Sixteen Texas senators have put their names on a bill that would tie data center tax incentives and grid interconnection to how a facility cools its servers and whether it reports its water use. Senate Bill 338, captioned "Relating to data centers," was filed on Nov. 12, 2026 for the 90th Legislature, according to the Texas Legislature Online bill history.

The author is Sen. Charles Perry (R-Lubbock), who chairs the Senate Water, Agriculture and Rural Affairs Committee. The bill history lists 15 joint authors: Campbell, David Cook, Flores, Hagenbuch, Hall, Adam Hinojosa, Juan "Chuy" Hinojosa, Huffman, Hughes, Kolkhorst, Ligon, Parker, Paul, Paxton and Sparks. KLTV reported that fifteen Republicans and one Democrat signed on as authors.

SB 338 is a filed bill, not law. As introduced, it would take effect Sept. 1, 2027. Below is a walk-through of what the introduced text does, where it leaves room for the Public Utility Commission to set details, and what has been reported about it.

What counts as a data center under the bill?

The introduced text adds a definition to Tax Code Section 312.2042. A data center is a site with one or more facilities totaling at least 100,000 square feet that were built or adapted to house servers and related equipment and support staff. The proposed utility and water-permit provisions use the same 100,000-square-foot threshold. KLTV also described the bill as targeting sites with at least 100,000 square feet of facilities.

The definition turns on floor area, not electrical load. A smaller facility under 100,000 square feet would fall outside these provisions even if it draws a lot of power.

What would it require on cooling and water?

Most of the cooling and water requirements work through tax abatement agreements. Under the introduced text, a municipal abatement agreement with a data center owner or lessee would have to require the use of only a closed-cycle recirculating, dry, saline water or water-efficient cooling system, or a combination of them. The agreement would also have to include:

  • an estimate, filed with the Public Utility Commission of Texas (PUC) when the agreement is executed, of the facility's annual cooling-water needs and the anticipated water sources;
  • annual reports to the PUC, starting on the first anniversary of the date the data center begins operations, on the previous year's cooling-water use and sources;
  • a requirement that the owner or lessee pay the cost of remediating environmental harm to the property;
  • conveyance to the municipality of a permanent nonpossessory interest in the property that limits the facility to the approved cooling systems, unless the owner has already conveyed an interest to another taxing unit, a municipality or county under a Chapter 380 or 381 agreement, or a school district; and
  • compliance with any PUC standards limiting light and noise pollution or regulating the minimum distance of buildings from the site boundary.

The permanent nonpossessory interest is written to bind the owner's assignees and successors, so as drafted the cooling restriction would stay with the property rather than ending with a particular agreement.

Perry's office pointed to testimony at the PUC to explain the cooling requirement. According to the senator's release, published by the Gilmer Mirror, PUC testimony stated that data centers using traditional evaporative cooling consume approximately 3.8 times as much water for cooling as facilities using closed-loop systems. The release also said the PUC reported at the September hearing that only 155 of the 377 data center facilities it surveyed had provided timely responses to requests for water-use information.

How does it touch the grid?

The bill adds two sections to the Utilities Code. New Section 39.362 directs the PUC to require large-load customers at data centers of 100,000 square feet or more to register the facilities receiving service. New Section 39.920 directs the PUC to adopt rules requiring a registered data center customer, before interconnecting to the ERCOT transmission grid, to use an approved cooling system and to submit an estimate of its cooling-water needs and sources. After interconnection, the customer would report its cooling-water use and sources annually.

That makes cooling a condition of grid access, separate from tax incentives. A developer that never sought an abatement would still face the cooling requirement at interconnection, assuming the PUC rules work as the text describes.

The introduced text also covers enforcement. Section 39.920(f) directs the PUC to prohibit utilities from interconnecting a site that does not meet the cooling and documentation requirements. It also directs the PUC to require utilities to disconnect a customer's campus from the ERCOT grid if the customer uses a cooling system other than an approved one while interconnected, or fails to timely submit the annual documentation. KLTV described the same disconnection requirement.

What about light, noise and setbacks?

The light, noise and setback standards are less fixed in the introduced text. Section 39.920(g) says the PUC "may" by rule require data center customers to limit noise and light pollution and to locate facilities a minimum distance from the tract boundary. Section 39.920(h) says the PUC may bar or disconnect a site that does not comply with those standards. Abatement agreements would have to require compliance with whatever standards the PUC adopts. Perry's release describes the scope as statewide standards set by the PUC, including potential buffer zones and dark-sky requirements.

The release says the standards respond to concerns raised by Texans living near existing or proposed data center developments, including excessive noise and light pollution.

How would the 50% abatement cap work?

New Tax Code Section 312.204(a-1) would bar a municipality from exempting more than 50 percent of the portion of a data center's property value that is otherwise subject to abatement in any year covered by the agreement. Perry's release describes this as a cap limiting abatements to 50 percent of a facility's market value. KLTV reported the cap as 50% of the otherwise eligible property value.

The bill also sets consequences for non-compliance. Municipal abatement agreements would have to authorize the municipality to terminate the agreement if the owner or lessee fails to comply with a term. They would also have to require a penalty equal to all lost ad valorem tax revenue from the data center, plus interest, if the agreement is terminated.

The bill also reaches state-level school-tax incentives. It amends Government Code Chapter 403, which governs school-district agreements, so that for a data center the taxable value would be not more than 50 percent of market value. Either the governor or the school district could terminate an agreement if the applicant fails to comply with a data center term, after providing written notice and a 180-day period to cure and dispute the alleged failure. If an agreement is terminated, the state would recover a penalty equal to all lost ad valorem tax revenue from the project plus interest.

"Being open for business does not mean giving businesses a blank check," Perry said in the release.

What about construction and stormwater permits?

The introduced text adds two Water Code provisions. New Section 5.517 would require the Texas Commission on Environmental Quality to issue an emergency order requiring a data center to stop construction if the commission determines that it does not or will not comply with the PUC standards and rules tied to the stormwater construction general permit. New Section 26.054 would require applicants for that general permit to attest that they comply or will comply with the applicable PUC standards and rules, and would require the commission, after a hearing, to deny or suspend a discharger's authority if the data center does not or will not comply. KLTV similarly reported that state regulators could halt construction or deny or suspend certain stormwater-permit authorizations.

Where did this come from?

Perry's release says the bill follows a seven-hour Senate committee hearing in September at which lawmakers heard from state agencies, industry experts, local officials and members of the public. The PUC testimony on evaporative versus closed-loop water use, and the response rate to the PUC's water-use survey, are the specific findings the release cites from that hearing. According to KLTV, the bill covers cooling methods, water reporting, grid connections, tax incentives and construction permits.

What Happens Next

The bill history lists two actions, both on Nov. 12, 2026: filed in the Senate and received by the Secretary of the Senate. It shows no committee referral or hearing so far. The introduced text states that, if enacted as written, the act would take effect Sept. 1, 2027, and that the new PUC interconnection rules would apply only to data center sites interconnected to the ERCOT grid on or after that effective date. The tax abatement provisions would apply only to agreements entered into on or after the effective date, so existing agreements would not be covered.