For years, arguments over how much new grid capacity data centers require have mostly relied on peak demand forecasts. Virginia now has a second set of numbers to work with: how much of the existing grid is actually in use across a full year.

Under Chapter 612 of the 2026 Virginia Acts of Assembly, each Phase I and Phase II Utility in the state had to petition the State Corporation Commission (SCC) for approval of electric grid utilization metrics by Oct. 15, 2026. Latitude Media reported that Virginia's major investor-owned utilities, including Dominion Energy and Appalachian Power, have now disclosed how much their distribution systems are used through the year, and said the filings are the first to publicly quantify that utilization.

The results show a wide gap between average use and peak use. That gap is now at the center of a national debate over whether flexible loads, batteries and demand response can let utilities connect large customers such as data centers without building as much new infrastructure.

What the Filings Show

According to Latitude Media, Dominion reported annual utilization of 41% for the period from July 2025 to July 2026. During infrequent peak hours, the grid operates at an average of about 80% capacity, though that rate is higher or lower depending on location. Utility Dive, reporting on the filing Dominion's Virginia subsidiary made last month, put the figures this way: an average distribution load factor of 41%, with utilization peaking just under 80%.

Utility Dive also reported a transmission figure from Dominion's filing: median facility utilization of about 33%. Dominion said individual facilities may approach or exceed rated capacity during outages, demand peaks or significant power transfers.

Appalachian Power's numbers were lower. Latitude Media reported that the utility's annual utilization was 14%, rising to 54% during peak hours.

Those averages do not mean the unused share of the grid can simply be handed out. Distribution and transmission equipment is sized for the highest-demand hours, and a peak near 80% leaves limited headroom during those hours. Dominion itself said, as Latitude Media reported, that system-wide measurements can obscure differences among specific feeders, substations and geographic areas, and that the results should be considered alongside reliability, resilience, operational requirements and customer needs.

Latitude Media also reported that Dominion's transmission filings showed growing strain in northern Virginia. One metric, which counts how often the system is so constrained that "ordinary correction actions may not be sufficient," rose from eight events in 2023 to more than 172 so far this year, spanning 2,530 hours, nearly all of them in the data center corridors of Loudoun and Prince William counties. Dominion said this does not necessarily mean facilities are physically overloaded under normal conditions, but that contingency margins are shrinking.

What the Law Requires

Chapter 612 directs each Phase I and Phase II Utility to petition the SCC for approval of grid utilization metrics, according to the text of the act. The petition may include a request that the SCC consolidate it with the utility's integrated resource plan, if one is filed in 2026. Any proposed metrics must include the ratio of distribution system peak load to total distribution capacity, the ratio of current load delivered to total potential deliverable load, the percentage of kilowatt-hours lost on the distribution system, an analysis of constrained circuits, and an evaluation of distribution performance at system peaks.

The act has the SCC determine which metrics are approved and how they may be applied at the feeder and substation level. In approving them, the commission is to include, as appropriate, a timeline for each utility to increase grid utilization and a description of how the metrics may inform future requests for cost recovery on capital investments. The act also has the commission analyze, in its annual report, the potential for non-wires alternatives such as energy storage and virtual power plants to raise utilization.

According to Latitude Media, the Utilize Coalition's goal is not to stop utilities from building infrastructure but to give regulators the tools to determine when capital-intensive builds are truly necessary. Ian Magruder, the coalition's founder and executive director, told the outlet: "We've historically asked utilities to build for peaks. Now, we're shifting to say, peak remains important, but there's more we can get out of the system 8,760 hours of the year."

Disputes Over Dominion's Approach

Latitude Media reported that Dominion said the metrics should mainly serve as a screening tool to identify constraints, not a "deciding factor" for regulators weighing whether to deny capital expenditures. Deploy Action, a group that advocates for clean energy as an affordability solution and worked on the Virginia law, said in a statement that this reading conflicts with one of the legislation's core purposes. The group also said Dominion and Appalachian Power undervalued distributed energy resources and flexible demand in their metrics.

Dominion also asked Virginia regulators to observe data trends over three to five years before approving binding metrics, Latitude Media reported. Deploy Action argued that is too long given how fast demand is growing in Data Center Alley. Under Dominion's approach, the first year of numbers would serve as a starting baseline for that trend analysis.

The National Picture

The Virginia filings came out as utilities and technology companies discuss the same issue publicly. At the 2026 BNEF Houston Summit, in a panel covered by Utility Dive on Nov. 13, speakers offered several estimates of how much of the grid goes unused.

Google's Tyler Norris said estimated grid utilization rates run between 40% and 60%, Utility Dive reported. The publication also cited Grid Strategies' estimate, made late last year, that the systemwide load factor is about 60% and heading to 66% by 2030. Utility Dive said Grid Strategies defines load factor as the ratio of average energy usage to peak load.

These figures measure different things. Dominion's 41% is a distribution figure for one utility, and its 33% is a median across transmission facilities. Grid Strategies' 60% is systemwide, and Norris gave a range. Read together, they point the same way: much of the capacity built for peak hours is used well below its rating most of the time.

A Data Center Example From Oregon

The most concrete example raised at the panel came from outside Virginia. Norris cited an agreement between Aligned Data Centers and Portland General Electric in which the developer agreed to deploy a 31 MW/62 MWh battery for a 72-MW data center in Hillsboro, Oregon, to accelerate interconnection. "That allowed them to bypass what would have otherwise required a fully firmed network upgrade," Norris said, adding that "we will see more" of these arrangements, according to Utility Dive.

Norris also said large-load customers are eager to contribute flexible capacity if it lets them interconnect faster. Whether such arrangements will be accepted in Virginia is not addressed in the sources reviewed for this article.

Utility Dive also reported that NRG, a Texas-based independent power producer and retail energy provider, aims to deliver 25 GW of demand response, energy storage and virtual power plant capacity by 2035, according to Jessica Hogle, the company's vice president of federal affairs.

What the Metrics Do Not Settle

The filings are system-wide analyses. Molly Knoll of Align Energy Advisors told Latitude Media she is cautious about drawing insights from them in part because they provide limited information on localized constraints and conditions. The metrics therefore do not show whether a specific substation or transmission line has room for a specific data center, and the sources reviewed do not say how much of a large customer's load would have to be flexible or backed by storage to avoid an upgrade.

What Happens Next

Latitude Media described the filings as the beginning of a potentially years-long process by utilities, state regulators and other groups to finalize metrics. The petitions are before the State Corporation Commission, which under Chapter 612 determines which metrics are approved. The sources reviewed for this article do not give a hearing date or a deadline for a commission order. Dominion's filing asks for three to five years of trend analysis before binding metrics are adopted.

Sources