Applied Digital says it has reached Ready for Service on the first data hall at its second North Dakota AI campus. In a press release dated Nov. 24, 2026, the company said it finished base-build commissioning for the first 75 MW of the initial 150 MW building at Polaris Forge 2 in Harwood, N.D. It also said it completed fit-out of the first 25 MW data hall there and reached Ready for Service on schedule.
Three days later, an investor presentation the company furnished to the Securities and Exchange Commission as an exhibit to a Form 8-K listed another 100 MW at Polaris Forge 2. The presentation puts that expansion on a separate line labeled as in negotiation and not yet signed.
Every capacity and revenue figure in this article comes from Applied Digital's own statements. Where an outside outlet repeated those figures, the article says so.
What "Ready for Service" Covers Here
Applied Digital's release describes a building delivered in pieces. According to the company, each 150 MW building is commissioned in two 75 MW phases, and each phase holds three 25 MW data halls that are tested and commissioned together. So the Nov. 24 milestone has two parts:
- Base-build commissioning is finished for the first 75 MW phase, which is half of the first building. The release says the base-build infrastructure for the full 75 MW phase has been tested and commissioned.
- Fit-out and Ready for Service are finished for the first 25 MW data hall in that phase.
The company said the remaining 50 MW "can now advance through fit-out and customer delivery." The release does not give a date for when those two halls will reach Ready for Service. It also does not say when work on the building's second 75 MW phase will be finished.
The release does not define "Ready for Service" beyond what it reports. It says the first hall's fit-out is complete and that the hall reached Ready for Service on the company's schedule. The release does not say when the customer will begin operating equipment in the hall.
The Tenant and the Lease
The company says the Harwood building is fully leased as part of the customer's 200 MW long-term lease at Polaris Forge 2. The release does not name the customer. In the November investor presentation, the Polaris Forge 2 tenant is described as an "investment-grade hyperscaler." TheEnergyMag, which covered the Tuesday announcement, also described the tenant only as an unnamed hyperscale customer.
Applied Digital's figures leave a gap that the release does not explain. The lease covers 200 MW, and the first building is 150 MW. The release does not say where the rest of the leased capacity will be built or on what timeline.
The release also says Applied Digital has more than $41 billion in contracted base-term lease revenue. TheEnergyMag reported the same $41 billion figure. That number is the company's own total across its contracts. It does not refer to Harwood alone, and it is not revenue the company has already earned.
Where Harwood Fits in the Portfolio
Applied Digital calls these campuses "AI Factories." The company says Harwood is the first Ready for Service achievement at its second AI Factory campus. It follows Polaris Forge 1 in Ellendale, N.D., where the release says Applied Digital has delivered 250 MW of operational critical IT load.
The investor presentation lists critical IT load under contract for each campus:
- Polaris Forge 1 (Ellendale, N.D.): 400 MW, with CoreWeave as the tenant.
- Polaris Forge 2 (Harwood, N.D.): 200 MW, with an investment-grade hyperscaler.
- Polaris Forge 3 (Center, N.D.): 300 MW, with a tenant the presentation calls a "high investment-grade hyperscaler."
- Delta Forge 1 (Louisiana): 300 MW, with a high investment-grade hyperscaler.
Applied Digital's figures for Ellendale show 250 MW delivered as operational critical IT load out of 400 MW under contract. Its figures for Harwood show 25 MW Ready for Service out of 200 MW under lease. Both comparisons use the company's numbers and stated categories. The release calls Ellendale's figure "operational critical IT load," while it describes Harwood's milestone as Ready for Service. The two terms may not mean the same thing.
TheEnergyMag's article also mentioned that Applied Digital recently secured a $300 million bridge loan for the Delta Forge 1 campus in Louisiana. That outlet labels its own text as AI-generated with editorial support. Its Harwood figures match the company's release.
The 100 MW That Is Not Signed
The investor presentation puts the possible Harwood expansion on a separate line from the contracted capacity. That line lists a 100 MW Polaris Forge 2 expansion as "In negotiation" and "Not yet signed," and a footnote says it is not yet contracted and that the values are estimates. The presentation shows 1,560 MW of contracted capacity and 1,660 MW in total if the expansion lease is signed. The 1,660 MW is the company's figure for a scenario that has not happened, not for capacity now under contract.
The presentation also says all of the capacity, with or without the expansion, would be delivered by 2028. It puts the investment-grade share at about 75 percent of contracted capacity and about 76 percent with the expansion; a footnote says that share is measured by contracted base-term lease revenue. The presentation does not say who the counterparty in the expansion talks is, when talks might end, or whether the expansion would need new buildings at Harwood. Until a lease is signed, the extra 100 MW is a negotiation and not a project.
For local officials and residents, the release and the presentation leave several questions unanswered. The company's figures are capacity numbers. Neither document gives acreage, site-specific water use, construction jobs, permanent jobs, or the power supply arrangements for the Harwood site.
What the Company Said
Chairman and Chief Executive Wes Cummins was quoted in the release. He said that "with our second campus now reaching Ready for Service on schedule, we're demonstrating that our execution model is repeatable." The release does not give operating details beyond the commissioning and fit-out milestones described above.
What Happens Next
Applied Digital says the remaining 50 MW in the first 75 MW phase of the initial 150 MW building can now advance through fit-out and customer delivery. That means the second and third 25 MW halls. The company's commissioning model calls for a second 75 MW phase, also made up of three 25 MW halls, to complete each 150 MW building. The release gives no dates for either step.
The investor presentation lists the 100 MW Polaris Forge 2 expansion as in negotiation and not yet signed. It shows contracted capacity delivering through 2028. Neither document says when the negotiation might conclude.