Data center developers who can't wait years for a grid connection have mostly been turning to on-site natural gas. A new report from the think tank Energy Innovation proposes a different off-grid option: new wind and solar paired with large heat batteries, steam generation and backup boilers, built together as what the group calls a "clean energy park with thermal infrastructure."
The report, written by Energy Innovation's Eric Gimon and published Nov. 20, says such a park can power data centers around the clock "without any initial connection to the power grid or gas pipelines." It is a modeling and policy proposal. In a Canary Media article published Nov. 23, Gimon said he is unaware of a U.S. data center taking this approach today.
The Problem the Report Targets
Energy Innovation frames the proposal around speed to power, not price. According to the report's executive summary, U.S. data center demand could reach 118 GW of installed capacity by 2030. The report puts the proposed pipeline of gas "bridge power," meaning off-grid or near-grid generation that bridges a data center's needs until a grid connection is achieved, at roughly 90 to 189 GW.
The grid itself is the bottleneck the report describes. Interconnection queues hold 773 GW of solar, 220 GW of wind and 749 GW of battery storage, according to the executive summary. Only 13% of capacity submitted to those queues between 2000 and 2020 had been connected and commissioned by December 2025, the report says. It also notes that more than 170 GW of clean energy projects have been "safe-harbored" for federal tax credits, meaning developers have already made meaningful progress but may not yet have customers for the power.
"The issue right now isn't so much cost, but speed to power," Gimon told Canary Media.
How a Thermal Clean Energy Park Would Work
In the report's design, wind, solar and four hours of battery storage are combined with a "thermal hybrid power" layer of thermal batteries (54 hours of storage at full output), steam generation and backup boilers. According to Canary Media, heat batteries store energy by heating rocks, bricks or other materials to more than 1,000 degrees Celsius. When power is needed, the stored heat boils water to drive a steam turbine. The report says the boilers supply a limited backup source using the same steam turbines during the most difficult renewable droughts and contingencies.
The main technical tradeoff is efficiency. Canary Media reports that storing heat to make electricity recovers only about 40% of the energy put in, compared with a low-to-mid 90% round-trip efficiency for lithium-ion batteries. In other words, a heat battery returns roughly 40% of the electricity used to charge it. Gimon told Canary Media that when the solar and wind power is cheap enough and the electricity from the steam turbines valuable enough, the losses are tolerable, and that thermal batteries would be cheaper than lithium-ion storage over longer durations.
Canary Media names four companies that make heat batteries: Antora, Brenmiller Energy, Electrified Thermal Solutions and Rondo Energy. Neither the report nor the Canary Media article says that any of them has agreed to supply a data center project of this kind.
What It Would Cost, by the Author's Estimate
Gimon estimates that hybrid thermal power would deliver round-the-clock power at about $120 per megawatt-hour, including the cost of developing the renewables, Canary Media reports. For reference, Canary Media cites about $72 per megawatt-hour for a data center in West Texas, along with an estimate from investment bank Jefferies (spelled "Jeffries" in the article) that Meta pays $140 to $165 per megawatt-hour for power from an off-grid gas plant in Ohio.
These numbers come from different sources and rest on different assumptions. The $120/MWh figure is Gimon's modeled estimate, not a contracted price. The Meta figure is Jefferies' estimate, not a number Meta disclosed. Canary Media says that, depending on location, the thermal approach can be competitive with building a dedicated gas plant.
On timing, Gimon told Canary Media that where renewable energy is already under development, hybrid thermal power could deliver power within a year or two, much faster than the wait for a gas plant.
The Competing Path: Gas
The proposal arrives as gas development tied to data centers keeps growing. In an August 2026 analysis, Global Energy Monitor reported that U.S. gas-fired capacity in development rose 50%, or 127 GW, in the first half of the year, from 252 GW to 378 GW. The group's tracker counts 189 GW of gas-fired capacity in the U.S. intended to directly power data centers.
Texas accounts for much of the activity. Global Energy Monitor counted 122 GW of gas capacity in development in the state, 77 GW of it planned to directly power data centers. Nationally, gas projects under construction rose 76% to 52 GW, with 16.9 GW of that for data centers. The analysis also reported that developers are increasingly turning to reciprocating engines and smaller aeroderivative units to skip the turbine supply constraints; engine capacity in development tied to data centers more than tripled in six months, reaching 45 GW.
Canary Media reports that, according to Gimon, large developers' gas plans are constrained by the gas-turbine supply chain, workforce availability and pipeline capacity, while steam turbine manufacturers are not nearly as backlogged. The report itself says the conventional boilers and steam turbines in its models draw on established industrial equipment and supply chains.
Open Questions
Based on what the sources say, several things have not been shown:
- No deployment. Gimon said he is unaware of a U.S. data center using this approach today. The cost and schedule figures are modeled, not measured. The report calls thermal hybrid energy parks a promising option worthy of further detailed engineering study and commercial development.
- Efficiency penalty. At about 40% energy recovery, according to Canary Media, heat storage loses far more energy than lithium-ion batteries do. Gimon says the economics can still work when the renewable power is cheap enough.
- Backup fuel. The design includes fuel-fired backup boilers. The report's screening model assumes up to around 1% on-site fuel use, and Canary Media says Gimon looked at boilers running on fuel stored on site. The sources reviewed here do not say which fuel would be used.
- Site availability. The one-to-two-year timeline Gimon described applies to places where renewable energy is already under development.
What Happens Next
The sources do not list a scheduled next step. The Energy Innovation report is a think-tank proposal, and neither it nor the Canary Media coverage names a project, a regulatory filing, a hearing or a construction milestone tied to the concept. The report is licensed under Creative Commons CC BY 4.0, which allows others to reuse and adapt its analysis.