Until this week, Lancaster, Ohio, had no zoning rules written specifically for data centers. On Monday, Nov. 23, the Lancaster City Council changed that. It voted 10-0 to add a new "Data Processing Centers" section to the city's Planning and Zoning Code. The vote came after a public hearing that the Lancaster Eagle-Gazette said about 100 people attended. About 20 of them spoke, and most favored restrictions.
The setback distance changed before the vote. According to the Eagle-Gazette, the ordinance as passed requires data centers to sit at least 500 feet from nearby residents, and a data center's power generating station to sit at least 650 feet away. The original ordinance called for 1,000 feet, and council amended it to the shorter distances. The rules apply to new data centers and to any expansion at Google's existing data center in the Whiley Road area, the paper reported.
One caveat on the documents: the copy of the ordinance posted on the city's website is the as-introduced text, Temporary Ordinance No. 33-26. It still shows the 1,000-foot setback, and its blanks for the passage date and the vote count are empty. The 500-foot and 650-foot figures in this article come from press reports of the meeting, not from an adopted ordinance text that DataCenterFeed could review.
What the ordinance does
The introduced ordinance says plainly that the city's zoning code "does not currently contain specific regulations governing Data Centers." It creates a new Section 1147.12 and sets out a framework that, according to the introduced text, works as follows:
- Where they can go: Data centers are allowed only in the Advanced Manufacturing (AM) District, and only as a special exception granted by the Board of Zoning Appeals. They are not a by-right use anywhere in the city.
- Setbacks: The introduced text set a 1,000-foot minimum distance from a residential district for both the principal structures and the accessory structures that generate energy. Press accounts say council cut these to 500 feet and 650 feet respectively.
- Height: 60 feet maximum.
- Buffer yard: 50 feet wide, planted with 50 shrubs, 15 small trees and 7 large trees per 50 feet of frontage.
- Berm: An earthen berm at least 12 feet high with a 3:1 slope. If a berm isn't feasible, an acoustic barrier may be used instead, as determined by the Board of Zoning Appeals.
- Lighting: A photometric lighting plan is required.
- Noise: Industrial noise from the site may not exceed the average noise of the busiest roadway within a quarter mile, as measured by a sound study.
- Traffic: Planned construction traffic routing must go to the City Engineer and City Planner for approval before construction starts.
- Environmental: Facilities must comply with applicable environmental laws, including U.S. EPA and Ohio EPA requirements.
The introduced ordinance applies to data centers approved after its effective date and says any "modification, expansion, or an increase in the intensity" of an existing center must comply too. That clause is how Google's current campus comes under the new rules if the company builds more.
From one foot per foot to 500 feet
Under the city's previous Advanced Manufacturing rule, the setback depended on building height. NBC4 described it as one foot of setback per foot of building height. NewsForce247, summarizing Eagle-Gazette and NBC4 reporting, noted that under that rule a 60-foot building could sit about 60 feet from a home.
The city's Planning Commission reviewed the amendments on Aug. 13, 2026, and voted to recommend them, according to the introduced ordinance. The commission's minutes attached to that document record a motion to approve with setbacks of 1,000 feet for principal and accessory structures, which carried on a 4-2 vote with one abstention. The final ordinance, per press accounts, cuts the building distance in half from that figure. The 650-foot figure for power generation sits 150 feet beyond the 500-foot building setback.
The neighboring jurisdiction already had a stricter rule. NBC4 reported before the vote that Greenfield Township, where Google's current campus sits, has a 1,000-foot setback. That matters because of where Google's next land is.
Google's land and the annexation question
NBC4 reported that Google bought more than 100 acres attached to its current data center campus in Greenfield Township, and that the land will likely be annexed into the City of Lancaster. If that happens, any development there would fall under the city's new data center section, with its 500-foot setback as reported, and not under the township's 1,000-foot rule. None of the sources reviewed for this article gave a date or filing for an annexation.
At the hearing, Google representative Molly Boyle told council, "We don't oppose thoughtful, careful guardrails," according to the Eagle-Gazette. Before the vote, NBC4 reported that a Google spokesperson said the company has been installing noise and light barriers to reduce the impact on residents.
What residents raised
People who live near Google's existing facility described noise, bright lights and the smell of diesel fuel, the Eagle-Gazette reported. Some said the adopted setbacks don't go far enough. Those concerns line up with sections of the ordinance: the sound-study noise limit, the photometric lighting plan, the berm or acoustic barrier, and the separate, larger setback for energy-generation structures.
The shorter setbacks council adopted are the main gap between what residents asked for and what passed. The introduced text's 1,000 feet matched the Planning Commission's recommendation and the township's existing standard. The final figures, per press accounts, are half that for buildings and about two-thirds of it for power generation.
What the structure means for developers and officials
Making data centers a special exception, not a permitted use, means each new project or expansion goes to a Board of Zoning Appeals decision. By contrast, the ordinance's own text says a permitted use is issued a Zoning Clearance Permit by the City Planner or designee.
For developers, the operative numbers in the ordinance are the setback distances, the 60-foot height cap and the noise standard. That standard ties allowable sound to the busiest nearby road, not to a fixed decibel figure.
What Happens Next
None of the sources reviewed identified a further scheduled hearing, vote or filing on the ordinance. The introduced text says it takes effect at the earliest period allowed by law. Once it does, any new data center, or any modification, expansion or intensification of Google's existing Whiley Road campus, would be subject to Section 1147.12, with data centers permitted only as a special exception in the Advanced Manufacturing District. NBC4 reported that Google's adjacent land of more than 100 acres will likely be annexed into the city, but no annexation date or application was given in the sources. The city had not posted an adopted version of the ordinance text showing the amended distances when this article was published.
Sources
- City of Lancaster, Ohio: Temporary Ordinance No. 33-26, adding Section 1147.12 Data Processing Centers (as introduced)
- Lancaster Eagle-Gazette (via Yahoo): City council passes restrictions on data center growth after public hearing
- NewsForce247: Lancaster Council Votes 10-0 to Push Data Centers 500 Feet From Homes
- NBC4 (Columbus): Central Ohio data center expansion prompts zoning fight in Lancaster