For the first time, New York's grid operator projects a statewide shortage of electric resources, not only shortages in its transmission-constrained downstate zones. The New York Independent System Operator's 2026 Reliability Needs Assessment (RNA) finds a statewide resource deficiency of about 225 MW starting in 2033, growing to more than 1,850 MW by 2036, according to the final report and to Utility Dive's Nov. 19 coverage.

New large loads are a main driver. The assessment's baseline includes about 2,700 MW of existing and proposed large loads, which the NYISO report breaks into 1,700 MW of computational data centers and 1,000 MW of industrial load. The report also models how the 2036 need changes if new planned data centers can cut their consumption at peak.

What the assessment found

The RNA is NYISO's look at whether the bulk power system will meet reliability criteria over the next ten years. In the 2026 edition, according to the NYISO report, the statewide deficiency starts at 225 MW in 2033 and rises to more than 1,850 MW in 2036.

The downstate shortfalls arrive a year earlier. Utility Dive reported that New York City is deficient by about 400 MW in 2032, growing to about 1,850 MW by 2036. The Lower Hudson Valley is short about 130 MW in 2032, growing to about 1,950 MW by 2036. FingerLakes1, which described the draft assessment on Nov. 15, called these transmission-constrained deficiencies. The NYISO report says transmission investments can help with these local needs but cannot resolve the statewide shortfall.

Utility Dive also reported that the ISO expects to rely on emergency operating procedures on about 3.5 days next year, rising to 21 days by 2036.

Three forces behind the gap

Utility Dive's account of the assessment points to three factors that together shrink the margin between supply and demand.

New large loads. Utility Dive reported about 2,700 MW of new large load by 2036, made up of roughly 1,000 MW of manufacturing and 1,700 MW of data centers. That matches the NYISO report's 1,000 MW industrial and 1,700 MW computational data center figures. FingerLakes1 reported that these large loads are concentrated Upstate and include semiconductor manufacturing, AI infrastructure, cryptocurrency operations and cloud computing.

Winter fuel limits on gas generation. According to Utility Dive, about 5,400 MW of gas-fired generation in eastern New York is modeled as unavailable at the winter peak, partly because of constraints on fuel delivery. FingerLakes1 reported that by 2036, winter accounts for about 40% of statewide reliability risk.

Retirements. Utility Dive reported that about 4,000 MW of aging generation is anticipated to leave the system by 2036.

The data center number in context

The 1,700 MW of computational load in the baseline is much smaller than the volume of projects asking to connect. FingerLakes1 reported that as of September, NYISO had 53 projects seeking interconnection for more than 14,000 MW of combined demand. The outlet stressed that these are proposals, not a forecast. The RNA baseline of about 2,700 MW of large load by 2036 is the amount the planning study actually assumes.

The gap matters for anyone reading the assessment. The shortfall in the report comes from a baseline with far less new load than the interconnection queue, and the queue figure is not a demand projection.

What if data centers can flex?

The NYISO report includes a flexibility sensitivity. It assumes that all new planned data center large loads, not counting those already in service, are flexible and curtailed at peak. Under that assumption, the 2036 resource need falls from about 1,850 MW to 850 MW.

The sensitivity does not assume data centers stop being built. It tests how much of the projected 2036 gap would close if the new facilities in the baseline lowered their consumption during the peak hours when the system is short. On NYISO's numbers, that would cover a little over half of the 2036 statewide need. The remainder of the modeled need would still have to be met by other means.

According to the NYISO report, data center loads may be able to reduce demand during stressed conditions if appropriate interconnection requirements, market mechanisms or contractual arrangements are established. The result is a sensitivity case, not part of the base case.

Why this assessment is different

Earlier New York reliability concerns centered on New York City and nearby zones, where limited transmission makes local supply critical. The 2026 RNA still finds those local shortfalls, now starting in 2032. It adds a statewide deficiency in 2033, which Utility Dive described as the state's first.

The findings come from a planning study, separate from NYISO's tariff and interconnection rules for large loads. DataCenterFeed covered those rules earlier in connection with the ISO's large-load filing at the Federal Energy Regulatory Commission.

What Happens Next

The RNA still needs approval from NYISO's Board of Directors. The NYISO report lists the next steps as a request for updates to the base case after Board approval, continued reform of the Reliability Planning Process, and the 2027-2036 Comprehensive Reliability Plan (CRP).

According to Utility Dive, if the projected shortfall persists, the ISO will solicit market-based backstop resources, and will evaluate proposed solutions in the 2027-2036 Comprehensive Reliability Plan. The sources do not give dates for the Board vote or for the solicitation.