Nasdaq-listed Nocera has signed a binding letter of intent to invest about US$22 million in cash in Calgary-based BitRock Ltd. In return it would get roughly a 44% stake in a company planning a natural-gas-powered AI data center near Hanna, Alberta. Nocera disclosed the deal in a press release dated Nov. 23, 2026, filed as Exhibit 99.1 to a Form 8-K. The release says the LOI was fully executed on Nov. 19.
The deal is small by hyperscale standards. It matters because of where the power would come from. BitRock plans to run the site on generation it says it owns, not on a new grid connection. That puts the project in the lane Alberta's government says it favors for data centres, at a time when the grid operator reports that the province's interim allowance for large loads is fully allocated.
The Terms
According to Nocera's filing, the company would pay about US$22 million in cash for newly issued BitRock shares. The release puts BitRock's pre-money valuation at about US$28 million and its post-money valuation at about US$50 million. That works out to the roughly 44% stake Nocera describes ($22 million of $50 million). The release also says Nocera would have the right to appoint directors to BitRock's board.
The filing says the proceeds would go solely toward BitRock's first data center in Alberta, a facility of about 10 MW of IT load. Nocera describes the LOI as binding. Funding is still subject to due diligence, a definitive agreement and the necessary approvals. The release says the LOI term runs 60 days from signing and can be extended by 30 days by mutual written consent. It also says the arrangement is non-exclusive and that the transaction may not be completed.
The Hanna Project as Described
All project details below come from the Nocera release and are statements by BitRock and Nocera. The release says they are based on information provided by BitRock and have not yet been independently verified by Nocera. None of them come from an independent regulator or permitting authority.
- Site: About 37 acres near Hanna, Alberta, according to the release.
- First phase: About 10 MW of IT load, built from four prefabricated modules of about 2.5 MW each.
- Long-term plan: The release cites an eventual buildout of about 200 MW, added in 10-MW units as customer demand warrants. The release calls this a long-term objective, not a commitment.
- Efficiency and redundancy: According to BitRock, the campus is designed to a power usage effectiveness (PUE) target of about 1.225, with N+1 redundancy.
- Business model: Colocation, according to the filing, with customers installing their own computing equipment.
- Power: Natural-gas generation that BitRock owns. The release says BitRock represents that it owns the generation equipment and has obtained the permits required to generate and supply electricity in Alberta.
- Customers: The release says BitRock represents that customers have signed memoranda of understanding for computing power hosting services. It does not name them. An MOU is a preliminary document, not a contract for capacity.
The 200-MW figure is a long-term plan. The Nocera investment, as described, would fund only the first 10-MW phase.
Why the Power Arrangement Matters in Alberta
The Alberta Electric System Operator (AESO) says on its Large Load Projects page that Phase 1 of its Large Load Integration program is complete. It also says all 1,200 MW of its interim connection limit has been allocated. AESO lists two projects with executed load contracts: P2936, GLDC Load, at 970 MW, and P3083, Keephills Data Centre Phase I, at 230 MW. All other large-load requests now go to Phase 2 of the program. The page also lists a Phase 2A: Large Load Integration | BYOG Process session. AESO also posted a connection-requirements guide for transmission-connected data centres on June 12, 2026.
The provincial government's guidance points in the same direction. Alberta's page on AI data centres and electricity says a data centre must show it will not put grid reliability at risk before AESO approves a connection. It also says data centres pay for their own electricity and connection costs, and that in an emergency they must reduce their electricity use first. The province says it encourages data centres to build their own generation. It adds that under the Utilities Statutes Amendment Act, 2025, projects that bring their own power supply are prioritized.
That policy sits within Alberta's broader Artificial Intelligence Data Centres Strategy. The government says the strategy rests on three pillars: power capacity, sustainable cooling and economic growth. Its stated aim is to make Alberta the most attractive place in North America to build AI data centres. Under the power pillar, one stated objective is to prioritize both off-grid and grid-connected power solutions that avoid compromising the affordability and reliability of electricity.
BitRock's plan, as Nocera describes it, is to run the Hanna facility on its own natural-gas generation. Neither the filing nor the provincial and AESO pages reviewed for this article say whether the Hanna project has any application before AESO, or how it would be treated under the Phase 2 process.
What the Filing Does Not Establish
Several points are not settled by the public record. BitRock's claims about owning equipment, holding permits and having customer MOUs are its own representations, which Nocera repeats in its release. The release says diligence is a condition of funding. It does not give a construction schedule for the first 10-MW phase or a date when the first modules would be energized. It does not identify the colocation customers. It also does not say what happens to the project if the investment is not completed, beyond noting that the deal is non-exclusive.
What Happens Next
According to Nocera's filing, the parties have committed to execute a definitive investment agreement as soon as practicable. The LOI has a 60-day term from the Nov. 19, 2026 signing, and the term can be extended by 30 days by mutual written consent. Funding also depends on the completion of due diligence and the required approvals. Nocera states that the transaction may not be completed on the terms described or at all.