Spartanburg County Council in South Carolina gave final approval on Nov. 16, 2026 to development agreements for three data center projects. Together they cover hundreds of megawatts of proposed computing capacity and several billion dollars in stated investment. According to Fox Carolina, the approvals went to a high-performance computing project at 4000 South Pine Street that the station identifies as Valara, a campus near 430 Jones Road, and AIB Data Centers' CLT1 site at 389 Tyger River Industrial Drive. Council also held first readings on three more AIB agreements.
On the same day, AIB Data Centers released its third-quarter results in a statement filed with the Securities and Exchange Commission. The release says CLT1 has an anchor customer: Nebius, under a 12-year agreement for 50 MW of critical IT capacity.
The Three Approved Agreements
South Pine Street (Valara). The largest of the three is described by Fox Carolina as a 457-MW project with about $2.76 billion in investment and 27 full-time jobs identified as a target, not a guarantee. Fox Carolina describes the Valara data center as already under construction, and reports that the agreement protects the project for 10 years from certain future county regulations, moratoriums and zoning changes. It also sets a review clock. The county must determine within 10 days whether an application is complete and then has 45 days to take final action, and if it does not act within that period the agreement says the application could be considered approved based on the submitted documentation. The agreement requires annual reporting to the county on investment, construction, utilities and employment, according to the station. In exchange, the company commits to noise mitigation, landscaping and at least one community meeting each year.
Coverage differs on the name of the developer entity. Fox Carolina calls it "Numara LLC," while WSPA calls it "Pneuma LLC." DataCenterFeed could not read the county agenda or meeting record to confirm the correct name, so this article does not use either one.
Fox Carolina reported that Councilman Mo Abusaft said before the meeting that he planned to vote no on the Valara agreement, as he did on second reading. In its coverage of the second reading, WSPA reported that council member Paul Abbott said he would again vote against the South Pine Street project. The sources available to DataCenterFeed do not give the final vote tally for any of the agreements.
Jones Road. The second agreement is with 300 Jones Road Associates LLC for approximately 137 acres at or near 430 Jones Road. Fox Carolina reports the project at up to 65 MW of IT capacity, about $1.5 billion in investment and 25 full-time jobs. The agreement includes $9 million in community benefit payments over five years. The proposal has a history of county opposition. According to Fox Carolina, county planning staff denied an earlier application for the property in June, and the Board of Zoning Appeals upheld that denial on Aug. 25. The station says the original denial was not overturned; the developer is now pursuing the project under an exception to the county's data center moratorium, adopted in September.
The project's size matters because of that exception. Fox Carolina reports that it allows qualifying data centers of 65 MW or less on designated industrial park sites or former industrial properties to move forward if they meet additional requirements. At up to 65 MW, the Jones Road project is within that size limit.
AIB CLT1. The third agreement covers AIB Data Centers' CLT1 site at 389 Tyger River Industrial Drive, which Fox Carolina describes as an existing bitcoin mining operation proposing to convert to a conventional data center, with 50 MW of capacity and an estimated investment of $1.2 billion.
What AIB Told the SEC
AIB's Nov. 16 earnings release, filed as Exhibit 99.1, adds detail on CLT1 that the council coverage does not include. The release is a company statement and does not describe the Spartanburg votes.
According to the release:
- AIB signed a 12-year Master Colocation Services Agreement with Nebius for 50 MW of critical IT capacity at CLT1, backed by a parent company guarantee. Prepayment obligations were funded into escrow, and AIB has received its first draw.
- Service under a 15-year, 65-MW electric service agreement at CLT1 began Oct. 1, 2026.
- AIB estimates delivery of its first 25-MW data hall in the fourth quarter of 2027 and its second in the first quarter of 2028, subject to permitting, financing and construction milestones.
- After acquiring a Texas site it calls DFW1, which has 15 MW energized and up to 40 MW of additional service, AIB puts its contracted power at about 120 MW. It also reports non-binding letters of intent for DFW2 (an approximately 60 MW powered site) and GSO1 (a site with up to 90 MW of planned capacity).
AIB reported third-quarter revenue of $0.8 million and a net loss of $4.8 million. It said it ended the quarter with $25.5 million of cash, cash equivalents and restricted cash and no traditional debt. The release includes comments from CEO Jerry Tang.
The 65-MW electric service agreement is larger than the 50 MW Fox Carolina attributes to the county agreement and the 50 MW of critical IT capacity AIB attributes to the Nebius contract. The release does not explain the difference.
Three More AIB Agreements on the Table
Fox Carolina reports that council also gave first reading to agreements for AIB's CLT2, CLT3 and CLT4 projects. Each agenda item included a proposed special source credit agreement and development agreement, and the station says draft agreements indicate the tax incentives could run for 40 years. The coverage DataCenterFeed reviewed does not give megawatt or investment figures for the three sites.
Public Comment and the Exhibits Question
The agreements drew extended public comment as they moved through council. At the second reading, according to WSPA, several speakers said key parts of the agreements, including site master plans and development schedules listed as exhibits, had not yet been filled in. County staff responded, per WSPA, that the missing exhibits were expected to be completed and released with the tentative agenda for council's November meeting, ahead of the final vote. DataCenterFeed could not read the county agenda and has not confirmed whether those exhibits were published or what they contain.
For residents and other local stakeholders, the South Pine Street agreement's terms are the ones most likely to have lasting effect. Fox Carolina reports that the agreement establishes limits on certain future county regulatory actions affecting the project, including a 10-year protection from certain future regulations, moratoriums and zoning changes, along with the provision under which an application could be considered approved if the county does not act within 45 days of a completeness determination.
What Happens Next
Fox Carolina reports that the three AIB agreements for CLT2, CLT3 and CLT4 will need additional council consideration before final approval. The sources DataCenterFeed reviewed do not give a date for the next reading.
For CLT1, AIB's SEC release estimates delivery of the first 25-MW data hall in the fourth quarter of 2027 and the second in the first quarter of 2028, subject to permitting, financing and construction milestones. Under the South Pine Street agreement, Fox Carolina reports that the developer must report annually to the county and hold at least one community meeting each year.