXDC. AWS remains the tenant. The press release included a statement from Prasad Kalyanaraman, vice president of AWS Infrastructure, about local benefits, good jobs and workforce training programs; the statement is general and does not tie specific commitments to these two campuses. Neither the release nor the 8-K gives job counts or local investment figures for this transaction, so none are reported here.

Local officials and residents may notice that neither filing names the Indiana or Mississippi sites. Matching these campuses to specific local projects, tax abatement agreements or permits would require information beyond what BXDC disclosed on Nov. 16.

Discrepancies Between the Documents

The documents use different figures. The press release and the Irish Times and Financial News reports give rounded numbers: a 75% stake for BXDC, 25% for AWS and a deal value of "approximately" or "roughly" $5 billion. The 8-K specifies 75.1% and 24.9% and an aggregate gross value of $5.0 billion. This article uses the 8-K figures where the documents differ.

What Happens Next

BXDC's press release says the transaction is expected to close in the fourth quarter of 2026 and is subject to certain closing conditions. According to the 8-K, either party may terminate the contribution agreement if closing has not occurred by Dec. 31, 2026, or a later date extended under the agreement. Termination by a party for the other's failure to close when required entitles the non-breaching party to a $150.0 million termination fee as its sole and exclusive remedy. The 8-K says the roughly $2.5 billion of mortgage loans are backed by lender debt commitment letters, and that the transactions, including the loans, may not be completed on their contemplated terms, or at all.