Nov. 16, 2026 is the date New York's grid operator set for itself to answer federal regulators on how data centers and other very large electricity users should connect to the state's transmission system. In an order issued Aug. 14, the Federal Energy Regulatory Commission put its large-load show cause proceeding against the New York Independent System Operator (NYISO) on hold for 90 days, after NYISO said it would use that time to prepare its own tariff proposal and file it on Nov. 16.

When this article was published, DataCenterFeed had not confirmed that the filing was submitted. The case is FERC Docket No. EL26-69-000, and anyone following it should check that docket for a NYISO submission dated on or before Nov. 16. This explainer covers what FERC ordered, what the abeyance order requires, and what NYISO showed stakeholders in July as the outline of its proposal.

What FERC ordered in June

According to FERC's Aug. 14 order (196 FERC ¶ 61,130), the proceeding began with a Show Cause Order issued June 18, 2026 (195 FERC ¶ 61,216). That order directed NYISO and the New York transmission owners to do one of two things: explain why NYISO's tariff remains just and reasonable even without certain provisions addressing large loads and co-located loads, or propose tariff revisions to address FERC's concerns.

On Aug. 3, NYISO, the New York Transmission Owners (NYTOs) and the Non-Incumbent Transmission Owners each filed a motion asking FERC to hold the proceeding in abeyance for 90 days. FERC granted the motions. According to the order, NYISO stated that, provided it secures approval from its Management Committee, to which it planned to present the final proposal on Oct. 28, 2026, and from its Board of Directors, it will submit a filing under section 205 of the Federal Power Act on Nov. 16, 2026.

The order sets a fallback. Responses to the Show Cause Order are due Nov. 16, 2026, and answers to those responses are due Dec. 16, 2026. If NYISO or the transmission owners submit a section 205 filing addressing FERC's preliminary findings on or before Nov. 16, the filing party's obligation to file a show cause response is suspended, and the proceeding stays in abeyance pending further FERC direction.

The two routes work differently. In a show cause response, NYISO would be defending or explaining its existing tariff. In a section 205 filing, NYISO proposes new tariff language, and FERC then rules on that language.

Who is filing what

FERC's order describes the work as split between the grid operator and the utilities that own the wires. According to the order, NYISO told FERC it presented proposals to:

  • replace its existing load interconnection rules with a new large-load study process;
  • design firm and non-firm transmission services for customers serving large loads;
  • develop co-located load provisions, including sunsetting NYISO's existing Behind-the-Meter Net Generation program;
  • prevent cost shifting; and
  • mandate large-load operational requirements.

The order says the NYTOs plan to propose tariff revisions on cost allocation and cost recovery, rate design for new transmission services for large loads, parts of the load interconnection study process they would be responsible for, and certain operational requirements. It also says the NYTOs will need to coordinate with the New York Department of Public Service and the New York Public Service Commission on mechanisms to prevent cost shifting. For data center developers, that split suggests the terms of a New York interconnection may not come from a single document: NYISO's filing addresses how large loads are studied and what kind of service they receive, while the transmission owners' filings address cost recovery, rate design and their part of the study process.

What NYISO showed stakeholders in July

The most detailed public view of NYISO's thinking is a July 23, 2026 presentation, titled "Large Load FERC Show Cause Order," given to the Electric System Planning Working Group (ESPWG), the Transmission Planning Advisory Subcommittee (TPAS) and the Installed Capacity Working Group (ICAPWG). NYISO marked it "for discussion purposes only" and asked for written feedback by July 27. It is not the final filing.

A 50 MW definition

NYISO proposed defining a large load as commercial or industrial load at a single site with a peak load of 50 MW or more, connected to the transmission system at a voltage above 69 kV. The presentation also described a separate "Sizeable Load" category for loads with a peak of 10 to 50 MW connected above 69 kV.

For comparison, the presentation says the current process applies to loads over 10 MW connected at 115 kV or higher, or 80 MW or more connected below 115 kV. A Feb. 9, 2026 legal alert from the law firm Harris Beach Murtha describes the same existing thresholds.

Firm and non-firm withdrawal service

The central design choice in the July draft is two kinds of service for large loads:

  • Firm Withdrawal Service, under which the load would be treated the same as other customers taking firm service, including having the same curtailment priority.
  • Non-Firm Withdrawal Service, which would carry a lower curtailment priority than firm service and be subject to a $200/MWh Mandatory Bid Cap, which the presentation describes as the mechanism by which these loads are interruptible or curtailed.

As the July draft describes it, a large load could choose a service it can be curtailed from, and the bid cap is the market tool NYISO proposed for carrying out that curtailment. The presentation also notes that non-firm service does not currently exist in New York.

Co-location

The July presentation also listed co-located load provisions, covering loads sited with generation. FERC's August order describes that piece of NYISO's plan as including a sunset of the Behind-the-Meter Net Generation program.

Why the queue matters

The Harris Beach Murtha alert gives a sense of the volume behind the proceeding. Citing NYISO, it says the NYISO interconnection queue included six large load projects accounting for 1 GW of demand in 2022, and 48 large load proposals totaling approximately 12 GW as of Dec. 31, 2025.

The firm's summary of NYISO's earlier reform principles includes more predictable study timelines, evaluation of how reliability impacts compound when many large loads are added, clearer processes for modifying a large load interconnection, and milestones for including large loads in NYISO's Reliability Planning Process studies and Short-Term Assessments of Reliability. Those goals were described in February, before FERC's June order. The order moved the effort onto a federal docket with a deadline.

The schedule so far

Taken together, the FERC order and NYISO's July presentation give this sequence:

  • June 18, 2026: FERC issues the Show Cause Order.
  • July 20, 2026: deadline for NYISO's resource adequacy informational report, per the NYISO schedule.
  • July 23, 2026: NYISO presents its discussion draft to stakeholders, with written comments requested by July 27.
  • Aug. 3, 2026: NYISO and the transmission owners file motions for a 90-day abeyance.
  • Aug. 14, 2026: FERC grants the abeyance.
  • Aug. 17, 2026: the original response date without abeyance, which NYISO's presentation said would move to about Nov. 16 under a section 205 process.
  • Oct. 28, 2026: NYISO's planned date to present the final proposal to its Management Committee, according to FERC's order.
  • Nov. 16, 2026: NYISO's planned section 205 filing date, and the response deadline if no filing is made.

What Happens Next

Under FERC's Aug. 14 order in Docket No. EL26-69-000, Nov. 16, 2026 is the deadline. If NYISO or the transmission owners file a Federal Power Act section 205 proposal on or before that date, the filing party's obligation to file a show cause response is suspended and the proceeding remains in abeyance pending further Commission directive. Otherwise, responses to the June 18 Show Cause Order are due Nov. 16, and answers to those responses are due Dec. 16, 2026.

The order also says the New York Transmission Owners plan to propose tariff revisions on cost allocation, rate design and operating requirements, in coordination with NYISO, stakeholders and the New York Public Service Commission. Readers should check Docket EL26-69-000 to see what was filed and on what date. The July presentation was a discussion draft, so the filed proposal is the document to read.