Digi Power X Inc. (Nasdaq: DGXX) reported third-quarter 2026 results on Nov. 13. The company has shifted from bitcoin mining toward AI and describes itself as an AI data center infrastructure operator. The release, filed with the SEC as Exhibit 99.1, centers on a 40-MW AI data center in Columbiana, Alabama, where Cerebras is the AI colocation tenant. According to the company, tenant access to the first phase is set for Dec. 15, 2026, and billing is expected to begin in January 2027.

The quarter's numbers show a company still between business models. Revenue was $12.25 million, which the company says is up 85% from the prior quarter and 50% from a year earlier. It ended the quarter with $119.6 million in cash, cash equivalents and digital currencies and no outstanding borrowings. None of that revenue came from the Cerebras lease yet. An analysis of the results by the financial news site Panabee also points out that cost of revenue was higher than revenue for the quarter.

The Columbiana Contract, by Phase

The company describes its agreement with Cerebras as a ten-year take-or-pay colocation contract, meaning the tenant pays for the contracted capacity whether or not it uses it. Digi Power X splits the deal into two phases.

Phase 1 (15 MW). According to the company's release, annual fees for Phase 1 are expected to average about $40 million per year over the ten-year term, for a total of about $402 million. Panabee's analysis puts the Phase 1 pricing at $195 per kilowatt per month, rising 3% a year.

Phase 2 (25 MW). The company says Phase 2 would add about $58.5 million in annual fees, "subject to satisfaction of various conditions." If both phases begin, the release says combined average annual fees would come to about $107 million per year and total contract value to about $1.07 billion. The company's own illustrative revenue table labels Phase 2 "conditional" and says it remains conditional, including on adequate financing.

That difference matters for anyone reading the headline numbers. The $402 million Phase 1 figure is the contract value for the first phase. The $1.07 billion figure assumes a second phase that has not yet met its conditions.

Panabee also notes a $12 million construction payment from Cerebras. According to Panabee, it is recorded as unearned lease revenue and is refundable in certain circumstances before the lease begins.

The Financing Gap

The company plans to use debt to help pay for the build-out. On Oct. 13, 2026, Digi Power X announced it had received a commitment letter from a major lending institution for $200 million in debt financing, syndicated by Goldman Sachs, to support the Columbiana campus. Baxtel's report on that announcement says the lender was not named. Baxtel also reports that the project is being built in two phases, 15 MW by the end of 2026 and 25 MW by the end of the first quarter of 2027, and that the company says the project remains on schedule.

The commitment is not a closed loan. The Q3 release says closing is "currently expected in Q4 2026, subject to definitive documentation and various conditions," including the lender's completion of its diligence. The company adds that "there can be no assurance that the financing will be completed on the anticipated terms or at all." According to the release, the loan is expected to be structured at a project special purpose vehicle level, with an unsecured company guarantee through project completion and other limited matters, and the proceeds are intended to support completion of the Columbiana project and related project costs.

The company's spending plans go beyond Columbiana. Digi Power X expects 2027 capital expenditures of about $350 million, primarily for roughly 10 MW of AI inference capacity and the completion of Phase 2 at Columbiana. The release says the company intends to fund this principally through customer deposits and prepayments and debt financing, including the proposed $200 million facility, together with cash on hand.

Inside the Quarter

According to the release, AI revenue was $5.66 million in the quarter, or 46% of the total, compared with no AI revenue a year earlier. The company reported net income of $1.0 million and said it was "materially supported by digital currency and warrant valuation gains." It reported adjusted EBITDA, a non-GAAP measure, of $0.6 million.

Panabee's analysis adds context the press release headline does not highlight:

  • Cost of revenue, including depreciation, was $14.65 million against revenue of $12.25 million. That is a gross loss of about $2.4 million; the release reports a GAAP gross loss of $2.41 million.
  • About $3.32 million of the quarter's revenue came from Cerebras-related equipment procurement, which Panabee describes as a point-in-time sale rather than recurring rent.
  • No Cerebras lease revenue had been recognized by quarter-end, because the facility had not commenced.

Taken together, more than a quarter of the quarter's revenue ($3.32 million of $12.25 million, or about 27%) came from that one-time equipment procurement for Cerebras rather than ongoing operations. The lease has not started billing.

The 2027 Target

Digi Power X's 2027 outlook calls for an annualized revenue run-rate of about $250 million to $300 million by the end of the third quarter of 2027, subject to adequate financing and market and other conditions. The release says about $143 million of that run-rate is supported by current operations and the Columbiana tenant agreement, and that figure includes the conditional Phase 2. Panabee cites the same $143 million figure. The company says the balance is expected to come from additional AI colocation and GPU capacity currently in development and in customer negotiations.

Put another way, the $143 million is a little more than half of the $250 million low end of the target, and it includes a Phase 2 that has not yet met its conditions. The remainder, according to the company, depends on capacity still in development and customer negotiations.

What Happens Next

The company has put three dates on the record. According to the Q3 release, Digi Power X expects to give its tenant access to the Phase 1 facility on Dec. 15, 2026 and to begin commissioning the liquid-cooling and power systems at that time. Phase 1 billing is expected to begin in January 2027, following commissioning. Work on Phase 2 is underway, and the company is targeting tenant access for Phase 2 in March 2027, subject to various conditions.

Columbiana, Alabama campus: financing and phase milestones
  1. $200 million debt commitment letter announced
  2. Phase 1 tenant access and commissioning expected
  3. Phase 1 billing expected to begin
  4. Phase 2 tenant access targeted
Dates as stated by Digi Power X. December 2026 and later dates are company targets, not completed events. Source: Digi Power X Form 8-K Exhibit 99.1. DataCenterFeed graphic.

Separately, the company says closing of the $200 million Goldman Sachs-syndicated credit facility is currently expected in the fourth quarter of 2026, subject to definitive documentation and the lender's diligence.