Two subsidiaries of WhiteFiber, Inc. that hold its NC-1 data center in Madison, N.C., signed a $300.0 million term loan credit agreement on Nov. 9, 2026, with Morgan Stanley Senior Funding, Inc. as administrative agent, according to a Form 8-K the company filed with the Securities and Exchange Commission. The filing says no money had been lent as of the report. The first draw depends on the campus's first 40 MW being ready and accepted by the customer.

The next day, WhiteFiber's third-quarter 2026 results release said that milestone had been reached. "NC-1 is now fully operational across all 40 MW of contracted IT capacity, and we have entered into a $300 million secured financing facility for the project," CEO Sam Tabar said in the release.

How the Loan Is Built

According to the 8-K, the borrower is Enovum NC-1 Bidco, LLC, and its parent, Enovum NC-1 Midco, LLC, is also a party. Both are indirect subsidiaries of WhiteFiber. Morgan Stanley Senior Funding is administrative agent, collateral agent, lead arranger and bookrunner.

The filing describes $300.0 million in total commitments, split into two parts:

  • a $200.0 million initial term loan, and
  • a $100.0 million delayed-draw term loan.

The 8-K says the proceeds will pay for Phase 1 construction and punch-list costs at NC-1 in Madison, fund reserves, and cover fees and expenses. The money may also fund permitted distributions to equity holders, subject to the agreement's terms.

The filing lists two interest options. Borrowings can bear interest at Term SOFR, with a 2.00% floor, plus 6.00%. Alternatively, they can bear interest at a base rate, with a 3.00% floor, plus 5.00%. The loans mature on the fifth anniversary of the initial funding. Starting with the quarter ending March 31, 2027, the borrower must repay 2.50% of the principal funded at initial funding each quarter.

Repaying early costs extra, according to the filing. Specified prepayments before the second anniversary of initial funding carry a make-whole premium. The premium is 2.00% from the second to the third anniversary and 1.00% from the third to the fourth, with none after that.

Who Is on the Hook

The loan is project debt. The 8-K says WhiteFiber, Inc., the publicly traded parent, does not guarantee it. The borrower and its parent, Enovum NC-1 Midco, grant security interests in substantially all of the borrower's assets, and the filing requires a mortgage on NC-1 as a condition to initial funding. Before initial funding, White Fiber Operating Partnership LP will be required to deliver an unsecured guarantee of Phase 1 completion, including cost overruns, and specified project carry costs.

The agreement also includes two financial covenants: a minimum debt service coverage ratio and a maximum ratio of debt to net operating income. Both are tested starting with the period ending March 31, 2027, according to the filing. A summary from the aggregator Rallies.ai, dated Nov. 10, reported the same main terms, including that the loans were unfunded and that the parent company gave no guarantee.

The Commissioning Delay Behind the Funding Condition

Because initial funding is tied to readiness and customer acceptance of the first 40 MW, the loan's timing depends on how fast the campus is commissioned. WhiteFiber's quarterly release says that process ran late. Switchgear-related commissioning issues pushed the NC-1 ramp past the company's August target. The release also says total development costs are expected to remain within the original budget range, near the upper end, pending reconciliation of final contractor and vendor invoices.

The release now describes all 40 MW of contracted IT capacity at NC-1 as online. The 8-K, filed when the agreement was signed, still lists customer acceptance of the first 40 MW as a condition for funding. Neither source says when the lenders will formally confirm that the condition has been met.

The Quarter in Numbers

WhiteFiber reported total third-quarter revenue of $24.0 million, up 19%, according to the release. Of that, cloud services brought in $18.1 million, including about $3.4 million in termination fees. Colocation revenue was $5.6 million, up 232%. The company reported an operating loss of $12.4 million.

Net loss was $101.4 million, or $2.44 per share. That figure includes $80.8 million of induced conversion expense tied to the company's 2031 convertible notes, which is the cost of persuading noteholders to convert early. Excluding that charge, the net loss would have been about $20.6 million, by DataCenterFeed's arithmetic.

The release also describes new contracts. WhiteFiber says it has signed more than $700 million of new cloud contract value with five customers since its August earnings call, and that it is expanding into Sydney and Dublin. The company says its signed cloud portfolio should generate about $365 million in annualized revenue once fully deployed, which it is targeting for mid-2027. It reported remaining performance obligations, meaning contracted revenue not yet recognized, of about $729.0 million at Sept. 30, 2026. These are company figures and targets, not audited results.

In the same release, WhiteFiber said it had closed its $60 million purchase of the NC-2/NC-3 site in Yadkin County, N.C. The company says the site has at least 60 MW of initial gross utility capacity, could reach about 200 MW within seven years, and is targeted to be ready for service in late 2027.

What Happens Next

The next step in the 8-K is the initial funding. It is scheduled within 30 days after closing, and the borrower can extend it twice, by 30 days each time. Before any money is lent, the borrower must have the NC-1 mortgage in place and must show readiness and customer acceptance of the first 40 MW.

After funding, the filing sets two more fixed dates. The first 2.50% quarterly principal payment applies to the quarter ending March 31, 2027. The debt service coverage and debt-to-NOI covenants are first tested for the period ending on the same date. The $100.0 million delayed-draw portion becomes available after initial funding and ends six months after it, and drawing it is subject to final completion of the first 40 MW phase, pro forma financial tests and other conditions.