The U.S. Energy Information Administration wants to start counting how much energy data centers use, one facility at a time. In a Federal Register notice filed Nov. 25 and set for formal publication Nov. 27 (Document 2026-24077), the agency proposes a new information collection, Form EIA-872, the Data Center Energy Consumption Survey. It would gather facility-level energy and operating data every year from U.S. data centers with a design capacity of at least 1 megawatt.

EIA gives its reason in the notice: no existing source comprehensively measures the end-use energy consumption of data centers. The agency notes that its Commercial Buildings Energy Consumption Survey (CBECS) most recently collected data from 2018. The notice invites public comment under the Paperwork Reduction Act, and comments are due Jan. 26, 2027. According to CASRAI's summary, EIA would then submit a formal information collection package to the Office of Management and Budget (OMB) for clearance.

Below is what the notice says, and what it leaves out.

Who would have to report?

The threshold is IT design capacity. According to the Federal Register notice, EIA will ask each company with at least one data center to identify a roster of its facilities, then provide data for each in-scope facility with an IT design capacity of at least 1 MW. The notice says facilities that may be in scope include:

  • enterprise data centers
  • colocation facilities
  • hyperscale facilities
  • edge data centers
  • what the notice calls "super intelligence (SI)" data centers
  • carrier hotels
  • network gateways
  • cryptocurrency mines

The notice adds that facilities that do not meet the definition and the capacity threshold would be excluded. Because cryptocurrency mines, carrier hotels and network gateways are on the list, the survey would reach past the traditional data center industry. The notice defines a data center facility as a dedicated building, buildings, or a clearly delineated or partitioned portion of a building whose primary purpose is housing computer servers and associated IT equipment, and says a facility may be a campus, meaning a multi-building complex where energy, cooling or power delivery infrastructure is functionally integrated or shared.

EIA estimates about 1,400 respondents, each filing one response per year, for a total of 1,400 responses, according to the notice.

Is it mandatory?

The Federal Register text does not say. CASRAI's Nov. 26 summary describes the notice as seeking OMB approval for "mandatory" facility-level reporting, but that wording is not in the notice itself. The notice says only that information on the form "is confidential by law" and will be used for statistical purposes. Until EIA says otherwise in the formal record, DataCenterFeed is treating the survey's legal status as unstated. Operators and trade groups that want it clarified can raise it during the comment period.

What the notice does make clear is the schedule. EIA will collect data annually for the previous reference year, and the notice says EIA will conduct the survey in 2027. CASRAI describes the first collection as covering reference year 2026.

What would it ask, and how would the data be protected?

The notice describes the collection as facility-level statistical information on energy consumption and energy-related physical and operational characteristics. It points to continuous IT loads, uninterruptible power supplies and complex liquid- and air-cooling systems as features that set data centers apart. EIA's earlier pilot work gives a sense of what that means in practice. In March 2026, the American Public Power Association reported that EIA was launching three voluntary pilot field studies on data center energy use. The pilot questionnaire covered energy sources, electricity consumption, site characteristics, server metrics and cooling systems. The pilots used web-based surveys in Texas and Washington state and in-person interviews in Northern Virginia and Washington, D.C. EIA identified 196 companies operating data centers across those regions, according to APPA.

Colocation providers and other multi-tenant operators have a specific reason to care about the next point. The Federal Register notice says EIA is not proposing to collect any confidential business information pertaining to the customers these facilities may serve. Under the Confidential Information Protection and Statistical Efficiency Act of 2018 (CIPSEA), the notice says, responses will not be disclosed in identifiable form without consent, and collected data will be published only in aggregate form.

That means residents and local officials hoping to learn the power draw of a particular campus near them should not expect EIA-872 to provide it: the notice commits to aggregate publication only. The notice says the survey is meant to fill a gap, since no source currently measures data center end-use energy consumption comprehensively.

What would it cost respondents?

EIA estimates the total annual burden at 12,200 hours across all respondents, according to the notice. The agency puts the associated cost at $1,158,268, calculated as 12,200 burden hours times $94.94 per hour. These are EIA's own estimates of the time and expense respondents would bear completing the form. They do not describe a federal program budget. The notice invites comment on whether EIA's burden estimate, including the methodology and assumptions behind it, is accurate.

Why now?

The notice's justification is short: comprehensive end-use measurement for data centers does not exist, and CBECS most recently collected data from 2018. The notice also says EIA is working to move all of its consumption survey programs from a multi-year to an annual publication frequency, and that EIA-872 will be the annual data collection component of commercial energy consumption statistics in 2027.

According to APPA's March report, EIA Administrator Tristan Abbey is prioritizing data collection efforts in the rapidly evolving energy sector. CASRAI's summary describes EIA-872 as the first federal statistical survey dedicated to facility-level energy consumption across large data centers. Taken together, the sources show regional voluntary pilots announced in 2026, a proposed national instrument in the Federal Register, and a collection scheduled for 2027.

The notice states that the data will be used to produce national statistics on data center energy consumption and electricity demand.

Who signed the notice?

The notice was signed Nov. 23, 2026, by Pushpal Mukhopadhyay, Director of EIA's Office of Statistical Methods & Research, and filed Nov. 25, 2026. It names Maura Bardos Chihil as the EIA Clearance Officer.

What Happens Next

Public comments on the proposed Form EIA-872 are due Jan. 26, 2027, according to the Federal Register notice. Comments, identified by "EIA-872: Data Center Energy Consumption Survey," go by email to the address given in the notice, and Maura Bardos Chihil is listed as the clearance officer. According to CASRAI, after the comment period EIA will review submissions, revise the instrument as necessary and submit the information collection package to OMB. The notice says EIA will conduct the survey in 2027. Operators of facilities with 1 MW or more of IT design capacity who want to raise questions about scope, burden or the definition of a data center facility can do so in that comment window, which the notice says also covers EIA's definition of a data center facility.