The Loudoun County, Va., Board of Supervisors has formally adopted its pause on legislative data center and electrical substation applications. At its Nov. 17, 2026 meeting, a majority of the Board voted to stop Board action on those applications for up to 12 months, according to a county news release. The county says 12 months is the maximum Virginia law allows. The resolution is retroactive to Sept. 15, the date supervisors first voted to start the pause.

The county release says a majority voted for the resolution. It does not give the vote count.

The county release notes a previous opinion from the County Attorney that a moratorium stopping all data center approvals is not legal. What the Board adopted is narrower than a moratorium. It is a time-limited halt on the Board's own hearings and votes on one category of land-use cases. It ends once new comprehensive plan and zoning rules are in place.

Below is what the resolution does, based on the county's release and the September statements that led up to it.

What exactly is paused?

The pause covers legislative applications for data centers and electrical substations. These are cases that need a discretionary decision by the Board, not staff-level administrative approval. The county says the pause could affect 33 active legislative applications.

According to the county, developers can still submit applications, and the Planning Commission will keep holding hearings on them. Only Board public hearings and Board votes are on hold.

What is not covered?

The county release lists three categories that fall outside the pause:

  • Route 28 Tax District properties. Properties in the Route 28 Tax District are excluded.
  • Administrative applications. These include by-right projects that were grandfathered before the Board ended by-right data center development. The release says the Board previously ended by-right data center development, so data center projects must come before the Board through the special exception process. A Sept. 16 statement from Algonkian District Supervisor Juli Briskman said at least 17 grandfathered land-use cases, representing more than 11 million square feet of development, are not affected by the pause because they proceed through a by-right administrative process.
  • Case-by-case exceptions. The county says exceptions are possible where electric grid reliability is at stake, or where a statutory decision period is about to expire.

Baxtel reported in September that the county was also considering ending the grandfathered by-right status of those projects. The county's Nov. 17 release does not mention that question.

Why not a moratorium?

The legal limit set the shape of the policy from the start. Briskman's September statement says County Attorney Leo Rogers advised that the Board may defer legislative applications that are subject to statutory deadlines. He also advised that Virginia law does not allow a blanket moratorium on administrative applications. WJLA reported that the county attorney said an indefinite moratorium would not be legal and that a temporary pause would be limited to 12 months.

WJLA reported in September that Board Chair Phyllis Randall said the measure is not a moratorium and described it as a way to give the county time to develop new laws addressing data centers.

How did the Board get here?

The Board first acted at its Sept. 15 meeting, according to Briskman's statement. Supervisors voted 7-1-1 to begin a temporary pause on Board consideration of certain legislative data center and substation applications, effective immediately. Briskman introduced the motion, according to Baxtel. WJLA reported that Supervisor Kristen Umstattd voted against and Supervisor Caleb Kershner abstained. Baxtel reported the same split as 7-1 with one abstention.

The Board also took a separate 7-1-1 vote that day to approve an exception for "grid reliability" substations, according to Briskman's statement. Briskman was the vote against.

Briskman's statement said staff would return at the Oct. 20 Business Meeting with a formal resolution. The county release says the Board adopted a resolution on Nov. 17, made retroactively effective as of Sept. 15.

The September statement also said staff would identify applications that could reach their 12-month deadline before the new rules are complete and ask those applicants to voluntarily delay.

What ends the pause?

The pause is for up to 12 months, but the county ties its end to a specific action. The county says it ends when the Board adopts Comprehensive Plan and Zoning Ordinance amendments from the county's Data Center Standards and Locations project. The county says that project is expected to wrap up in summer 2027.

The county release explains that Virginia law requires action on legislative applications within one year, and that the one-year period begins when an application is first submitted to the Planning Commission.

Who is affected?

The county identifies 33 active legislative applications that could be affected. The release does not name them. For those applicants, the Planning Commission review process continues, but no case can reach a final Board decision during the pause unless it qualifies for one of the exceptions.

Grandfathered by-right projects keep moving. Briskman's statement put those at at least 17 cases and more than 11 million square feet of development.

What Happens Next

According to the county, Planning Commission hearings on data center and substation applications will continue during the pause, and developers may still file new applications. Board public hearings and votes on such applications are to stay on hold until the Board adopts the Comprehensive Plan and Zoning Ordinance amendments from the Data Center Standards and Locations project. The county says that project is expected to wrap up in the summer of 2027. The county says 12 months is the maximum the pause can last under Virginia law. Under the September direction described in Briskman's statement, county staff were also to ask applicants whose cases could reach their 12-month deadline to voluntarily delay them.