Metro Nashville's temporary moratorium on data center permits expires Tuesday, Dec. 1, and the mayor's office says it has no plan to extend it. After that date, applications are handled under the permanent data center zoning rules the Metro Council adopted in July. The Nashville Banner reported the expiration on Nov. 25.

The end of the pause does not settle the dispute that led to it. DC Blox's proposed data center next to the Nashville Zoo is now being fought in two places in the same week. A federal judge has a preliminary hearing on the company's amended lawsuit against Metro on Dec. 1, and the Board of Zoning Appeals hears appeals from the zoo and Councilmember Courtney Johnston on Dec. 3.

The sections below cover what expires, what replaces it, and where each part of the DC Blox case stands, based on Metro's legislative record and local reporting.

What exactly is expiring?

The moratorium is Bill BL2026-1448. Metro's Legistar record says it declares a temporary moratorium on the "acceptance, processing, approval, and issuance" of zoning, building, or grading permits for data center developments in Nashville and Davidson County. Johnston is among its sponsors on the Legistar record, and the Banner describes her as having sponsored it.

The bill took about seven weeks to pass. Legistar lists it as introduced June 8, 2026, and passed on first reading June 9. The Planning Commission approved a substitute version June 25. The public hearing and second reading were held July 7. The council passed it on third reading, as amended, on July 21, and the mayor approved it July 24. The Nashville Scene reported that the council approved the moratorium unanimously and that it paused all data center permits until Dec. 1.

What replaces it?

The permanent rules come from a companion bill, BL2026-1391. It is a zoning text amendment that adds data center uses and definitions to Title 17 of the Metro Code, under planning proposal 2026Z-012TX-001. Legistar shows it was filed May 26 and passed third reading, as amended, the same night as the moratorium, July 21. The mayor approved it July 24, and it took effect July 31.

When the moratorium lapses, the permanent rules remain.

Councilmember Rollin Horton told the Banner the permanent rules are "very strict." The mayor's office has produced a report on concerns raised by Metro departments, with recommended further changes, but the Banner reports that no legislation has been filed since. Horton called those recommended changes "relatively minor."

The mayor's spokesperson, Alex Apple, told the Banner: "There is not currently a plan to extend the moratorium."

Why doesn't the new ordinance simply govern the DC Blox site?

The answer depends on when DC Blox filed. In a Nov. 10 note to the board reported by the Banner, zoning administrator Joey Hargis wrote that DC Blox's building permit submission, dated May 29, 2026, is subject to the rules in place when it was filed. "There were no rules applicable to data centers at the time of its filing," Hargis wrote.

That filing came before the moratorium bill was introduced. Legistar shows BL2026-1448 was introduced June 8, and BL2026-1391, although filed May 26, did not take effect until July 31. Under the zoning administrator's reading, the data center rules Metro adopted over the summer do not apply to this application. The Banner reports that Horton takes a different view: he believes DC Blox did not submit "substantially complete" plans and should therefore be judged under the new rules.

The Banner reports that the Board of Zoning Appeals meets Dec. 3 to hear appeals from the zoo and from Johnston, and that appellant briefs are due Monday.

DC Blox spokesperson Nichole Thomas told the Banner the company is "working within clear zoning and regulatory frameworks."

Where does the federal lawsuit stand?

DC Blox sued Metro in federal court on Aug. 11, according to the Scene. U.S. District Judge Eli Richardson dismissed the complaint, and with it the company's request for an injunction against the moratorium. He gave DC Blox 21 days to amend three of its claims, finding that the company had not clearly pleaded protected property interests. The judge wrote that "a raw deal or sandbagging — real or imagined, without more — does not a federal lawsuit make," the Scene reported.

The Banner, describing the ruling as a federal judge siding with Metro "last month," reports that DC Blox has since filed an amended complaint and that a preliminary hearing is set for Tuesday, Dec. 1. That is the same day the moratorium expires.

What about eminent domain?

Metro has a further option on the table: acquiring the land itself. The Scene reports that the council approved condemnation legislation on Aug. 4 that would allow Metro to use eminent domain to seize the zoo-area property for public use. The Scene also reports that DC Blox paid $23 million for the property in late July.

Whether Metro will use that authority is unknown. The Banner reported on Nov. 25 that there was no update on the mayor's proposed use of eminent domain on the property.

Why it matters beyond Nashville

This case illustrates a problem many local governments face when they write data center rules for the first time: what to do with applications filed before any rules existed. The moratorium went from introduction to mayoral approval in about seven weeks, and the permanent ordinance, filed two weeks earlier, was approved the same day. Even so, the zoning administrator's position is that the DC Blox application was filed before either measure.

Metro's positions are being tested in several places at once: the moratorium in federal court, the permit question before the zoning board, and the possible use of eminent domain, which remains unresolved. How each plays out may be of interest to officials in other places writing their own ordinances.

What Happens Next

Three scheduled steps fall in the coming days, as the sources describe them:

  • Monday, Nov. 30: Appellant briefs are due in the Board of Zoning Appeals case, according to the Banner.
  • Tuesday, Dec. 1: The moratorium under BL2026-1448 expires, and the mayor's office says it has no plan to extend it. On the same day, a federal judge holds a preliminary hearing on DC Blox's amended complaint against Metro.
  • Thursday, Dec. 3: The Board of Zoning Appeals hears the appeals filed by the Nashville Zoo and Councilmember Courtney Johnston.

The Banner reports that no legislation has been filed to adopt the changes recommended in the mayor's office report. It also reports no update on the proposed eminent domain action. Coverage during Thanksgiving week was limited, so this article reflects the record as of the Banner's Nov. 25 report and Metro's Legistar entries.