CleanSpark, the bitcoin miner that is moving into leased data center capacity, used its fiscal fourth-quarter results on Nov. 24, 2026 to give an update on three groups of sites: a build-to-suit campus in Sandersville, Georgia; two newly acquired sites in Texas; and an expanding site in Washington, Georgia. The results release, filed with the Securities and Exchange Commission as Exhibit 99.1 to a Form 8-K, describes a signed 20-year lease at Sandersville that the company says is fully funded. It also discloses that exclusivity at the two Texas sites expired before a tenant was signed.
Below is what the filings say about each site, what they leave out, and the next dated milestone.
Sandersville: a signed lease, financed by secured debt
The release says CleanSpark signed a 20-year triple-net lease at Sandersville worth $6.6 billion with a tenant it describes only as "high investment grade." Under a triple-net lease the tenant usually pays property taxes, insurance and maintenance on top of rent. The release does not name the tenant or state the lease's capacity in megawatts. The company's Form 10-K, however, describes the lease as covering 175 MW of critical information technology load, with two five-year extension options.
The project's construction counsel, Holland & Hart, described Sandersville in a Sept. 24, 2026 note as a build-to-suit data center campus in Washington County, Georgia, built for a single high-investment-grade tenant on a 20-year lease representing about $6.6 billion in contracted revenue. The firm said the lease was announced in July 2026, that CleanSpark will deliver 175 MW of critical IT load, and that initial deliveries are expected in the fourth quarter of 2027. It also said it drafted the construction agreements.
CleanSpark's release says the project is fully funded by $2.276 billion of 7.875% senior secured notes due 2031. A Unite.AI summary of a Sept. 25, 2026 8-K filing adds more detail. According to that summary, subsidiary CSDC Finance I, LLC closed the $2.276 billion private offering with the notes issued at 98.500% of principal, under a Sept. 18 purchase agreement with Morgan Stanley & Co. LLC acting as representative of the initial purchasers. The summary says the proceeds will pay the remaining cost of Sandersville, reimburse earlier equity contributions and fund debt service reserves. It also says the notes carry first-priority liens and are backed by a completion guarantee from the parent company.
The release lists several steps the company says are done:
- The basis of design is aligned on 100% of the anticipated project.
- The development contract is turnkey and lump-sum, with the company's engineering, procurement and construction management general contractor.
- Long-lead items have been prepaid.
- All material building and development permits (zoning, building, drainage and others) have been obtained.
The release says construction is on track for the first planned data hall in November 2027.
The company's Form 10-K for the fiscal year ended Sept. 30, 2026 adds risks to that picture. Its risk factors say CleanSpark depends on a third party to lead construction at Sandersville, and also depends on outside parties for equipment supply, regulatory approvals and electrical power. The 10-K also says the company incurred significant additional indebtedness to fund the project.
Texas: Batch Zero status, but no exclusivity
The release says CleanSpark bought two Texas sites: Sealy, at 285 MW, and Brazoria, at up to 600 MW. Both received designations under the Electric Reliability Council of Texas (ERCOT) "Batch Zero" process.
- Conditional Batch Zero Baseload: 585 MW in total, made up of 285 MW at Sealy and 300 MW in Brazoria Phase 1.
- Conditional Batch Zero Studied Load: Brazoria Phase 2, up to 300 MW.
The release also says CleanSpark received permits from the Texas Commission on Environmental Quality (TCEQ) for the Brazoria project.
The release also says that the exclusivity period at both Sealy and Brazoria expired during what it calls a period of temporary regulatory uncertainty. It says commercialization efforts are proceeding with the existing Sandersville tenant and others. That means no exclusive arrangement is described for the Texas sites, and the release does not report a signed lease for either one. The release does not identify the regulatory uncertainty beyond that phrase, and this article does not guess at it.
The labels matter. In the company's wording, the designations are conditional, and Brazoria Phase 2 is "studied load" rather than baseload. Taken together, the Texas sites as described are acquired sites with Batch Zero designations and, at Brazoria, TCEQ permits. They are not contracted data center revenue.
Washington, Georgia: energized capacity and more land
At its Washington, Georgia site, CleanSpark says 86 MW of grid-connected power is energized. The release says the company submitted a high-density line study and that preliminary results indicate the ability to support up to 500 MW of transmission capacity over the next several years. It also says the company acquired 500 adjacent acres to support a future AI data center campus. The release gives no tenant, lease or construction schedule for any expansion. The 500 MW figure comes from preliminary study results and is not committed capacity.
On portfolio size, the sources differ by date. The Nov. 24 release says CleanSpark controls a portfolio of up to 2.1 GW of power, land and data centers across the United States, while the Unite.AI summary of the September filing cited more than 1.8 GW.
The financials
According to the release, revenue was $120.9 million in the fiscal fourth quarter and $576.5 million for the full year, down 46% and 25% respectively from a year earlier. CleanSpark reported net income of $9.8 million for the quarter and a net loss of $987.1 million for the year.
The release puts year-end liquidity at approximately $1.3 billion, made up of approximately $204.8 million in cash and cash equivalents and approximately $1,130.5 million in bitcoin holdings, including bitcoin pledged as collateral. The release's headline bullets describe more than $1 billion in liquidity. The release includes statements from CEO Matt Schultz and CFO Gary Vecchiarelli.
Much of that liquidity is held in bitcoin rather than cash, and the Sandersville notes were issued by a subsidiary, CSDC Finance I, LLC, and are secured, according to the Unite.AI summary. Readers comparing CleanSpark's balance sheet with the lease commitment should keep both facts in mind. This article makes no assessment of the company's securities.
What the sources do not say
The filings and summaries reviewed here leave several questions open:
- Who the Sandersville tenant is.
- How many data halls follow the first one at Sandersville, and when.
- What regulatory uncertainty caused the Texas exclusivity to lapse.
- Whether any lease talks for Sealy or Brazoria have reached signed terms.
None of these details appear in the public record that DataCenterFeed reviewed.
What Happens Next
The next scheduled, on-the-record milestone is the first Sandersville data hall, which CleanSpark's release says is planned for November 2027. The notes funding the project mature on Oct. 1, 2031, according to the Unite.AI summary of the September 8-K. For the Texas sites, the release says commercialization is continuing with the Sandersville tenant and others but gives no deadline. For the Washington, Georgia expansion, it cites preliminary line-study results pointing to up to 500 MW over several years, with no dated step.
Sources
- CleanSpark 8-K Exhibit 99.1: Fiscal Fourth Quarter and Full Year 2026 Results (Nov. 24, 2026)
- CleanSpark Form 10-K for fiscal year ended Sept. 30, 2026
- Unite.AI: CleanSpark Closes $2.276B Senior Secured Notes for Georgia Data Center
- Holland & Hart: Holland & Hart Represents CleanSpark on $6.6B Sandersville Data Center Campus Construction (Sept. 24, 2026)