The Arizona Corporation Commission (ACC) has finished one of the two big utility rate cases on its calendar. The other one, where a data center rate is on the table, is next. On Nov. 17, commissioners voted 4-1 to approve an amended order in Tucson Electric Power's (TEP) rate case, Docket No. E-01933A-25-0103. In a release dated Nov. 27, the Commission described one of the amendments in more detail: TEP and Commission staff must now define the triggers that would start cost-of-service studies for large-load users. The release notes that large-load contracts such as Project Blue, the data center project tied to a special TEP energy agreement, were not included in this rate case.
In the Arizona Public Service (APS) rate case, the Commission said in July that an administrative law judge's recommended order was expected by late November. The Commission's deadline to vote is Dec. 31. APS says it has proposed raising rates by more than 45% for extra-large energy users such as data centers. As of a Sept. 24 court hearing, the Project Blue agreement was still being challenged in court by Attorney General Kris Mayes.
The questions below cover what was decided, what was left open and what comes next.
What did the Commission approve for TEP?
The ACC said the vote came at its Nov. 17, 2026 Open Meeting after about six hours of deliberation. Commissioner Márquez Peterson cast the only vote against. According to the Commission, the decision sets an overall net revenue increase of about 10%, surcharges included.
The ACC said a typical residential customer on a basic plan may see a monthly bill increase of just under $13.00, or about 9.4%, bringing the average monthly bill to about $150. The Commission's release says the rate changes are effective Dec. 1, 2026.
The order also approves a new Annual Rate Adjustment Mechanism, or ARAM. The Commission said TEP's deadline to submit and publish its first Annual Update under the mechanism is Sept. 1, 2027. The ACC said TEP filed the case on June 17, 2025, and that a 14-day hearing was held between April 22 and May 12, 2026.
What changed through the amendments?
The Commission approved an amended version of the Recommended Order and Opinion. Its Nov. 27 release says several amendments introduced by Vice Chair Rachel Walden were approved, securing three protections for ratepayers:
- Return on equity. TEP's authorized return on equity was changed from 9.65% to 9.40%. The release says the amendment recognizes that TEP faces less financial risk under the new ARAM. It also said the 9.40% figure was supported by the Department of Defense and Federal Executive Agencies (DOD/FEA), whose analysis calculated a return on equity of 9.39%.
- Large-load cost-of-service triggers. A new ordering paragraph requires TEP and Commission staff to define triggering mechanisms for Cost of Service studies for Large Load Users. The release says large-load contracts such as Project Blue, which had a test year of Dec. 31, 2024, were not included in this rate case.
- Employee expenses. The amendment eliminated $546,258 in employee meal, entertainment and gift expenses from being recovered by ratepayers.
The release adds that Walden was the lone no vote on allowing TEP to recover trade association dues from ratepayers.
Why does the large-load paragraph matter?
A cost-of-service study estimates what it costs a utility to serve each customer class. Regulators use it to decide how much of the utility's revenue each class should pay. A rate case looks back at a "test year." The Commission's release states that large-load contracts such as Project Blue, with a test year of Dec. 31, 2024, were not included in this case.
The release says the cost-of-service studies will provide data the Commission needs to avoid cost shifts to residential customers and to determine what special rate classes or tariffs may be necessary for large-load electricity customers. The new ordering paragraph does not itself set rates for data centers or other large loads. According to the Commission's description, it requires TEP and staff to define the triggers that would start a cost-of-service study for large-load users. The release does not say when those triggers must be defined or what they will be.
Where does the Project Blue agreement stand?
The Attorney General's office said the Commission voted in December 2025 to approve the agreement between TEP and Beale Infrastructure for the Project Blue data center, and later denied the Attorney General's request for rehearing. KJZZ describes it as a 10-year energy service agreement. On Feb. 19, 2026, Attorney General Mayes announced an appeal in Maricopa County Superior Court. Her office argued that a provision letting TEP and Beale set electricity rate schedules between themselves violates the Arizona Constitution, which gives the Commission exclusive authority to set just and reasonable utility rates.
KJZZ reported that a Maricopa County Superior Court judge heard arguments on Sept. 24 on whether to grant a rehearing of the agreement. According to KJZZ, Mayes argues that the city of Tucson and others were denied due process and that the risk of costs shifting to existing ratepayers was ignored. The request also alleges a provision lets TEP and Project Blue approve rate changes without Commission approval. Commission attorneys say the section on future rate-setting includes a statement that the two entities must adhere to state law, which they argue shows Commission approval will be required. KJZZ reported that Judge Randall H. Warner discussed adding a stipulation to the contract that would make the approval requirement more clear, but did not issue a verdict on a rehearing. None of the sources cited here reports a ruling since then.
How does the APS case differ?
The APS case deals directly with how data centers are charged. The Commission said in July that key topics argued during the hearing include changes to APS's Extra High Load Factor rate, which applies to large-load users such as manufacturing companies and data centers, and authorization of a Formula Rate Adjustment Mechanism.
On its rate case page, APS says it has proposed a rate increase of over 45% for extra-large energy users like data centers. It also says its formula rate request would provide an annual process to ensure that other customers are not receiving cost increases associated with data center growth. APS says it filed the case in June 2025. That 45% figure is APS's proposal and has not been approved.
The Commission described the hearing record. The APS hearing ran 31 days, from May 18 to July 7, 2026, with more than 50 witnesses testifying and more than 300 exhibits admitted into evidence.
The two cases are not handling large loads the same way. In the TEP order, studies of large-load cost of service are a follow-up task for the utility and staff. In the APS case, the Extra High Load Factor rate that applies to large-load users is among the key topics before the Commission.
What Happens Next
TEP: The Commission's release says the rate changes are effective Dec. 1, 2026. TEP's deadline to submit its first Annual Update under the ARAM is Sept. 1, 2027. The order directs TEP and Commission staff to define triggering mechanisms for large-load cost-of-service studies. The Commission's release gives no date for that work. Documents in the case are in the ACC's eDocket system under Docket No. E-01933A-25-0103.
APS: In its July update, the Commission said the administrative law judge's Recommended Opinion and Order was expected by late November 2026. The deadline for the Commission to vote is Dec. 31, 2026. If the Commission approves, it said new rates are expected to go into effect sometime in early 2027.
Project Blue: The rehearing question argued on Sept. 24 was before Judge Randall H. Warner in Maricopa County Superior Court. KJZZ reported that he did not issue a verdict at that hearing.
Sources
- Vice Chair Rachel Walden Secured Three Important Ratepayer Protections in the TEP Rate Case (Arizona Corporation Commission, Nov. 27, 2026)
- ACC Votes on TEP Rate Case (Arizona Corporation Commission, Nov. 2026)
- Last attempt at rehearing Project Blue's energy service agreement rests on Maricopa County judge (KJZZ, Sept. 24, 2026)
- Attorney General Mayes Appeals ACC's Approval of TEP Data Center Deal (Arizona Attorney General, Feb. 19, 2026)
- What's Next in the APS Rate Case? (Arizona Corporation Commission, July 10, 2026)
- APS Rate Case 2025: Update (APS)