Vodafone Group used its first-half fiscal 2027 results on Nov. 10, 2026 to set out data center plans in three markets. In Kenya and Ethiopia, Safaricom is due to grow from 9.1 MW of current capacity to 35 MW. In Egypt, a joint venture is planned to reach 200 MW. In Türkiye, a 50:50 venture with DAMAC Digital has opened Vodafone's sixth sovereign data centre there.
The figures come from one slide in Vodafone's H1 FY27 results presentation, titled "targeted data centres investments." The written results announcement mentions the strategy only in general terms. Trade publication DatacenterDynamics (DCD) reported the Safaricom expansion on Nov. 27 under a headline saying Vodafone would triple Safaricom's data center footprint. On the deck's own numbers, 35 MW is a little under four times the current 9.1 MW.
What the Filing Says, and What Only the Deck Says
The SEC copy of the results announcement (a Form 6-K dated Nov. 10, 2026) contains two passages on data centers. The first says: "We are also making targeted investments in data centres in Egypt, Kenya and Türkiye, with our sixth sovereign data centre recently opened in Izmir." The second says: "In September 2026, we launched our sixth data centre with an initial 4MW capacity, scaling to 20MW."
The 6-K does not contain the Safaricom 35 MW figure, the 200 MW Egypt figure or the DAMAC Digital name. Those details appear only in the results presentation (page 24 of the deck). Every project-level figure below is attributed to that deck or to DCD.
Kenya and Ethiopia: Safaricom
The presentation lists Safaricom, which operates across Kenya and Ethiopia, with two central data centres, 9.1 MW of current capacity and 35 MW planned. The deck describes the result as one of Kenya's largest data centre footprints, providing sovereign AI and, going forward, GPU-as-a-service.
According to DCD, Safaricom's current 9.1 MW is spread across six facilities in Kenya and Ethiopia, and the 35 MW is planned across two central data centers. DCD said Vodafone gave no further project details and did not say how the capacity would be split between the two countries. The deck also gives no locations, timelines or capital costs for the Safaricom build-out.
DCD's report also quoted Vodafone's statement that Vodafone Business service revenue rose 40% organically in the results.
Egypt: A 200 MW Plan in a Three-Party Venture
For Egypt, the presentation describes a joint venture with El Sewedy Electric and Cassava Technologies. Vodafone holds a 30% equity stake. The deck lists 20 MW of initial capacity and 200 MW planned, and describes the venture as Egypt's largest data centre, providing cloud services, while separately developing Egypt's first sovereign AI data centre. Of the three markets on the slide, Egypt has the largest planned figure. The deck gives no site, timeline or investment amount for the Egyptian venture.
Türkiye: DAMAC Digital JV and the Izmir Site
The Türkiye entry in the presentation is a 50:50 joint venture with DAMAC Digital, with an initial investment of US$100 million, 4 MW of initial capacity and 20 MW planned. The deck says the sixth sovereign data centre opened in September 2026, that its first customers are live, and that agreements cover more than 50% of its capacity. A footnote on the Türkiye entry reads "Off-balance sheet joint venture."
The 6-K backs the Izmir opening and the 4 MW-to-20 MW figures. It places the sixth sovereign data centre in Izmir and says it launched in September 2026 "with an initial 4MW capacity, scaling to 20MW." The filing does not name a partner. DAMAC Digital's role is stated only in the presentation.
The Safaricom Ownership Dispute
The Safaricom plans come while a legal dispute over who controls the operator is still open. According to Vodafone's results announcement, Vodacom announced on June 30, 2026 that it had completed the purchase of an effective 20% stake in Safaricom. That stake was made up of 15% bought from the Government of Kenya for KES 204 billion and 5% bought from Vodafone for KES 68 billion. The deal raised Vodacom's holding to 55%.
The announcement says Kenya's High Court declared the transaction null and void on Sept. 15, 2026. On Oct. 13, the Court of Appeal in Nairobi ordered that the status quo be maintained pending its determination. Under that order, Vodacom remains the registered holder of the Safaricom shares acquired from the Government of Kenya, and the related purchase consideration is held by the Government of Kenya, pending the hearing of the appeal. DCD described the acquisition as in limbo after the High Court ruling, with the appeal ongoing.
Neither Vodafone's materials nor DCD's report says whether the court case affects the timing of the Safaricom data center expansion.
Reading the Slide
The three markets on the slide use three different structures:
- Kenya and Ethiopia: capacity built through Safaricom, an operating company in which Vodacom's stake is under legal challenge. Current 9.1 MW, planned 35 MW, per the deck.
- Egypt: a minority (30%) stake in a three-party venture. Initial 20 MW, planned 200 MW, per the deck.
- Türkiye: an equal partnership with DAMAC Digital and a stated US$100 million initial investment. Initial 4 MW, planned 20 MW, per the deck. The Izmir opening and its 4 MW-to-20 MW path are also confirmed in the 6-K.
Only the Türkiye venture has a stated investment amount. Only the Türkiye venture has an operating site with named contracted demand: agreements for more than 50% of capacity, per the deck. In Kenya, Ethiopia and Egypt, the planned figures are not tied to stated budgets or completion dates in any of the sources reviewed.
What Happens Next
The next on-the-record step is the Court of Appeal hearing in Nairobi on Vodacom's Safaricom stake purchase. Vodafone's results announcement does not give a date. Until the court rules, the Oct. 13 status quo order stands: Vodacom remains the registered holder of the shares acquired from the Government of Kenya and the Government holds the related consideration. Vodafone has not published a schedule for the Safaricom, Egypt or further Türkiye capacity listed in its H1 FY27 presentation.