Chowan County, N.C., has stopped accepting new data center projects in its unincorporated areas for a year. On Monday, Nov. 23, the Board of Commissioners voted 3-2 to pause development approvals for data centers, cryptocurrency mining operations and other high-impact data processing facilities. The Albemarle Observer reported the vote. The ordinance runs from Nov. 23, 2026, to Nov. 23, 2027.
The Observer reported that Commissioners Ron Cummings, Larry McLaughlin and Alton Lane voted for the moratorium. Chairman Bob Kirby and Commissioner Tony Shaffer voted against it. The vote followed a public hearing at the Public Safety Center. Before voting, commissioners debated whether a year was too long and whether the moratorium could expose the county to a lawsuit, the paper reported.
The moratorium was brought under North Carolina General Statute 160D-107, which the county's draft ordinance cites as the state law authorizing local governments to adopt temporary moratoria on development approvals.
What the Ordinance Covers
DataCenterFeed has not reviewed the adopted ordinance or the meeting minutes. The text described here comes from the draft ordinance posted on the county website, dated Oct. 20, 2026. In that draft, the adoption date is blank and the signature line for Chairman Kirby is unsigned. The board could have changed the wording before adopting it.
The draft bars the county from accepting, processing or approving several kinds of applications for covered facilities:
- special use permits
- conditional zoning permits
- zoning map amendments (rezonings)
- building permits
- any other development approval required by law
It covers three kinds of facility: data centers, cryptocurrency mining facilities and "other high-impact data processing facility" uses, including their establishment, construction, alteration or expansion. It applies across the county's unincorporated areas.
Two limits narrow its reach. First, the draft exempts developments that already hold a valid approval under G.S. 160D-107(c) before the effective date, and the Observer likewise reported an exemption for projects holding valid approvals under state law. Second, the Observer reported that the moratorium does not apply to the town of Edenton or its extraterritorial jurisdiction, the area just outside town limits.
The draft takes effect Nov. 23, 2026, and ends Nov. 23, 2027, unless the board terminates, extends or modifies it sooner.
Why the County Says It Needs the Time
County staff framed the pause as a fix for a gap in the zoning code. County Planner Robert Daniel said the county's zoning ordinance does not mention data centers, which leaves staff in a bind when someone proposes one. A use that is not listed has to be fit into an existing category or declared unlike anything in the ordinance, he said. "Either way, it's risky for the county," Daniel said. He described the moratorium as "pumping the brakes" while the county writes rules, according to the Observer. County Attorney Lauren Arizaga-Womble told commissioners the question before them was narrow, the paper reported.
The draft ordinance makes a similar case. It says the county's existing regulations were not developed with these uses in mind, and that general and special use permits lack specific performance standards such as noise limits, utility capacity requirements and setbacks. It lists extremely high energy consumption, noise from cooling systems and backup generators, substantial water use, environmental impacts and land-use compatibility among the concerns. The study phase of the schedule covers energy, water, noise and land use.
The Study and Drafting Schedule
The draft ordinance sets out a month-by-month plan for the year:
- Months 1-4: Study the energy, water, noise and land-use impacts of the covered facilities, in consultation with local utility providers and the UNC School of Government.
- Months 4-6: Draft land use ordinance amendments and performance standards, including appropriate zoning districts, setback requirements, noise limitations and utility capacity conditions.
- Months 6-10: Hold public workshops and Planning Board meetings to review the draft amendments and gather public input.
- Months 10-12: The Planning Board provides a recommendation to the Board of Commissioners, which holds the necessary public hearings to consider and potentially adopt the final ordinance amendments.
The Observer described the same order of work: staff would spend the first four months studying the issue, then draft standards and hold public workshops and planning board meetings, and bring a final ordinance to commissioners in the last two months.
The Split on the Board
The two commissioners who voted no included the chairman. According to the Observer, commissioners debated two questions after the hearing. One was whether a full year was too long. The other was whether the moratorium could expose the county to a lawsuit. The Observer's report, as reviewed here, does not say which commissioners raised which concern.
For context, the draft runs a full 12 months but says the board can terminate, extend or modify it earlier. It also exempts developments that already hold a valid approval under G.S. 160D-107(c).
A Statewide Pattern
Chowan County is one of many. In a report dated July 31, 2026, the Carolina Journal said more than 30 North Carolina local governments had temporarily halted new data center development since February, with moratoriums lasting several months to one year. Opponents most frequently cited data centers' electricity demand, water use, noise and impact on nearby neighborhoods, the Journal reported.
The same report cited an April News & Observer opinion piece in which two Republican state representatives, David Willis and Jeff McNeely, argued that blocking data centers through moratoriums would leave North Carolina on the sidelines. It also reported that business leaders argue moratoriums can send a broader signal to investors about whether North Carolina communities are open to long-term development.
Chowan's one-year term is at the long end of the range the Journal described. The ordinance also names cryptocurrency mining and other high-impact data processing facilities alongside data centers, according to the Observer and the draft.
What Happens Next
The moratorium is in effect through Nov. 23, 2027, unless the board terminates, extends or modifies it sooner. Under the schedule in the county's draft ordinance, the first step is a four-month impact study in consultation with local utility providers and the UNC School of Government. Draft standards are scheduled for months four through six. Workshops and Planning Board meetings follow in months six through ten. In the final two months, the Planning Board is to make its recommendation and the Board of Commissioners is to hold public hearings on the final ordinance amendments. None of the sources reviewed gives dates yet for those workshops or hearings.
Sources
- Albemarle Observer: Chowan commissioners approve one-year moratorium on data centers (Nov. 24, 2026)
- Chowan County: DRAFT ordinance imposing a temporary moratorium on development approvals for data centers (Oct. 20, 2026 draft)
- Carolina Journal: Local data center moratoriums may carry statewide consequences (July 31, 2026)