ISO New England has filed its proposal for connecting very large electricity customers to the six-state grid it operates. These are the data centers and industrial sites that could each draw as much power as a small city. According to the ISO's news service, ISO-NE, the New England Power Pool (NEPOOL) and the Participating Transmission Owners Administrative Committee (PTO AC) jointly filed the proposal at the Federal Energy Regulatory Commission, according to the ISO's Nov. 13 post. The ISO says the application and study process would be implemented June 1, 2027.
The filing is a proposal. FERC has not ruled on it.
Why ISO-NE Filed
The filing responds to a FERC order. The ISO's information summary, last updated Nov. 9, says FERC issued a Section 206 show-cause order on June 18 that covers five reform categories:
- an efficient study process
- cost transparency
- co-location rules
- flexible load service
- generation studies
The summary says FERC granted the ISO and the PTO AC abeyance so they could file their own proposal under Section 205 by Nov. 16, 2026.
New England is not the only region involved. AIxEnergy published a scorecard of the proceedings. It reports that FERC opened six Section 206 show-cause proceedings on June 18, 2026, docketed EL26-67 (PJM) through EL26-72 (ISO-NE). By AIxEnergy's account, five operators (PJM, MISO, CAISO, ISO-NE and NYISO) were due to respond Nov. 16, and SPP about Nov. 20. These dates come from secondary reporting, and readers should confirm them on FERC's eLibrary.
What Counts as a Large Load
ISO-NE's summary defines a Large Load as a single-site commercial or industrial customer with gross peak demand of 50 MW or more that interconnects above 60 kV. Existing loads and some critical loads are exempt. Growth can remove that exemption: an existing load becomes a Large Load if its gross peak demand rises 50 MW or more above its exempt demand as of June 18, 2026, the date of FERC's order.
The threshold is close to FERC's own suggestion. AIxEnergy reports that FERC proposed a 50-MW single-site load interconnecting above roughly 69 kV as a starting definition. ISO-NE's summary uses 60 kV.
Three Kinds of Service
The core of the proposal is three transmission service types. Each one gives a large customer a different deal on how firm its power is and what it has to wait for.
Firm contract demand service. The ISO Newswire account says this service requires new capacity and network upgrades. The ISO says it gives the customer the same priority as all other firm loads.
Interim contract demand service. The ISO describes this as non-firm service for customers working toward firm service. The information summary says it is temporary and lasts up to 7 years or until the needed upgrades are in service, whichever is longer. The service is provided for the requested firm amount until the designated capacity resources are designated and reach commercial operation, according to the summary.
Non-firm contract demand service. The ISO calls this a permanent option for flexible loads, meaning customers that can reduce consumption when the grid is stressed under certain conditions. The ISO says it does not require designation of new capacity supply and may require less extensive network upgrades.
The $250/MWh Trigger
The proposal states exactly when non-firm and interim customers would have to give way. According to ISO Newswire, the ISO would re-dispatch non-firm and interim customers whenever area energy prices reach $250/MWh. The ISO says the region crosses that threshold in about 1% of hours.
ISO Newswire says re-dispatch requires the customer to either reduce consumption or increase eligible generation, and that re-dispatching at this price is meant to instruct the non-firm customer to reduce demand before reliability risks arise from its lower level of network upgrades and lack of capacity supply. The ISO's figure of about 1% of hours describes how often the region currently crosses the threshold. The sources do not say how often it would happen once new large loads connect.
Capacity Accounting
The proposal also changes how these customers count toward New England's resource adequacy planning. ISO Newswire says non-firm and interim service would be excluded from the installed capacity requirement. The ISO's information summary says large loads are excluded from the Installed Capacity Requirement. ISO Newswire describes the installed capacity requirement as how much generating and demand-reducing capability must be procured through the region's capacity market.
One element is still open. ISO Newswire says stakeholder talks on a "bring your own new capacity" requirement will continue in 2027. The ISO's summary says large loads must bring their own new capacity, with exceptions, and the details remain under stakeholder discussion.
What It Means for Developers and Communities
For data center developers looking at New England, the filing sets out three service types that differ in firmness and in what a project must wait for. Firm service depends on new capacity and network upgrades. Interim service lets a project start before those upgrades are finished, for up to 7 years or until the upgrades are in service, whichever is longer, on the condition that it can be re-dispatched at the $250/MWh trigger. Non-firm service is a permanent option for flexible loads.
For utilities, local officials and residents, the 50 MW and 60 kV thresholds identify which projects this process covers. Under the ISO's summary, an existing load that grows 50 MW or more above its exempt demand becomes a Large Load. None of the terms are in effect yet. The June 1, 2027 implementation date is the ISO's proposed date and depends on FERC's review.
What Happens Next
The proposal now goes to FERC. According to AIxEnergy's scorecard, answers and protests are due 30 days after each operator's filing, so most comment windows close around Dec. 16. AIxEnergy also lists Nov. 16 filings from PJM, MISO, CAISO and NYISO in their own dockets, with SPP's response expected about Nov. 20. AIxEnergy is secondary reporting, so the docket dates should be confirmed on FERC eLibrary under EL26-72 for ISO-NE. Separately, ISO-NE says stakeholder discussion of the "bring your own new capacity" requirement will continue in 2027, and the proposed application and study process would begin June 1, 2027 as proposed.