The Warrick County Board of Commissioners in Indiana has approved an ordinance that sets how data center proposals will be zoned. Commissioners approved it at their Monday meeting by a 2-0-1 vote, with one commissioner abstaining, according to WEHT. Based on when the report was published, that Monday was Nov. 23. The station reported that the ordinance first came up for a vote at the Nov. 9 meeting and was tabled. It did not name the commissioner who abstained.
The ordinance does not approve a data center. WEHT reported that it establishes what it called a "floating data center overlay district." Officials said the district does not automatically approve any data center. Every project still needs its own public zoning review and has to disclose its infrastructure demands, impacts and safeguards. Separately, a 180-day moratorium on data center applications remains in effect until Feb. 7, the station reported.
This article describes the ordinance using county documents released before the vote. Those are a public FAQ dated Oct. 20 and a hearing draft dated Oct. 14. The county marked the draft as not adopted and subject to revision. DataCenterFeed has not reviewed the final adopted text or the minutes of the Nov. 23 meeting, so the final version may differ from what is described below. The 2-0-1 vote and the Feb. 7 end date come from the WEHT report. DataCenterFeed could not confirm either one in a primary county document.
What a "floating" overlay means
Most zoning districts are drawn on the county map in advance. A floating overlay is written into the zoning code first, and it lands on a specific parcel only when the local legislative body rezones that parcel for a specific project. The county's public FAQ says the proposed ordinance would set up a Data Center Overlay District (DC-O) and that each data center would go through its own public zoning review. The FAQ also says that meeting the minimum standards and filing a complete application does not guarantee approval, and that the overlay would not approve any site in advance.
The Oct. 14 hearing draft is titled "An Ordinance Amending the Warrick County Comprehensive Zoning Ordinance to Establish a Data Center Overlay District, Project-Level Legislative Approval Process, and Related Development, Monitoring, Enforcement, Project-Failure Reversion, and Decommissioning Requirements." Its recitals say the Board of Commissioners wants a neutral and reusable zoning framework. Under that framework, principal data centers would be considered only at locations found appropriate through the legislative zoning process, after review and recommendation by the Area Plan Commission.
The draft gives the project-level decision to the legislative body, not to the Board of Zoning Appeals (BZA). The BZA would still handle true development-standard variances and administrative appeals. According to the FAQ, the limits on each project would be set through a project-specific schedule of maximum scope and measurable standards. The recitals also cite the county's 2045 Comprehensive Plan, which distinguishes Industry Hubs from Reclaimed Mine Lands and says neither reclaimed-mine status nor any single land-use designation alone determines whether a site suits a data center.
The approval sequence
The county FAQ sets out the steps in order:
- The countywide ordinance itself, which commissioners have now approved, according to WEHT.
- A project application from a developer.
- A public hearing before the Area Plan Commission (APC), which makes a recommendation.
- A vote by the Commissioners to approve or deny the zoning.
- Development-plan approval and permits.
The FAQ says applicants must disclose all reasonably foreseeable phases, the project's maximum scope, measurable safeguards, impacts, supporting studies, and plans for decommissioning and restoring the site.
What applicants would have to put on the record
The hearing draft lists the required disclosures in detail. Applicants would have to submit information on:
- maximum acreage, total building area, number of buildings and phasing;
- water demand figures, cooling systems and wastewater discharge;
- on-site generation and battery energy storage (BESS) capacity;
- drainage and stormwater plans, and critical buffers;
- geotechnical studies plus studies of mine history and subsidence;
- fire flow;
- a decommissioning plan backed by financial assurance.
Under the FAQ, expansion beyond an approved project's limits would require another legislative zoning review, and other material changes could require amended permits, plans or commitments. The draft also says that meeting the minimum standards does not create a right to DC-O zoning.
The mine-history and subsidence studies reflect the county's geography. The comprehensive plan the draft cites includes a Reclaimed Mine Lands category, and the FAQ says a former mine site would still need its own review. The developer behind the one prospective project the county has described publicly said that project's land is primarily reclaimed mine land.
How the county got here
The ordinance follows a moratorium the county adopted in August. At an Aug. 11 special meeting, the Commission passed an ordinance that paused data center projects for six months and created a study committee, WNIN reported. The station said the Area Plan Commission had approved the measure the night before, after pivoting from work on a regulatory rule. WNIN's headline called Warrick County the first to pause data centers with a local ordinance. Commission President Sarah Seaton said project details were not available because the developers were still in the early stages of due diligence, WNIN reported.
The prospective project is known as Project Zora. In a county press release, the county reported on a July 30 executive session. It said the developer team represented that it had approximately 1,200 acres in northern Warrick County under project control, primarily reclaimed mine land, and had a preliminary concept to develop approximately 300 acres. The developer also said it had an agreement with a prospective end user and expected to identify it by year end. The county said it had signed no non-disclosure agreement, made no commitment and granted no approval. It said these statements were based solely on information from the development team and had not been independently verified.
The county posted updates on its official website under the headlines "Warrick County Provides Update on Preliminary Data Center Inquiry" and "Warrick County Working on Data Center Ordinance." The FAQ listed two public meetings on the draft, both at the Friedman Park Event Center in Newburgh: an APC hearing on Nov. 2 at 6 p.m. and a Commissioners meeting on Nov. 9 at 4 p.m. WEHT reported that the ordinance was tabled at the Nov. 9 meeting and approved at the following meeting. The county commissioners listed in the FAQ are Sarah A. Seaton (president), Terry J. Phillippe and Stacey Franz.
One point the sources leave open is how the moratorium and the permanent ordinance fit together. The FAQ says the proposed ordinance would repeal the temporary 180-day deferral when the permanent ordinance takes effect. WEHT, reporting after the vote, says the moratorium remains in effect until Feb. 7. DataCenterFeed has not seen the adopted text and cannot say which controls.
What the vote does not settle
The ordinance decides how future applications will be handled. It does not decide any application. No document reviewed for this article shows a DC-O application filed for Project Zora or any other site. The 1,200-acre and 300-acre figures are claims the developer made to the county in July, which the county said it had not verified. In the same release, the county said the developer stated it would not submit a permit application to the county before January 2027. For the county to vote on any real proposal, a developer would have to file the disclosures listed above, and the project would have to go through an APC hearing and then a separate commissioners' vote on zoning.
What Happens Next
WEHT reports that the 180-day moratorium on data center applications remains in effect until Feb. 7. Under the process in the county FAQ, any project would then need a full application, a public hearing before the Area Plan Commission, and a vote by the Board of Commissioners to approve or deny the zoning, followed by development-plan approval and permits. The county's July press release says the Project Zora developer stated it would not submit a permit application before January 2027. None of the sources reviewed lists a hearing date for any specific data center application.
Sources
- WEHT via Yahoo News: Warrick County commissioners vote on data center ordinance
- Warrick County Commissioners: Proposed Data Center Ordinance Public FAQ (Oct. 20, 2026)
- Warrick County Permanent Data Center Ordinance, public hearing draft v2026.10.14 (not adopted)
- WNIN: Warrick County Commission is first to pause data centers with local ordinance (Aug. 12, 2026)
- Warrick County press release: Update on Preliminary Data Center Inquiry
- Warrick County, Indiana official website