Texas data center developers are heading into December without final answers on where their projects stand in the state's grid queue. Since early August, the Electric Reliability Council of Texas (ERCOT) has held back final decisions on its large-load interconnection process, known as Batch Zero, while it carries out a verification and audit of data center requests that Gov. Greg Abbott ordered. Two reports are due to state regulators by Dec. 10. The Public Utility Commission of Texas (PUC) is scheduled to meet on Dec. 17. A new governor takes office in January.
A Nov. 16 analysis by Latitude Media found that ERCOT has provisionally allowed about 200 projects totaling 66.4 GW to keep their place, has shut out more than 350 projects totaling over 300 GW, and has left nearly 170 GW waiting. The figures come from the publication's research arm, Latitude Intelligence.
This explainer covers what has been decided, what has not, and the dates on the calendar.
How the Queue Got Frozen
According to an ERCOT presentation to its Board of Directors for the board's Sept. 14-15 meeting, Abbott issued a directive on Aug. 3, 2026, ordering a "comprehensive verification and audit" of data centers before they could proceed. The same day, ERCOT issued a Market Notice that paused the Batch Zero study and delayed final classification. It also paused approvals to energize data centers and cryptocurrency mining facilities of 75 MW or more.
Batch Zero is ERCOT's process for studying a large group of big-load interconnection requests together. On Aug. 10, ERCOT asked the PUC for three good-cause exceptions to PGRR 145, the planning guide revision that governs the process. The board deck says the Commission granted all three on Aug. 20.
Utility Dive covered the Aug. 20 PUC open meeting and reported that about 300 data centers of 75 MW or larger are in Batch Zero. It also reported that ERCOT will run a separate community impact review covering data centers and crypto facilities of 25 MW and above. Citing Abbott's letter, Utility Dive reported that requests in ERCOT's queue total about 474 GW, and that roughly 90% of that is data centers.
Where the Numbers Stand
The September board deck sets out ERCOT's conditional classifications. Its key-takeaways slide says 204 projects totaling 66.4 GW are conditionally included as "base load," and 158 projects totaling 127.9 GW are conditionally included as "studied load." (A later chart in the same deck labels the studied-load group 125.4 GW.) Both categories are conditional. The deck says final classification was delayed when the study was paused, and that final inclusion or exclusion determinations will be provided in December.
Latitude Media's November count, which it rounds to about 200 projects at 66.4 GW, matches ERCOT's base-load figure. Latitude Intelligence puts the volume still waiting at nearly 170 GW, and the volume shut out at more than 300 GW from more than 350 projects. The deck's chart notes that it omits excluded load of 302.2 GW from 373 projects, which is broadly consistent with Latitude's shut-out figure, but the deck does not report a separate "waiting" category. Readers should treat the 170 GW figure as Latitude's analysis, not as an ERCOT classification.
The board deck also says the verification and audit will have a "TBD impact" on the Batch Zero timeline. Utility Dive reported that the delay could also push back ERCOT's long-term load forecast and reliability assessment.
What the Dec. 10 Reports Cover
The board deck lists two filings ERCOT will make with the Commission by Dec. 10, 2026:
- The Batch Zero Eligibility Verification Report. This is the audit Abbott ordered, covering the large-load requests in Batch Zero.
- The Community Impact Review Report. This report draws on requests for information that ERCOT sent to transmission and distribution service providers about medium data centers (25-75 MW), large-load data centers and crypto facilities.
At the August PUC meeting, ERCOT's Chad Seely said, "Our goal is to head toward a December 10 filing," according to Utility Dive. The outlet reported that the plan was to deliver a comprehensive verification report to the PUC a week before the Commission's December open meeting.
The Political Calendar
The election added uncertainty. Latitude Media reports that Democrat Gina Hinojosa won the governor's race and takes office Jan. 19, 2027. It also reports that Democrats took the statehouse, which creates a partisan split in the legislature for the first time in 25 years. Latitude notes that the Dec. 17 PUC meeting may be the last one held by the Commission in its current makeup.
Latitude quoted analysts at Jefferies who wrote that "the most plausible policy outcome is a legislative compromise" and that "the pause could be long." The analysts said they expect significant Texas data center construction in 2028 and beyond. Jefferies also said that wholesale futures power prices assume about 6 GW of grid-connected data centers per year. Latitude reported that shares of NRG and Vistra, two Texas power generators, fell 14% after the election. DataCenterFeed reports these figures as context and does not offer price or market forecasts.
Questions Readers Are Asking
Is a project with a conditional base-load classification approved to connect? Not based on the sources. The ERCOT board deck calls these classifications conditional, says final classification was delayed, and says energization approvals for data centers and crypto loads of 75 MW or more are paused.
Are smaller data centers affected? The energization pause in ERCOT's Aug. 3 notice applies at 75 MW and above. The community impact review is broader. Utility Dive reports it covers facilities of 25 MW and up, and the board deck describes information requests on medium 25-75 MW loads as well as large loads.
Does the audit change the Batch Zero schedule? ERCOT's deck lists the impact on the Batch Zero timeline as "TBD." Latitude Media reports that final Batch Zero classifications are due in December.
Who decides what happens after the reports are filed? The reports go to the PUC. The sources do not describe what action, if any, the Commission will take on them at its Dec. 17 meeting.
What Happens Next
ERCOT is scheduled to file the Batch Zero Eligibility Verification Report and the Community Impact Review Report with the PUC by Dec. 10, 2026, according to its September board materials and Latitude Media. The PUC meets on Dec. 17, which Latitude says may be the current Commission's last meeting in its present makeup. Latitude also reports that final Batch Zero classifications are due in December. Gov.-elect Gina Hinojosa takes office on Jan. 19, 2027.