On Nov. 13 the City of Rockford named the company evaluating a possible data center on land in south Rockford, Ill. In a notice titled "Data Center Updates," the city said Microsoft is the company evaluating the Monarch-controlled property in south Rockford for a possible data center. The city added that Microsoft is still evaluating the site and that detailed plans are not available.

The news came four days before a separate step in the city's own process. On Tuesday, Nov. 17, the city's Zoning Board of Appeals (ZBA) holds a public hearing on draft citywide data center regulations. Council members ordered those rules in August, when they enacted a temporary moratorium. The city's notice says the Tuesday hearing "remains focused on the City's proposed data center regulations," not on Microsoft's project or its location.

Below is what the sources confirm so far, and what they leave open.

What the city announced

The city's notice is the main public record. According to the notice, Microsoft gave the city a packet of frequently asked questions and plans to hold community open houses "in coming months." No dates have been set. The notice also sets out what Microsoft calls a "Community-First AI Infrastructure" approach. Under it, Microsoft says it will pay for its own electricity without raising prices for other customers, use as little water as possible and replenish more than it consumes, create local jobs and add to the tax base. These are Microsoft's stated commitments as the city relayed them. They are not terms of any agreement with the city.

City Administrator Todd Cagnoni told Rockford News First that Microsoft has not submitted any site plans or development proposals. "They have not finalized whether they're going to move forward with the site or not," Cagnoni said. He told the station the city learned of Microsoft's interest over the summer and received formal confirmation the week of the announcement.

What is known about the site

The city's notice calls the land "the Monarch-controlled property in south Rockford." It gives no acreage or power figure. More detail comes from Data Center Dynamics (DCD), which cited Rockford News First. DCD reported that the property is owned by Monarch Energy, sits at 8685 Friday Road and covers 1,300 acres. According to DCD, the campus could reach 1.4 GW over several phases. Those acreage and capacity figures come from DCD's report. The city's notice does not state them.

DCD also reported that Monarch received a tax incentive agreement in July 2026 under Illinois' Data Center Investment Program. According to DCD, that program does not require local approval.

DCD reported several other points from Microsoft. The company says it operates 17 data centers in Illinois and does not ask municipalities to lower local property tax rates. It is developing 350 acres in Cherry Valley and 500 acres in Plano. DCD also reported that the Monarch site will not be fully subject to Rockford's new rules, but that Microsoft says it intends to meet them anyway.

Jobs and infrastructure: what the FAQ says

Rockford News First reported figures from Microsoft's FAQ packet. According to the packet, Microsoft's data center campuses typically employ 100 to 250 full-time employees and vendors, with about 50 working when the first facility opens. The station noted that these are general estimates and are not specific to Rockford. The packet also says Microsoft would pay for any water, sewer and electrical upgrades the project needs, according to the station.

The city has said detailed plans are not yet available, and the sources reviewed here give no power demand, water use or construction schedule for the Rockford site.

The moratorium and the draft rules

The draft rules began with a council vote. According to the city's data center page, the City Council enacted a temporary six-month moratorium on data centers on Aug. 5 and told city staff to draft regulations. The draft now before the ZBA would require the following:

  • Water: closed-loop cooling and near-zero wastewater discharge.
  • Air: air permits and emission standards for backup generators, in place before a certificate of occupancy is issued.
  • Noise: an independent acoustical study, with noise levels that meet Illinois Pollution Control Board rules.
  • Land use: larger setbacks, plus landscaping and screening, near homes, schools and parks.
  • Power: proof of adequate electrical service, confirmed by ComEd, another utility or an independent third party.
  • Cost: developers pay for necessary public infrastructure improvements such as water, sewer and roads, and provide a letter of credit covering 110% of those improvements or an equivalent form of security.

The city's position is that the regulations are citywide standards and are not specific to one project or property.

What a ZBA vote does, and does not, do

The city's data center page says a ZBA vote does not approve or deny the rules. Whatever the board decides, the item goes back to the Codes and Regulations Committee and then to the full City Council for more review and final approval. Tuesday's hearing is one step in that process. It does not finish it.

The city says the hearing is not about Microsoft's project or location. According to Cagnoni, as reported by Rockford News First, no site plans or development proposals have been submitted to the city.

What Happens Next

The Zoning Board of Appeals holds its public hearing on the city's proposed data center regulations on Tuesday, Nov. 17, at 6 p.m. in City Council Chambers at City Hall, 425 E. State St. After the ZBA votes, the regulations go to the Codes and Regulations Committee and then to the full City Council for further review and final approval. The city says the hearing will cover the draft regulations, not Microsoft's project or location.

Microsoft has said it will hold community open houses in the coming months, with dates to be determined, according to the city. According to Cagnoni, as reported by Rockford News First on Nov. 13, Microsoft had not submitted a site plan and had not finalized whether to go ahead with the site.

Sources