A Spain-based renewable energy developer is weighing a data center campus of up to 500 megawatts in San Diego County's rural East County, near Jacumba Hot Springs, about 70 miles east of San Diego. The project is called "Project ECO." The Jacumba Community Sponsor Group confirmed the proposal through county records obtained under the California Public Records Act. The developer, IGNIS, says it has not filed an application. A representative described the effort as a consultation with the county about what the permitting path would be.

No data center of any size exists in unincorporated San Diego County today. In a July 2026 report to the Board of Supervisors, county staff wrote that there are currently no data centers of any size in the unincorporated areas. The region has about 20 small data centers, most of them inside the City of San Diego.

What Has Been Proposed

ABC 10News reported that county records show Project ECO with an electrical load of up to 500 MW on 177 acres. The station said that is roughly four times the reported capacity of California's largest existing data center, which is in Santa Clara County.

Data Center Dynamics (DCD) reported that the site is at 1425 Carrizo Creek Road, north of Interstate 8, close to an existing substation and solar farm. According to DCD, site plans suggest two data center buildings and a battery energy storage system. DCD also reported that the site's owner is set to sell the land to Ignis Energy USA LLC. The outlet described IGNIS as founded in 2015, with more than 1 GW of owned generation capacity in operation or under construction and 10 GW managed in total across owned and third-party assets.

KPBS reported that the Jacumba Community Sponsor Group confirmed the proposal through county records obtained under the Public Records Act, and that a rough map of the proposed location was included in those records. According to KPBS, the project dominated discussion at the group's Nov. 9 meeting. KPBS also reported that the group's chair first heard about the plans after members of the Boulevard Community Planning Group were tipped off by a local landowner.

What the Developer Says

IGNIS representative Tahir Fazal told KPBS in an interview that the company is in the early phases of deciding whether to do the project. "We have not done an application, so this project right now is nothing more than a consultation to the county to assess what the permitting path will be, to assess whether there are any limitations that are in place for this project," Fazal said. He said IGNIS would do community outreach if it decides to pursue the project, and that he could not say when the company would take action on an application.

Speaking to ABC 10News by phone, Fazal described Project ECO as nothing more than a proposal to see whether it is feasible. He said "pushback is very reasonable."

How San Diego County Would Review It

The county's rules for a project like this are laid out in a memo the Deputy Chief Administrative Officer sent the Board of Supervisors on July 14, 2026. The memo answered a Jan. 14, 2026 Board direction to evaluate large AI data centers in unincorporated areas. It was written months before Project ECO became public and does not name it.

The memo's main points:

  • Discretionary permit required. A large data center would need a discretionary Major Use Permit and review under the California Environmental Quality Act (CEQA). The County Planning Commission votes to approve or deny Major Use Permits, and those decisions are appealable to the Board of Supervisors.
  • No applications yet. The county had received no complete data center Use Permit applications. Since the Board's January direction it had received one request for an Initial Consultation meeting, which the memo says is not a formal application but offers a preliminary review of a conceptual project.
  • Staff's chosen path. Staff said it intends to move forward with "Option 1." Under that option, the Planning and Development Services director would issue a Letter of Determination confirming that large-scale data center applications are processed as "Major Impact Services and Utilities" requiring a Major Use Permit, and staff would define data centers in the Zoning Ordinance. The other options, which include a new data center zoning ordinance, clarified legislative advocacy guidelines and an AI workforce program, would need Board direction.

A county spokesperson confirmed to KPBS that the project would ultimately need approval from the San Diego County Board of Supervisors. Under the process described in the memo, the Planning Commission decides on a Major Use Permit first, and the Board hears the matter if that decision is appealed.

ABC 10News reported that the county has flagged water availability as a major concern and wants the electrical infrastructure reviewed.

The Regional Context

Several nearby jurisdictions have already acted on data centers. ABC 10News reported that earlier in 2026 the City of San Diego and Escondido approved moratoriums on large-scale data centers, and the City of Poway passed an ordinance banning them outright.

The county memo also describes a 300-MW, 950,000-square-foot data center recently proposed in unincorporated Imperial County on a 75-acre site. According to the memo, the Imperial County Board of Supervisors adopted a 45-day moratorium on data centers on June 16, 2026.

Jacumba and Boulevard residents have opposed large energy projects before. KPBS reported that the two communities battled two solar and battery energy storage projects that the Board of Supervisors ultimately approved. Sponsor group chair Jeff Osborne told KPBS the group will represent itself at the table, will ask for representation, and hopes to hear from the supervisors soon on data centers.

Key Questions

Is Project ECO approved? No. IGNIS says it has not done an application, and county staff's July memo reported no complete data center applications.

Is Project ECO the Initial Consultation mentioned in the memo? The memo does not name the requester. IGNIS describes its own effort as a consultation to the county to assess the permitting path.

Who would decide? Under the process in the county memo, the Planning Commission would vote on a Major Use Permit after CEQA review, and its decision could be appealed to the Board of Supervisors. A county spokesperson told KPBS the project would ultimately need Board approval.

How was the proposal confirmed? The Jacumba Community Sponsor Group discussed the proposal at its Nov. 9 meeting and confirmed it through county records obtained under the California Public Records Act, KPBS reported.

What Happens Next

No hearing or vote on Project ECO has been reported, because IGNIS says it has not filed an application. Under the county process described in the July memo, a permit application would trigger a discretionary Major Use Permit review with CEQA analysis. The County Planning Commission would then vote, and its decision could be appealed to the Board of Supervisors. Separately, county staff said in its July 14, 2026 memo that it intends to issue a Letter of Determination classifying large-scale data centers as Major Impact Services and Utilities and to define data centers in the Zoning Ordinance. Any further policy options would need direction from the Board. IGNIS has said it would do community outreach if it decides to proceed.

Sources