Batteries seem to be arriving at SpaceX's proposed data center site in Starbase, Texas, before the project has its local tax agreement. On Nov. 27, DatacenterDynamics (DCD) reported that SpaceX has reportedly installed more than $250 million worth of Tesla Megapack battery systems on the tract. That number comes from a Tesla investor's post on X. DCD said it had reached out to confirm the reports, and nothing in the record reviewed for this article shows how the figure was calculated or that SpaceX has confirmed it.

A separate figure comes from SpaceX itself. In its quarterly report to the Securities and Exchange Commission for the period ended Sept. 30, 2026, the company disclosed buying $151 million of Megapack products from Tesla in the third quarter and $480 million in the first nine months of the year. The related-party note in the filing does not say where those batteries went.

Below is what each source says, what it leaves out, and what comes next on the public calendar.

The $250 Million Figure: Where It Comes From

DCD's report, which DataCenterFeed read through an archived mirror, attributes the "more than $250 million" estimate to a post on X by a Tesla investor. DCD quotes the post as saying the site was "literally just dirt less than 90 days ago." DCD presents the number as a report, not a confirmed figure, and its headline carries the qualifier "report."

DCD also describes SpaceX's plans for a data center costing more than $24 billion, with a co-located gas-fired power plant, on a 444-acre tract in Cameron County. It says the plant would operate behind the meter, meaning it would supply the campus directly rather than through the regional grid. DCD notes that SpaceX has since secured a major air pollution permit and that the Cameron County Commission rejected the company's tax break application. It also mentions an earlier reported deployment of 168 Megapacks at the Colossus site in Memphis.

Readers should treat the $250 million figure as an outside estimate from a social media post. It is not an accounting number.

What SpaceX's 10-Q Actually Says

The SEC filing is a firmer document, but it answers a different question. In its related-party disclosures, SpaceX (Space Exploration Technologies Corp.) reports these Megapack purchases from Tesla:

  • $151 million in the three months ended Sept. 30, 2026
  • $480 million in the nine months ended Sept. 30, 2026
  • $506 million for all of 2025, along with $131 million of Cybertrucks that year

So by the end of September, SpaceX's Megapack purchases for 2026 were already close to its full-year 2025 total. The note on Megapack purchases does not name a site. It does not say whether any of the 2026 batteries were installed, are waiting to be installed, or are meant for the data center tract at all.

That leaves a gap. The investor's estimate and the 10-Q both point to large battery spending. No public document reviewed here links a specific dollar amount of purchases to the Starbase compute site. The $250 million estimate should not be subtracted from, or added to, the $480 million figure as though the two were measured the same way.

The Project on Paper

The most detailed official description comes from a City of Starbase public hearing notice, which ConstructConnect reported on. The notice describes a gas-fired power plant and a "super-compute facility" on 444.45 acres near the Port of Brownsville, east of Brownsville in Cameron County, with an estimated $24 billion for initial phases.

ConstructConnect notes that the notice does not give the abatement terms, the power plant's capacity, the facility's size or a construction schedule. It also says this is not an approved construction project.

Baxtel reported more details on the location and permitting:

  • The tract lies between Boca Chica Boulevard and the Port of Brownsville, inside the Cameron County Enterprise Zone.
  • Citing the RGV Business Journal, Baxtel reported that Trinity Consultants filed an air permit application with the Texas Commission on Environmental Quality (TCEQ) on SpaceX's behalf listing 35 natural gas turbines capable of producing 748 MW. Baxtel describes those figures as a permit filing, not a plant under construction.
  • The land came within Starbase city limits in August.
  • Brownsville separately approved an agreement for up to $220 million from SpaceX for water and wastewater projects.

The 748 MW figure comes from the TCEQ filing as Baxtel reported it. The Starbase notice itself does not state a generating capacity.

Why Annexation Matters

Where the land sits determines which local rules apply. Baxtel, citing the RGV Business Journal, reported that because Starbase annexed the tract, the data center moratoriums adopted by Brownsville and Harlingen do not apply to it.

Annexation also shapes the tax question. Cameron County has already turned down SpaceX's tax break application, according to DCD. The pending request goes to the Starbase City Commission, which can consider an abatement for property within the city's own limits under Chapter 312 of the Texas Tax Code.

Batteries and a Behind-the-Meter Plant

None of the sources reviewed explain how SpaceX plans to use Megapacks at Starbase, so this article does not guess. What the record shows is that a large battery installation is reportedly in place. It also shows an air permit application for gas turbine generation, with DCD reporting that SpaceX has since secured a major air permit, and that DCD describes the planned power arrangement as behind the meter. How storage capacity would be paired with the turbines, and in what amounts, has not been disclosed in any document reviewed here.

What Happens Next

The Starbase City Commission is scheduled to meet at 7 p.m. on Dec. 9 at 48491 State Highway 4 to consider a Chapter 312 property-tax abatement and an economic development agreement for the project, according to the city's public hearing notice as reported by Baxtel and ConstructConnect. The notice has not disclosed the abatement terms, and ConstructConnect notes that the project is not an approved construction project. Separately, Baxtel reported, citing the RGV Business Journal, that the TCEQ air permit application lists 35 turbines and 748 MW; DCD reports that SpaceX has since secured a major air permit.