A Core Scientific entity has registered a new data center building at the company's Hunt County, Texas, campus with the Texas Department of Licensing and Regulation (TDLR). The registration lists an estimated cost of $1.3 billion and a construction start date of Nov. 24, 2026.

According to the TDLR project record (TABS2027005763), Telios Quinlan One, LLC registered the project "Core Scientific - Hunt" on Nov. 13, 2026. The filing describes new construction of a 341,326-square-foot "data center core and shell building with site and infrastructure improvements" at 4852 CR 3507 in Quinlan, Hunt County. The project is listed as privately funded on private land. It runs from Nov. 24, 2026 to Sept. 4, 2028. The design firm is Gensler's Houston office, and no tenant is assigned.

TDLR is the Texas state agency that keeps these project registrations on its public Architectural Barriers database. This filing covers one building. MLQ reports that Core Scientific has said the campus will have several.

What the filing does and does not say

The TDLR record gives the building's floor area, cost estimate, address, schedule, owner entity and architect. It does not give a power capacity for the building or name an operator or customer. Its tenant field reads "not assigned."

The record lists the owner as Telios Quinlan One, LLC, with a Dallas address. MLQ connected the filing to Core Scientific in its report on the registration, describing Telios Quinlan One as a Core Scientific subsidiary, and the project name on the state record is "Core Scientific - Hunt." MLQ put the site about 53 miles northeast of Dallas.

The $1.3 billion figure is TDLR's "estimated cost" field for a core-and-shell building plus site and infrastructure work. The filing does not say whether it includes electrical and mechanical fit-out or IT equipment, so it should not be read as the cost of the whole campus.

How Core Scientific acquired the site

Core Scientific's Form 10-Q for the quarter ended Sept. 30, 2026 describes the Hunt County deal. The company says that on May 5, 2026 it completed the purchase of land in Hunt County for about $232.5 million. It allocated $4.7 million of that to the land and $227.8 million to development rights.

The 10-Q also says the company signed a related electric service agreement. That agreement is expected to support about 430 MW of gross utility power capacity, and the company says it intends to develop the property as a future data center site.

The 10-Q describes the 430 MW as gross utility power capacity, while it describes the lease figures below as critical IT capacity. These are different measures, so the 430 MW should not be read as the amount of capacity available to tenants.

The 285-MW figure and the AMD connection

MLQ, citing DCD, reports that Core Scientific said in March that the Hunt County campus could support up to 285 MW of leasable capacity across several buildings. The same report says the company expected to start energizing the campus in 2027 and reach full power by 2029. DataCenterFeed could not read that March statement in a primary source, so these figures are attributed to DCD's account as relayed by MLQ.

MLQ also cites DCD as reporting that AMD is set to lease 110 MW at Hunt County. DataCenterFeed did not find that site-level figure in the 10-Q.

The 10-Q does describe the leases at the portfolio level. In July 2026 Core Scientific signed lease agreements with AMD and a counterparty it calls a "Neocloud" for about 530 MW of critical IT capacity across five sites. Each lease has a 15-year term with three five-year options and is expected to commence in phases beginning in 2027. According to the filing, none had commenced as of Sept. 30, 2026. The 10-Q also says AMD holds a reservation right to lease an additional 1,925 MW through Dec. 28, 2028, which the filing describes as not a binding lease commitment.

The TDLR record does not tie the new building to either lease, and its tenant field is blank.

Questions for Hunt County and local officials

Where is the site? The TDLR record gives 4852 CR 3507, Quinlan, TX 75474, in Hunt County.

Who is building it? The owner of record is Telios Quinlan One, LLC, and Gensler is the design firm. The filing does not name a general contractor.

Is public money involved? The TDLR record lists the project as privately funded on private land. It does not address local tax abatements or incentive agreements, and the sources reviewed for this article do not mention any.

How much power will this building draw? The filing does not say. The 430 MW electric service agreement in the 10-Q covers the site as a whole, and the 285 MW leasable figure reported by DCD describes several buildings.

Water, jobs and traffic? None of the sources reviewed give figures for water use, permanent employment or construction workforce.

What Happens Next

The TDLR record lists a construction start date of Nov. 24, 2026 and a completion date of Sept. 4, 2028 for this building. The project's TDLR status is "Project Registered." Core Scientific's 10-Q says its AMD and Neocloud leases are expected to commence in phases beginning in 2027. The filing does not say which sites or buildings come first.