Most of the attention on the Nov. 16 large-load filings at the Federal Energy Regulatory Commission went to the grid operators, PJM Interconnection's "Fast Energization" plan in particular. Groups of transmission-owning utilities filed alongside them. Those utilities answered a narrower question that matters a great deal to anyone financing or hosting a data center: once a utility builds network upgrades to serve a large load, how long must that customer keep paying for them?
According to Latitude Media's review of the filings, the utilities' answer is a long-term contract. The terms run from at least 10 years in PJM to as long as 20 years in the Midcontinent Independent System Operator (MISO). FERC has not accepted any of the proposals, and comments on several of them are due Dec. 7.
Where the Contracts Come From
The filings respond to show-cause orders FERC issued in June. In the PJM order, Docket EL26-67-000, issued June 18, 2026, the commission directed PJM and its transmission owners to show cause within 60 days why PJM's tariff remains just and reasonable without provisions on three subjects. The first was the application and study process for large-load transmission service. The second was transparency on network upgrade costs, including "a pro forma cost recovery agreement between PJM, the relevant transmission owner, and Eligible Customer" meant to "mitigate the risk of cost shifting among transmission customers." The third was transmission service for flexible large loads willing to limit their use of the system. The order lists Commissioners Swett (Chairman), Rosner, See, Chang and LaCerte.
The transmission owners' proposals respond to that order. Latitude reported that the utilities are using the show-cause order as an opportunity to ask FERC to approve long-term contracts similar to, but not identical with, terms already in some state-approved tariffs. Latitude also reported that by Nov. 16, five of the six grid operators had answered FERC's show-cause orders. The Southwest Power Pool's answer was due Nov. 20.
The operator filings are separate. PJM's own Fast Energization proposal, also filed Nov. 16, would study new generation and large loads together, which PJM says would cut the projected timeline from two years to one. PJM says the process also establishes new transmission services for large loads, including, as FERC found, an interim service while network upgrades are built, and gives states and utilities clear insight into the cost of serving large loads. PJM separately filed ride-through requirements for data centers. The transmission owners' cost agreements sit beside these filings and deal with who pays and for how long.
What the Utilities Proposed
The figures below are Latitude Media's reading of the filings. DataCenterFeed was unable to open the filings themselves.
PJM. The PJM transmission owners propose a cost recovery agreement that would require a data center to pay for at least 80% of the transmission service it requests for at least 10 years. The customer would post a financial guarantee starting at 25% of what it would owe and rising to the full amount by the time service begins. A customer that leaves early would owe the remainder.
California and New York. Utilities in both markets propose 15-year terms. Latitude reported that the New York contract would not take effect until May 2028.
MISO. The MISO proposal is a three-party agreement among the grid operator, the utility and the data center, with a term of up to 20 years.
How the Terms Compare With State Tariffs
Several utilities already impose minimum-payment terms on large loads through state-approved retail tariffs. Latitude cited two of them. Dominion's Virginia large-load tariff, taking effect in January, sets an 85% floor over 14 years. AEP Ohio's sets 85% over 12 years. A Latitude Intelligence analysis puts the average minimum term at 12 years for utilities in PJM whose state tariffs require a transmission commitment and 15 years in MISO.
Measured against those examples, the PJM owners' proposed 80% floor and 10-year minimum are lower than the Virginia and Ohio retail terms. The proposal covers different ground, though. Latitude noted that the new contracts cover only transmission and do not replace the state tariff, so a data center could end up signing two parallel but not identical sets of terms. In PJM states with retail choice, such as New Jersey and Pennsylvania, a utility's minimum bill generally does not apply, so Latitude said the federal agreement would become a data center's only long-term commitment to pay for transmission upgrades.
California shows the same gap from another direction. Latitude reported that PG&E has a 12.9-gigawatt data center pipeline, by the utility's own count, and its retail schedule sets no minimum term and no minimum bill. At PG&E, Latitude said, the proposed 15-year federal contract would be the only long-term commitment a data center would sign, at least for now. Latitude made the same point about Niagara Mohawk in upstate New York, which sets no minimum term for data centers today.
Why the Structure Matters
FERC's June order presented the cost recovery agreement as a tool to mitigate the risk of cost shifting among transmission customers. The concern is that a utility builds network upgrades for a large customer, the customer's load never arrives or the customer leaves early, and other ratepayers end up paying for the upgrades. Latitude described the state tariffs as working through two mechanisms, and the PJM proposal adds a third element. A minimum-payment floor sets how much the customer pays whether or not it uses the power. A minimum term sets how long that obligation lasts. In PJM, a financial guarantee and an obligation to pay the remainder on early exit are meant to make sure the money can be collected if the customer walks away.
For developers, the terms affect how much capital must be posted before service begins and how long the obligation stays on the books. Under the PJM owners' design as Latitude describes it, the guarantee would start at 25% and grow to the full amount by the start of service. Latitude also reported that in several of the largest markets utilities still have no data center terms in force.
The proposals come soon after a setback for PJM's previous large-load approach. Latitude reported that FERC rejected most of PJM's last large-load plan in October, in part for overreaching into retail territory.
What Happens Next
None of the transmission owners' proposals is in effect. FERC must decide whether to accept them. According to Latitude Media, comments on several of the filings are due Dec. 7. On the operator side, PJM asked for a 60-day comment period on its Fast Energization filing and a commission order within 120 days. If accepted, the New York utilities' contract would not take effect until May 2028, according to Latitude.
Sources
- Utilities want FERC to lock data centers into paying for grid upgrades (Latitude Media, Nov. 18, 2026)
- FERC order to show cause, PJM Interconnection and Transmission Owners, Docket EL26-67-000, 195 FERC ¶ 61,211 (June 18, 2026)
- PJM Plan Would Cut Interconnection Process Time in Half (PJM Inside Lines, Nov. 16, 2026)