A Blackstone-affiliated landlord has floated a 252-megawatt data center campus for a vacant former defense manufacturing site in Fridley, Minn., a first-ring suburb north of Minneapolis. City officials say the project is still only an idea. Link Logistics, the owner of the former BAE Systems property at 4800 East River Road NE, gave an informal presentation of the concept, which it calls "Project Sunflower," at a Nov. 5 joint work session of the Fridley City Council and the city's Housing and Redevelopment Authority (HRA).

No application has been filed. In an open letter posted to the city's website on Nov. 25, Mayor Dave Ostwald described the city's contact with Link as "informal conversations." He wrote that the Nov. 5 session was a presentation, not a hearing or a vote, and that no decisions were made there.

What Link Has Proposed

Blandin on Broadband, quoting reporting by Bring Me The News, puts the proposal at a 252-MW campus on the 41-acre site in the area known as Northern Stacks. The property has been vacant since BAE moved to Maple Grove in 2025. According to that account, the plan calls for two buildings totaling 676,000 square feet. The south building would carry 84 MW and the north building 168 MW.

Construction Review Online, in a Nov. 25 report, gives slightly more detail on the buildings. It describes the south building as a single-story structure of 225,500 square feet with 84 gross MW, and the north building as a two-story structure of about 451,000 square feet with 168 gross MW. It puts the total at about 676,500 square feet and 252 gross MW. The publication reports a total investment of $4.8 billion: about $2.4 billion from Link and $2.4 billion from a future tenant that has not been identified. It says the campus would be Fridley's first data center if the necessary approvals are secured.

The power would come from Xcel Energy. Both Blandin on Broadband and Construction Review Online say the plan includes a 4.3-acre substation on the site. All of these figures come from the developer's presentation as reported by those outlets. None has been reviewed or approved by the city or by a utility regulator.

The Site

The parcel has a long industrial history. Construction Review Online reports that it now holds about 561,000 square feet of industrial buildings. It says Gramercy Property Trust bought the property for $46.8 million in 2015 and that Blackstone subsequently acquired Gramercy. Blandin on Broadband's account says the facility sits on a former Superfund site and reports that the nearest homes are at least 2,000 feet away.

A data center is not the first use Link has raised for the property. According to the city, Link also approached Fridley in June 2026 about converting the site into a distribution center.

Link has also pointed to how many data centers already operate in the region. Per Blandin on Broadband and Construction Review Online, the company counts 55 data centers within 25 miles of the site, 10 of them hyperscale facilities.

What the City Has Said

Ostwald's letter is mostly about procedure. Its key points:

  • No application. The city has had only informal conversations with Link. No formal application has been submitted.
  • No NDA. The city has not signed a nondisclosure agreement, has not been asked to sign one and will not sign one. The mayor wrote that the city told the developer the process will be fully transparent.
  • Standard review if filed. If Link files an application, it would be reviewed under the zoning chapters of the City Code. It would also have to be in full compliance with the site's redevelopment requirements, including a formal environmental review.
  • Public process. Public notice and one or more public hearings would come before any council action.

The city says it is preparing a question-and-answer page on data centers. Its page on the proposal also lists the Nov. 5 agenda packet, draft minutes of the session, Link's presentation, a community benefits agreement proposal from Link, and an environmental assessment dated Aug. 21, 2026. DataCenterFeed did not review the contents of those documents for this article.

The Developer's Timeline

Link's own schedule, as reported by Blandin on Broadband, depends on several approvals. The company expects to complete environmental review in 2027 and start construction in 2028 if it secures approvals, which would lead to completion in 2030. Those dates are the developer's targets. The city has not adopted or endorsed them, and the formal review the mayor described would have to happen before any of them could be met.

What Happens Next

According to the city, there is currently no application on file, so no hearing or vote has been scheduled. The mayor's letter says that if Link files an application, the city will review it under the zoning chapters of the City Code, require it to be in full compliance with redevelopment requirements including a formal environmental review, and give public notice and hold public hearings before the council acts. The city says it is also preparing a data center Q&A page for residents.

Sources