Residents of Coal City, Illinois, get their formal chance to speak on Aligned Data Centers' proposed campus on Tuesday. The village's Zoning Board of Appeals and Plan Commission will hold a joint public hearing at 6 p.m. Dec. 1 at the Coal City Lions Club, 460 S. Illinois St., according to Shaw Local's Morris Herald-News. The hearing covers Aligned's planned unit development (PUD) for land at the southeast corner of East Reed Road and South Carbon Hill Road in the Grundy County village.

Village Administrator Matt Fritz announced the date at the Nov. 23 village board meeting. He said the hearing might be continued to Dec. 2 to leave room for public comment, Shaw Local reported.

The hearing follows a village committee review that ran from August into November. Here is what is in the application, what the review found, and what the village has published about the next step.

What Aligned Is Asking For

Aligned, a Texas-based developer, submitted its application in a letter dated July 20, 2026, through the engineering firm Kimley-Horn. The PUD narrative on file with the village asks for four approvals: a preliminary and a final PUD, and a preliminary and a final plat of subdivision. The narrative describes the site as about 320 acres, the majority of it inside Coal City. Shaw Local described the property as 300 acres and said Aligned plans an 11-building campus on it.

The site is made up of six parcels, labeled A through F in the narrative. Five are already in the village and zoned I-1 Industrial. The sixth, Parcel C (parcel number 09-15-100-008), is under Grundy County agricultural zoning. The narrative requests that it be annexed into Coal City and rezoned I-1.

The narrative describes the project as a technology campus plus an adjacent 30-acre public utility substation. Its plat sets out the substation and the campus as separate lots:

  • Lot 1: the 30-acre public utility substation that, according to the narrative, would be owned and operated by ComEd.
  • Lot 2: the technology campus itself.

The application also asks for deviations from village standards. For the substation lot, the narrative asks that minimum off-street parking and loading requirements be eliminated, citing that the substation is unmanned. It also asks to allow an 11-foot-tall expanded-metal fence topped with 12 inches of barbed wire, with certain posts up to 18 feet tall.

The narrative says Aligned is pursuing municipal economic development incentives, including tax increment financing (TIF), on parallel administrative tracks, and refers to a subsequent development agreement. The narrative presents these as separate from the PUD approvals.

The Applicant's Operating Claims

Several figures in the application are Aligned's own statements and had not been independently verified in the sources reviewed for this article.

The PUD narrative says the campus would employ approximately 600 to 800 people and operate 24/7. It says the campus requires only 17,000 gallons per day of water, using a non-evaporative, closed-loop cooling system. It says each building would take 12 to 18 months to construct, and that the number of buildings under concurrent construction would depend on customer demand.

The company's Coal City project page makes similar claims. It says the campus uses air-cooled heat rejection with a closed-loop system that needs water only for the initial fill and minimal maintenance, so water use would be primarily domestic. On power, Aligned says it is committed to covering the cost of electricity tied to its data centers as well as on-site power generation, so that the cost of powering its facilities does not fall on local families. It also says it can switch to on-site backup systems during rare regional power emergencies, leaving more electricity on the grid. The page describes downward-facing, fully shielded lighting and silencing technology on chillers and backup generation equipment.

Shaw Local reported that residents have regularly attended village board meetings over nearly two years to raise concerns about traffic, water use, electricity costs and noise, and have also questioned how the project would benefit the area economically.

How the Village Reviewed It

The PUD process falls under Section 156.185 of the village code. After Aligned's PUD submittal, the Village Board approved a PUD Review Committee to review it, according to the village's official data center page. The village says the PUD process is conducted prior to the joint public hearing of the Zoning Board of Appeals and Plan Commission.

The village has posted the review record on that page. It shows committee agendas for Aug. 18, Sept. 1, Sept. 9, Oct. 14 and Nov. 4, plus a rescheduled Oct. 27 date, along with minutes for the first four of those meetings. It also includes review comments (the first round, revised Aug. 28 and Oct. 6), the petitioner's response dated Oct. 9, a final PUD findings report from the committee, the joint public hearing notice, the Dec. 1 agenda, and the hearing files.

According to Shaw Local, the committee met five times and reviewed reports by the engineering firm HR Green. At its final meeting on Nov. 4, the committee determined that Aligned's proposal complies with the village's standards for new developments.

The village says on its project page that the posted material is background information and "should not be thought of as promotional or supportive of the project." The committee's finding of compliance with development standards is a finding by the review committee ahead of the hearing, and the village page does not describe it as an approval of the project.

Items in the Application

The application and the reporting point to several matters on the hearing's subject list:

  • Annexation of Parcel C. One parcel is still under county agricultural zoning, and the narrative requests that it be annexed into the village and zoned I-1.
  • The deviations. The parking, loading and fencing requests for the ComEd substation lot are requested exceptions to standard village requirements.
  • Water and power claims. The 17,000-gallons-per-day figure comes from Aligned's PUD narrative, and the pledge to cover electricity costs comes from Aligned's project page. Shaw Local reported that residents have raised water use and electricity costs as concerns.
  • Site size. The PUD narrative says about 320 acres, while Shaw Local reported 300 acres.

What Happens Next

The joint Zoning Board of Appeals and Plan Commission hearing opens at 6 p.m. Tuesday, Dec. 1, at the Coal City Lions Club, 460 S. Illinois St. If needed to accommodate public comment, it may be continued to Dec. 2, Village Administrator Matt Fritz said, according to Shaw Local. The hearing notice, agenda, committee findings report and review documents are posted on the village's data center page.