In October 2025, Energy Secretary Chris Wright asked the Federal Energy Regulatory Commission to standardize how large loads such as data centers connect to the transmission grid. According to Latitude Media, a year later developers are not getting a single national process. FERC chose to handle each region separately. In mid-November, the country's six regional grid operators filed responses that each mix firm and non-firm service, curtailment, resource adequacy and cost allocation in a different way.

The filings do share one assumption. A data center that wants firm transmission service, or wants to connect before the grid is built out to serve it, is increasingly expected to bring new generating capacity of its own.

Why FERC Went Region by Region

On June 18, 2026, FERC issued show-cause orders under section 206 of the Federal Power Act to the six regional transmission organizations and independent system operators: PJM, MISO, SPP, CAISO, ISO-NE and NYISO, according to the commission's news release. A summary by the law firm Orrick says the orders stem in large part from a rulemaking the Secretary of Energy initiated in October 2025.

Each grid operator, together with its transmission owners, had 60 days to show that its current tariff was just and reasonable or to propose changes. Each also had 30 days to file an informational report on generation adequacy for large loads. FERC said its staff reviewed more than 3,500 pages of public comments before acting. The release says the commission's orders recognize that a one-size-fits-all solution is not currently the most efficient way to integrate large loads; the six operators differ in market design, structure, stakeholder makeup and geography.

The orders cover five reform areas:

  • efficient processes for applying for and studying transmission service;
  • preventing costs from shifting to other customers, and making transmission costs more transparent;
  • co-location and behind-the-meter generation;
  • new transmission services for large loads that can be flexible; and
  • a process for studying generation that serves large loads located electrically nearby.

What FERC Had Already Done

The June orders followed several regional decisions. FERC's release says they build on a December 2025 order on PJM co-location and on the commission's approval of SPP's High Impact Large Load initiative.

According to Orrick, after FERC's December 2025 order directing PJM to adopt transparent tariff rules for co-located load, PJM adopted three transmission service options: interim non-firm service, firm contract demand and non-firm contract demand. In January 2026, FERC accepted SPP's High Impact Large Load study process, which Orrick says is designed to support interconnection decisions within 90 days. In June 2026, FERC approved PJM's Expedited Interconnection Track. Orrick describes it as allowing up to 10 requests per year for resources of 250 MW or more that can reach commercial operation within three years. It requires a $500,000 study deposit and a $15,000/MW readiness deposit, and it is scheduled to expire at the end of 2027.

FERC has also turned down a PJM approach. Latitude Media reports that the commission rejected PJM's plan to require large loads to bring matching new generation or face mandatory curtailment during capacity shortfalls, while suggesting PJM could pursue a similar outcome through a voluntary non-firm transmission service.

What the Six Filings Propose

Latitude Media's review of the mid-November responses found the same idea in several regions: bringing new capacity is becoming the default way for a large load to get either firm transmission service or earlier non-firm or interim service. Mary Yang, chief operating officer and senior energy advisor at 804 Advisory, told the publication that bring-your-own-capacity is becoming a "no-brainer."

The details differ by region, according to Latitude Media:

  • ISO-NE and NYISO proposed tying firm transmission access to bring-your-own-capacity requirements.
  • MISO proposed a service that splits a customer's demand into firm and non-firm portions. The firm portion would be subject to interruption when wholesale prices exceed $100 per megawatt-hour, and would have to be curtailed entirely during a capacity event regardless of price. Latitude Media reports the proposal would not be implemented before 2029 and does not yet have FERC approval.
  • SPP's existing conditional service pathway sets no annual cap on the number of hours a customer can be curtailed.

For developers, the result is that terms for interruptible service, the trigger for curtailment, and the conditions for firm service will depend on where a project is located.

State Rules Still Apply

The federal proceedings are only part of what a developer has to deal with. Latitude Media notes that state rules, executive orders and utility terms of service add their own requirements. In Pennsylvania, Gov. Josh Shapiro's August executive order gives data center developers different permitting review pathways depending on whether they make binding commitments, such as meeting project demand with new generation in their region.

Federal legislation could reinforce that state-by-state approach. Latitude Media reports that the Bipartisan American Affordability and Jobs Act, which the Senate passed in November, would explicitly allow states to require certain data centers to procure or build new generation, or else accept limits on their access to the grid.

What It Means for Communities and Ratepayers

One of FERC's five reform areas goes directly to households and businesses that do not run data centers: the commission listed preventing cost shifting and making transmission costs transparent as a separate category. FERC also asked grid operators to report on how they will ensure adequate generation for existing and new large loads. Latitude Media reports that several of the show-cause proposals leave key cost-recovery arrangements to bilateral agreements between utilities and developers, which can shape who bears the financial risk of building infrastructure and how much a customer must pay if its plans change.

What Happens Next

The six grid operators have filed their show-cause responses. None of the sources cited here gives a date for commission action on any of the six. MISO's proposed firm/non-firm service does not yet have FERC approval, and Latitude Media reports it would not be implemented before 2029. PJM's Expedited Interconnection Track, which FERC has already approved, is scheduled to expire at the end of 2027, according to Orrick.