The switches that connect GPUs inside a large AI cluster usually rely on pluggable optical transceivers: modules that turn electrical signals into light at the front panel of each switch. Co-packaged optics, or CPO, moves that conversion onto the switch package itself, placing optical engines next to the switch chip and shortening the electrical path from inches to millimeters, according to Nvidia and GCN.
On Nov. 16, at the SC26 supercomputing conference in Chicago, Lambda and Nvidia described a large deployment. According to Nvidia's blog, Lambda is using Nvidia Photonics CPO switches to connect GB300 NVL72 racks holding more than 10,000 GPUs. GCN placed the cluster of more than 10,000 Blackwell Ultra GPUs at Lambda's Quebec data center campus and reported that the companies describe it as the world's first large-scale deployment of the technology running production AI workloads.
The deployment itself is not new. Lambda said earlier this year that the work was underway. The new part is the performance and operating data the two companies released with it, most of it measured by Lambda.
What Lambda Measured
Lambda's figures come from comparing CPO switches with conventional pluggable optics. Nvidia's blog says network latency, the time needed to move data, dropped by about 4% at rack scale and by up to about 10% at pod scale, and that across rack, scalable unit and pod configurations the network kept the same throughput as conventional pluggable optics. GCN gave the more precise numbers: the latency gap grew from 3.8% at rack scale to 10.1% at pod scale.
A latency cut of a few percent sounds small. Nvidia's own framing of why the network matters is different: in a large training job, it says, one interrupted link can stall thousands of GPUs, and every watt spent on networking is a watt not available for compute.
The second Lambda-reported number is about heat. Nvidia's blog says the company reports a median optics temperature of 36 C, compared with 51 C for conventional pluggable optics, along with more stable signal integrity. These are Lambda's own measurements as Nvidia and GCN reported them. Neither source describes an independent test.
What Nvidia Claims
Nvidia's own claims are broader, and they are vendor figures. The company's blog says that by replacing pluggable transceivers with co-packaged optical engines on the switch package, Nvidia Photonics delivers up to 5x better power efficiency and up to 15x higher reliability than conventional pluggable optics, and uses 4x fewer lasers. The blog states these as properties of the product rather than as measurements from Lambda's cluster, and GCN attributes the 15x reliability figure to Nvidia's Gilad Shainer. Readers should treat them as Nvidia's claims, not results confirmed in this deployment.
The hardware details Nvidia published explain where the claims come from:
- Port count and speed: each switch has 144 ports running at 800 Gb/s, according to Nvidia.
- Cooling: liquid cooling carries heat away from the switch chip and optical engines.
- Light sources: each switch has 18 removable external light sources that supply light to the optical engines, and technicians can replace them in the field.
The last point matters for repairs. Nvidia says that with traditional pluggable optics, the entire module must be replaced if a laser fails, while its design lets technicians swap the light-source modules on site. Nvidia also says that 4x fewer lasers means fewer components that can fail. Together with the lower temperatures Lambda reported, that is the basis for Nvidia's argument that the design is more reliable.
Nvidia's blog also includes a statement from Dave Ward, president of cloud services at Lambda, who said networking has to keep pace with increasingly large AI clusters and called bringing co-packaged optics into a deployment of this scale an important step.
The Quebec Site
The Nvidia blog does not name the site. GCN, citing Lambda's announcement distributed through Business Wire, reported these details about Lambda's Quebec campus:
- 142 MW of secured energy capacity, described as nearly 100% renewable;
- free cooling for up to 80% of the year;
- a guaranteed power usage effectiveness (PUE) of 1.2;
- no process water consumption associated with server cooling.
All of these figures are Lambda's statements as GCN reported them. The sources do not say how much of the 142 MW the cluster uses, and they do not explain how the 1.2 PUE is measured or guaranteed. The sources also do not say whether the cooling and water figures apply to the CPO cluster specifically or to the campus as a whole.
How the Timeline Fits Together
According to GCN, the SC26 announcement builds on Lambda's early adoption of Nvidia CPO networking, first announced in November 2025.
On March 16, 2026, during Nvidia's GTC conference, Lambda's own blog said the company was leading one of the largest deployments of Nvidia Quantum-X InfiniBand Photonics co-packaged optics switches to date, in an AI factory with 10,000+ Nvidia GB300 GPUs. It said: "We announced our work on NVIDIA CPO and next-generation networking fabrics in 2025. Now it's running in production." That post did not include the latency or temperature figures released at SC26.
Put together, the sequence runs from an early-adopter announcement in November 2025, to a production claim at GTC in March 2026, to measured operating data at SC26 in November 2026.
Why It Matters Beyond One Cluster
Nvidia's argument for CPO rests on power and interruptions. In its blog, the company says every interruption costs time and every watt spent on networking is a watt not available for compute. GCN adds that Nvidia says its photonics switches let Lambda's customers get more productive GPU hours from their investment. Those are Nvidia's characterizations, not figures from the sources' own testing.
Those wider effects depend on numbers that, so far, come mainly from the vendor. The results Lambda measured itself are narrower: modest latency cuts at the same throughput and noticeably cooler optics. The 5x power efficiency and 15x reliability figures are still Nvidia's claims.
What Happens Next
The sources give no scheduled date, filing or construction milestone tied to this deployment. On the product side, GCN reported that Nvidia has said it plans to extend co-packaged optics across both its Quantum-X InfiniBand and Spectrum-X Ethernet switch lines, without a stated timeline. Lambda has not announced, in the sources reviewed, an expansion of the cluster beyond the more than 10,000 GPUs now connected.