Chaince Digital Holdings Inc. (Nasdaq: CD) said on Nov. 23, 2026 that its wholly owned subsidiary Chaince Compute Inc. had signed a binding Joint Venture Framework Agreement with Bitlakedata Inc. ("Bit Lake") to develop an AI and high-performance computing data center in Big Lake, Texas. The press release, which appears on SEC EDGAR as Exhibit 99.1, says the agreement was signed on Nov. 19.
According to the release, the first phase is 5 megawatts, and the most the project could reach under the framework is 25 MW. Nearly every step beyond signing depends on someone else: the utility AEP Texas Inc., a future anchor tenant, a pending interconnection application, and negotiations over prices that have not yet been set. Fazen Markets, a financial news site, calls the structure a template for the power-constrained AI buildout: taking an operating bitcoin mining site with energized capacity and converting the load to AI tenants.
What Was Signed
The release describes a framework, not a finished joint venture. Chaince Compute and Bit Lake expect to own the venture 60% and 40%, respectively. The two parties plan to form the joint venture and sign definitive documents, including an operating agreement, within 90 days of signing. If they don't, either party may terminate the agreement, according to the release.
Each side has a defined role. Bit Lake operates a bitcoin mining site in Big Lake with 15 MW of grid-connected power in service, according to Chaince's release. Chaince Compute will lead project financing and customer development, and each party will fund the venture in phases in proportion to its ownership. The release does not disclose a tenant, a purchase price, a capital budget or a construction schedule.
Fazen Markets, which says its summary was written by AI from the SEC EDGAR filing, and the aggregator Rallies both repeat the main terms: the Nov. 19 signing, the 60/40 split, a 5 MW first phase that depends on AEP Texas confirmation, and a path to 25 MW that depends on tenants and approvals. Fazen describes the deal as a binding framework rather than a built data center.
How the Power Is Supposed to Work
Power is the core of the deal, so it helps to follow it step by step through the release.
Phase 1 (5 MW). Chaince says 5 MW is currently available to contribute to the joint venture for the first phase. That depends on written confirmation from AEP Texas, which the release describes as the electric transmission and distribution utility serving the area, that a separate parcel can be served by that capacity. The parties will arrange Phase 1 power supply separately, including a joint-venture meter under Bit Lake's existing Peridot Power supply agreement, according to the release. In practice, the data center would draw on an existing supply agreement through its own meter, provided the utility confirms the new parcel can be served.
Expansion (up to 25 MW). According to the release, the venture could grow in two more blocks:
- 10 MW of existing mining load bought from Bit Lake's existing shareholders at a negotiated price. That purchase would happen only once an anchor tenant and schedule for Phase 2 are confirmed.
- Another 10 MW bought from BitRealm Inc. at a negotiated price, once AEP Texas approves the pending interconnection application.
Rallies' summary describes the same order: a first phase of 5 MW that depends on AEP Texas confirming power availability for a separate parcel, a 10 MW expansion through the purchase of existing mining capacity after a Phase 2 anchor tenant and schedule are confirmed, and another 10 MW from BitRealm.
The first expansion block would convert load that now runs mining equipment; the release says Bit Lake would phase out mining and switch the power to the data center. The second depends on a utility approval that the release does not say has been given. Neither block has a disclosed price.
Land and Legal Conditions
The release says the joint venture plans to buy land near the existing mining site, subject to AEP Texas's written confirmation that the parcel can be served by the first-phase capacity and to clearance from Texas counsel under state law. The release does not give an acreage, a parcel location or a purchase price.
The "separate parcel" language matters. Phase 1 is not described as a data center placed inside the existing mining operation's footprint. It is a new parcel that the utility must confirm it can serve. Until AEP Texas confirms in writing, the release presents even the 5 MW figure as conditional.
Why a Mining Site
Chaince's release states the company's view that access to power has become a key constraint on new AI data center development. The release says Chaince Compute plans to focus on small and mid-sized AI data centers in the United States, using modular construction and diversified power sources. Big Lake is its first announced project, and the company intends to apply the same model, partnering with holders of power capacity, at additional sites.
The deal's structure reflects that view. Bit Lake brings 15 MW of grid-connected power in service, an existing supply agreement, and mining load that its shareholders would sell to the venture. The company says that, if AEP Texas confirms the parcel can be served, it believes this can shorten the path to a first operating facility compared with projects that must first secure new grid capacity. That is the company's belief, not an outcome the release reports. Whether capacity can actually be moved to an AI workload depends on the AEP Texas confirmations and approvals described in the release.
What Is Not Disclosed
Several items that usually appear in data center deal announcements are absent from the release:
- No anchor tenant or customer is named. The release makes the first 10 MW expansion contingent on one.
- No prices are given for the mining-load purchase or the BitRealm capacity. Both are described as negotiated.
- No capital cost or construction timeline is stated, although Chaince Compute is to lead project financing.
- No acreage or building size is given for the planned land purchase.
What Happens Next
According to the release, the next stated milestone is the 90-day window that began with the Nov. 19 signing. In that period, Chaince Compute and Bit Lake plan to form the joint venture and sign definitive documents, including an operating agreement. If that does not happen, either party may terminate the framework. Phase 1 separately depends on written confirmation from AEP Texas that the separate parcel can be served by the 5 MW. The land purchase depends on that same confirmation and on clearance from Texas counsel. The release gives no date for the utility's response or for a decision on the pending interconnection application tied to the BitRealm capacity.