The Electric Reliability Council of Texas (ERCOT) has set out how it would limit the combined power draw of groups of large computational loads, such as bitcoin mines and other computing facilities, that could disconnect together after a single transmission fault. The approach was presented to ERCOT's Large Load Working Group on Sept. 17, 2026. It drew new attention on Nov. 29, when crypto-focused outlets linked one of the monitored groups to Riot Platforms' site in Corsicana, Texas.

None of the plans are in effect yet. ERCOT's presentation says large-load consumption has not yet reached a level at which the mitigation plans are active. CryptoSlate reported that the plan covering the group that includes Corsicana had not been activated when Riot filed its quarterly report.

The Problem ERCOT Is Trying to Solve

ERCOT's presentation describes the concern this way: when a system fault occurs, large computational loads without ride-through capability can trip offline or transfer to backup generation. That customer-initiated load reduction, the deck says, causes high system frequency and overvoltage conditions. A single load tripping offline is one thing. Many loads in the same electrical neighborhood tripping together is a bigger problem, because the grid is suddenly left with more generation than demand.

The presentation, delivered by ERCOT's Patrick Gravois, a Principal Operations Engineer, under the title "QSA Results and Large Load IROL Mitigation Plans," quantifies that risk. ERCOT identified that 3,200 MW of load loss results in frequency overshoot to 60.4 Hz under certain system conditions, and the deck says frequency at that level leads to potential cascading outages and frequency instability. CryptoSlate and The Currency Analytics note that the normal frequency is 60 cycles per second.

Each quarter, ERCOT runs a Quarterly Stability Assessment (QSA) that identifies groups of large loads in which a single voltage disturbance may cause more than 3,200 MW of load loss. For those groups ERCOT develops Interconnection Reliability Operating Limits (IROLs) and mitigation plans. The deck says the 3,200 MW limit may not be exceeded, even temporarily. The Currency Analytics reported that ERCOT uses simulated faults to identify which groups could disconnect together for the fourth quarter of 2026.

How the Limit Works

ERCOT does not plan to run these groups right up to the 3,200 MW threshold. According to the presentation, it will control each IROL to 85% of the limit, or 2,720 MW of combined consumption. That is 3,200 MW multiplied by 0.85.

Mitigation starts below that ceiling. ERCOT says it will activate a plan "once aggregate consumption of an IROL group reaches ~2,500 MW." Once a plan is active, each Transmission Service Provider (TSP) and Qualified Scheduling Entity (QSE) with loads in the group must keep its load at or below a "Not To Exceed" limit. ERCOT says those limits are based on each load's maximum consumption over the previous three months, using telemetry where available. Loads consuming less than 5 MW are assumed to be construction load only and are not used in the share calculations. Until a plan becomes active, the deck says affected loads may continue to ramp up.

ERCOT also says the mitigation plans, which list all large loads in each IROL group, cannot be shared publicly. That means the public record does not show which individual facilities belong to each group or what share each would get.

The Three Groups, by the Numbers

The presentation lists three large-load groups and compares the capacity ERCOT has approved in each with what the loads have actually drawn. ERCOT says it combined five original groups in North and Central Texas into two. One of the five, original Group 4, fell below 3,200 MW and was removed from the IROL groups.

  • NORTH_LL: 5,465 MW of approved capacity, with maximum simultaneous consumption of 1,615 MW and maximum non-simultaneous consumption of 1,825 MW, per ERCOT.
  • CENTRAL_LL: 5,240 MW approved, with maximum simultaneous consumption of 1,560 MW and maximum non-simultaneous consumption of 1,670 MW, per ERCOT.
  • FARWEST_LL: 4,198 MW approved, with maximum simultaneous consumption of 1,035 MW and maximum non-simultaneous consumption of 1,463 MW, per ERCOT.

In every group, the maximum simultaneous draw is well below both approved capacity and the roughly 2,500 MW activation point. Approved capacity in each group exceeds the 2,720 MW control level, so if enough approved loads were built out and ran together, a group could reach the point where ERCOT starts assigning limits. ERCOT's deck says the FARWEST_LL group is still needed for monitoring but is unlikely to become active in the upcoming quarter, because about 1,400 MW of its approved capacity is a single large load that has not received approval to energize.

Where Corsicana Fits

ERCOT's deck does not name individual sites, and the mitigation plans are not public. The link to Riot's Corsicana operation comes from news coverage published Nov. 29. CryptoSlate reported that Corsicana belongs to a group ERCOT monitors. TokenPost described the monitored group's September simultaneous draw as 1,615 MW against 5,465 MW of approvals, which matches the NORTH_LL figures in ERCOT's presentation. The Currency Analytics reported that the roughly 2,500 MW threshold applies to a group in the northern part of the grid that includes Riot's Corsicana mine.

Under the mechanism ERCOT described, the group's 2,720 MW ceiling is divided into limits for each TSP and QSE according to recent measured consumption. The deck does not describe a facility-by-facility cap. TokenPost reported that the group limits would apply at roughly 2,500 MW of combined demand, under a shared ceiling of 2,720 MW, compared with the 3,200 MW of sudden demand loss ERCOT modeled.

TokenPost and CryptoSlate reported that Riot says its existing Corsicana operations qualify for an exemption from newer requirements to remain connected through voltage and frequency disturbances, and that the mine still belongs to a monitored group. The Currency Analytics and TokenPost both reported that Riot booked about $24.7 million in power credits in the third quarter, from power sales and demand-response programs.

Context: Flexible Load During Winter Storm Fern

The IROL plans deal with loads dropping off the grid unexpectedly. ERCOT also benefits when large loads cut consumption on purpose during supply emergencies. CryptoSlate reported that during Winter Storm Fern in January 2026, bitcoin miners cut about 4,100 MW, nearly 5% of ERCOT's roughly 84,500 MW forecast peak. According to the same report, oil and gas customers cut 4,200 MW, steelmakers about 420 MW and data centers 170 MW. Those are estimated reductions.

The two situations differ in who chooses the timing. During Fern, miners could decide when to power down. In a fault, equipment without ride-through capability can disconnect all at once. The working-group presentation addresses only the second case: keeping the combined load that could disconnect together below the level ERCOT has found could destabilize frequency.

What It Means for New Large Loads

For developers planning large computing campuses in the affected areas, the main practical point is how approved capacity compares with the 2,720 MW control level. In each of the three groups ERCOT listed, approved capacity is between about 1.5 and 2 times that level (4,198 MW to 5,465 MW), while the maximum simultaneous draw is between 1,035 MW and 1,615 MW. As more approved projects come online, the share each TSP and QSE can claim would depend on the measured-consumption method ERCOT described, assuming that method is unchanged when a plan activates. The deck notes that ERCOT moved to this method after TSP feedback, because several energized loads with large approved capacity were consuming less than 5 MW and running far behind their ramp schedules.

For utilities and local officials, the deck shows that adding computing load is a question of how many large sites in one electrical area could trip together, in addition to how much energy those sites use. Because the mitigation plans are not public, outside parties cannot see which specific sites would be affected or how a group limit would be divided.

What Happens Next

According to ERCOT's presentation, the mitigation plans become active only when ERCOT activates them, which it will do "once aggregate consumption of an IROL group reaches ~2,500 MW," and consumption has not yet reached a level at which plans are active. When a plan does activate, each TSP and QSE in the group must keep its load at or below its "Not To Exceed" limit, with limits based on a 2,720 MW total. The deck lists additional work still needed: ERCOT meeting with QSEs whose loads are co-located with generation resources, creating telemetry points, developing operator procedures and updating its System Operating Limit methodology. The sources do not give a date for a further working-group review or for any plan to take effect.