Soluna Holdings reported its third-quarter 2026 results on Nov. 16. The release covers two Texas campuses that are both under construction but have no signed tenants yet. At Project Kati 2, the company signed a new non-binding letter of intent for 118 IT megawatts. At Project Dorothy 3, it agreed to form a joint venture with Applied Digital for a 50-MW first phase that already has its own non-binding tenant LOI. Soluna expects that joint venture to close by the end of 2026.

Both campuses have received sales and use tax exemptions, and construction began at both in October; Dorothy 3 Phase 1 also has a county tax abatement. Neither has a binding lease. The rest of this piece covers what the company disclosed and what has to happen before either project becomes contracted capacity.

The Quarter in Numbers

The company's earnings release, filed with the SEC as Exhibit 99.1 to a Form 8-K, reported revenue of $15.1 million for the quarter, up 80% from the same period a year earlier. Soluna reported a net loss of $35.4 million and an adjusted EBITDA loss of $7.5 million. The release cited $3.0 million in unplanned repairs to turbines at the Briscoe Wind Farm.

Soluna ended the quarter with $109.3 million in cash and $16.7 million in total debt. On Oct. 22, after the quarter closed, it repaid its Generate Capital debt in full. The company said that left about $7.7 million in principal outstanding. It raised $37.7 million through its at-the-market (ATM) equity program during the third quarter. The release also says $170.1 million raised year to date through the ATM and its SEPA equity line funded the Briscoe Wind acquisition, project capex, buyouts of joint venture partners at Dorothy 1A and 1B, and $40.5 million of debt repayments. Soluna filed its Form 10-Q the same day as the release.

Kati 1, the first building at the Kati site, was fully energized at 83 MW on Sept. 8, according to the release. The two newer projects are larger.

Kati 2: A New Counterparty, Still Non-Binding

Soluna describes Kati 2 as part of a planned campus of more than 350 MW. The new non-binding LOI covers 118 IT MW there. The company's newsroom version of the release carries it in its subheadline: "Signed a new non-binding LOI for 118 MW at Kati."

The word "new" matters here. The deal replaces an earlier arrangement with a prospective tenant whose exclusivity period ended. Soluna did not name the new counterparty in the materials reviewed for this article. A non-binding LOI shows intent to negotiate. It does not, by itself, commit the counterparty to lease capacity. Soluna says construction at Kati 2 began in October, so the company is building ahead of a signed lease.

Dorothy 3: Applied Digital Takes the Majority Stake

According to the release, Soluna acquired 397 acres for Dorothy 3 on Aug. 24 for a planned 300-MW campus. On Oct. 20, it signed a subscription agreement to form a joint venture for the campus's first phase of 50 MW of critical IT load. Applied Digital will hold 51% and Soluna 49%.

Under that structure, Soluna will be the minority partner in its own project's first phase. Applied Digital takes the majority stake. The release says ChronoScale has signed a non-binding LOI to lease the Phase 1 capacity. Closing of the joint venture is expected by the end of 2026.

Local approvals are also moving forward. The Briscoe County Commissioners Court approved a Chapter 312 tax abatement for Dorothy 3 Phase 1 on Nov. 9, according to the release. Soluna says Dorothy 3 construction, like Kati 2, began in October.

The Power Position

Soluna's interconnection status is one of the more concrete parts of the quarter. The release says the company received ERCOT Base Load classifications in September covering 266 MW of existing interconnection capacity: 166 MW at Kati, including Kati 2, and 100 MW at Dorothy. A request for another 50 MW at Dorothy is under study.

For a developer, the ERCOT classification addresses part of the power question. It does not address the tenant or financing questions. The release states the Kati 2 LOI in IT megawatts and the ERCOT figures as existing interconnection capacity. These measure different things, and readers should not assume one maps directly onto the other.

How Neocloud Leases Are Being Written

Another filing on the same day shows what a binding contract looks like. In a press release filed as an 8-K exhibit dated Nov. 16, Corvex disclosed a three-year, $103 million take-or-pay agreement for NVIDIA Blackwell capacity at its Mid-Atlantic 1 site using 1.6 MW of IT load. Corvex said the deployment is funded by a $26 million customer prepayment and $38 million in committed debt financing, with Corvex funding the remaining $14 million of an expected cost of about $78 million.

The two deals are different businesses. Corvex is selling GPU compute capacity, while Soluna and Applied Digital are developing powered data center space. What the Corvex filing shows is the kind of terms a binding contract carries: a fixed term, take-or-pay obligations, and named funding sources. In the Soluna release, neither campus has a binding lease.

What Is Signed and What Is Not

  • Signed or completed: Dorothy 3 land purchase (Aug. 24); Kati 1 energization at 83 MW (Sept. 8); Dorothy 3 JV subscription agreement with Applied Digital (Oct. 20); Generate Capital repayment (Oct. 22); Briscoe County Chapter 312 abatement for Dorothy 3 Phase 1 (Nov. 9); ERCOT Base Load classifications for 266 MW.
  • Non-binding: the 118-IT-MW LOI at Kati 2 and ChronoScale's LOI to lease Dorothy 3 Phase 1.
  • Pending: closing of the Dorothy 3 joint venture, ERCOT's study of the additional 50 MW at Dorothy, and project financing and binding leases at both campuses.

"Our priorities now are securing definitive leases, arranging project financing and advancing both projects toward delivery," CEO John Belizaire said in the release.

What Happens Next

The next on-the-record milestone is the closing of the Dorothy 3 joint venture with Applied Digital, which Soluna expects by the end of 2026. Separately, the additional 50-MW request at Dorothy is under study, and the release gives no date for a decision. Construction is underway at both Kati 2 and Dorothy 3, which began in October according to the release. Converting the Kati 2 and ChronoScale LOIs into binding leases, and arranging project financing, are the remaining steps. The release gives no schedule for either.