Voters in Coweta County, Georgia, will decide on Jan. 12, 2027 whether to reverse the county's approval of Project Sail. Developer Atlas Development, LLC has proposed the campus southwest of Atlanta, and its regional-impact filings put its value at about $17 billion. The same ballot question asks whether data centers should be removed as an allowed use everywhere in the county.

Coweta County Probate Judge Carrie B. Markham ordered the special election in a Nov. 23 order, Atlanta News First reported. Her order found valid a citizen petition filed under the home rule provision of the Georgia Constitution. WSB-TV described the provision as rarely invoked. In October WSB-TV reported that it found only two other times the provision had successfully been used in Georgia history. WSB said this could be the first time a home rule petition has been used to stop a data center development.

How the Petition Reached the Ballot

The dispute dates to April 2026. That month the Coweta County Board of Commissioners voted 3-2 to approve the rezoning for Project Sail, according to WSB-TV. The rezoning case is REZONE 24-019, and the board approved it on April 7, 2026, according to the ballot language quoted by Atlanta News First.

Under the home rule provision, a petition needs signatures from at least 10 percent of the county's registered voters, WSB-TV reported. Atlanta News First's account of the judge's order puts the threshold at 10,971 signatures, which is 10 percent of the county's 109,703 active electors in the last general election.

The petition was filed in Coweta Probate Court on Oct. 16. WSB-TV reported that more than 14,000 residents had signed it, and that the group Citizens for Rural Coweta was leading the effort. The number that counted legally was lower. On Nov. 20, the county's director of elections certified in a written report that 11,065 signatures were verified, according to Atlanta News First. That is 94 more than the minimum. Markham's Nov. 23 order found the petition valid.

What the Ballot Asks

The question is a single ballot question with two parts, based on the ballot text quoted by Atlanta News First:

  • Repeal of the rezoning. Voters will decide whether to repeal the Board of Commissioners' April 7, 2026 approval of REZONE 24-019, the Project Sail rezoning.
  • A countywide prohibition. Voters will also decide whether to amend the county code to delete data centers and data center campuses as permitted and conditional uses in all zoning districts, and to prohibit data centers, data center campuses, cryptocurrency data centers and cryptocurrency mining operations in all zoning districts of the county.

The second part reaches well beyond Project Sail. It would set a countywide land-use rule, not just settle the fate of one site. According to Atlanta News First, the county will pay for the election, and the court will declare and certify the results. The county's Elections Department will conduct the election using normal election equipment and precincts, according to the county's statement.

The Developer's Objection

Atlas Development filed an objection to the petition, which the court received on Oct. 23. Markham dismissed it in a separate order on Nov. 23, Atlanta News First reported. The order said the Georgia Supreme Court has made clear that no party has legal standing to object to a petition filed under that provision of the Georgia Constitution. The order also said the objection was not verified. Atlas representatives did not respond to Atlanta News First's requests for comment.

WSB-TV's October report named a different company, Prologis, as the developer of Project Sail and quoted a Prologis statement saying the petition "does not change our commitment to Project Sail." The Georgia Department of Community Affairs record and Atlanta News First name Atlas Development, LLC. The sources reviewed do not explain the difference.

What Project Sail Would Be

Project Sail went through Georgia's Development of Regional Impact (DRI) review. The process lets the regional commission and neighboring governments comment on large projects before local approval. The Georgia Department of Community Affairs record for Project Sail lists the following:

  • Coweta as the submitting local government
  • Atlas Development, LLC as the developer
  • Chattahoochee Flint RDC as the regional development center
  • Metro as the DRI tier
  • Georgia Regional Transportation Authority (GRTA) jurisdiction: yes

The DCA record gives this timeline for the review:

  • Dec. 31, 2024: initial and additional DRI information forms submitted
  • Jan. 21, 2025: state determination that the project "warrants regional review"
  • May 21, 2025: completeness certification and request for comments
  • June 10, 2025: regional development center issues its finding
  • June 20, 2025: projected process completion

The DCA lists the review's current status as completed.

Atlanta News First described the project as stated in the DRI filings. All of the following figures come from its report:

  • Buildings: 13 buildings of about 378,000 square feet each, plus substations
  • Location: listed as "Welcome To Sargent Rd & Wagers Mill"
  • Estimated completion: Dec. 31, 2036
  • Value at build-out: $17,161,900,000
  • Local tax revenue: an estimated $163 million per year
  • Water demand: 9.1 million gallons per day
  • Sewage flow: 3.03 million gallons per day
  • Solid waste: 800 tons per year
  • Water and wastewater provider: the Coweta County Water & Sewer Authority

The building count differs between sources. WSB-TV described a nine-building campus, while the DRI filing as reported by Atlanta News First lists 13 buildings. DataCenterFeed has not reviewed the detailed DRI forms, and the available sources do not explain the difference.

None of the sources reviewed for this article give a power capacity in megawatts or an employment figure.

The County's Position

The county has not said how it expects the election to affect the approved rezoning or any later permits. "Given the unique nature of this situation, we are still assessing its potential implications," Coweta County Government communications manager Cathy Wickey said in a statement reported by Atlanta News First. The statement added, "We anticipate that legal questions and challenges may arise among the entities involved."

The sources reviewed here do not say what legal challenges may be filed, who might file them, or how they would affect the election schedule.

Why It Matters Beyond Coweta

The petition uses a rarely invoked route. WSB-TV found only two earlier successful uses of the provision in Georgia's history, and it reported that this could be the first time a home rule petition has been used to stop a data center development. WSB-TV also reported that residents say their concerns extend beyond Project Sail, and that at least five data centers are in various stages of planning and development across Coweta County.

Because of the countywide part of the question, the ballot measure would apply to data center proposals across Coweta County as well as to Project Sail.

What Happens Next

The special election is set for Tuesday, Jan. 12, 2027, under Judge Markham's Nov. 23 order, as reported by Atlanta News First. The order directs the Board of Elections and director of elections to administer it under Georgia laws governing special elections. The county will pay for it, and the court will declare and certify the results. No court dates related to the election have been announced in the sources reviewed.