Springfield, Missouri, will not consider any data center plans until after Feb. 24, 2027. City Council voted Monday, Nov. 16, to extend its administrative delay on data center applications, according to KY3. The pause had been due to expire the next day, Tuesday.
Council approved only part of what city staff proposed. It extended the pause but did not pass the new zoning definitions meant to decide what counts as a data center under city code. The mayor offered an amendment that changes how the largest category of facility would be defined, and the amended definitions will come back at the council's Nov. 30 meeting, KY3 reported.
The vote came six days after KY3 reported on Nov. 10 that a judge had denied a company's request to end the pause, leaving it in place.
How Springfield Got Here
The pause followed an application for a data center project. In June, KSMU reported that council was considering a 120-day suspension of data center applications, with some exceptions. City Manager David Cameron said at the time that the city had received an application for a data center in an existing mixed-use building, though he said it was not the only reason the city wanted to start a conversation. He said the city wanted time to study the impacts, including questions of capacity and the effect on ratepayers.
On Oct. 5 the city laid out its next steps in a news release. The administrative delay was set to expire Nov. 17. Staff proposed two things: extend the delay, and amend the Land Development Code to define "data center." The release said the city had completed three public engagement sessions. Residents raised concerns about electricity and water use, utility rates and reliability, wastewater, noise, air quality, land use and public safety, among other topics.
The city framed the extension as procedural. Cameron said in the release that extending the pause gives the city time to sort through questions about utilities, public safety, the environment and land use. The release also said the extension would not determine whether data centers ultimately will or will not be permitted in Springfield. The city said it would keep monitoring state and federal action that could affect what regulations local governments are authorized to adopt.
The Definitions Council Held Back
The proposed code language would sort facilities into three tiers. Justin Crighton, the city's assistant director of planning and development, described them at an Oct. 26 council hearing, according to KY3:
- Accessory Data Center: located inside a principal building, taking up no more than 20% of its gross floor area, serving only the building's owner or tenants, and with a maximum power demand of less than 1 MW.
- Large Load Data Center: a facility with a maximum power demand of 5 MW or more, or more than 10,000 square feet.
- Micro Data Center: a data center that is under both large-load thresholds and does not meet all the accessory criteria.
As proposed, a facility could be classed as large-load based on either power demand or floor area. The mayor's amendment, as KY3 described it on Nov. 17, splits up the large-load category and defines it only by megawatts, not square footage. The amendment would also differentiate between information technology equipment and other uses. KY3's report did not give the megawatt thresholds for the new sub-categories.
The sizing question had come up at the October hearing. Ten residents signed up to speak, KY3 reported. A speaker who works for a local internet provider said the definitions were too broad, and pointed to fiber huts, small buildings of roughly 8 by 10 feet used to provide service to businesses and residents, as an example of what the accessory-tier wording could catch, because that tier covers only facilities serving the building's owner or tenants.
The Court Challenge
A company called NSI went to court over the pause, according to KY3's Nov. 10 report. Citing court records, KY3 said NSI claims zoning for the property at 2900 South National Ave. allows "data processing services," so the moratorium does not apply. The lawsuit also contends city planners approved the project before the moratorium was put in place. The ruling did not go in NSI's favor.
NSI also faces a moratorium in Benton County. KY3 reported that in September a different judge stopped a moratorium to allow NSI to build in Benton County, meaning county commissioners there cannot enforce it until a final judgment is made. KY3 said a court date had not been set in that case.
Taken together, the two rulings have gone in opposite directions for the same company. In Benton County a judge blocked enforcement against NSI while the case continues. In Springfield a judge refused to end the city's pause. Neither KY3 report described any appeal.
What the Extension Does and Does Not Do
The council's Nov. 16 vote keeps the freeze on data center applications in place until after Feb. 24, 2027. It does not ban data centers. In its Oct. 5 release the city said the extension would not determine whether they will be permitted. The vote also leaves the zoning code unchanged for now: council did not pass the new definitions, and the city's release said the current Land Development Code does not specifically define "data center." Writing that definition is the second half of the staff proposal, and it remains in front of council.
Under the amendment as KY3 described it, the large-load category would be defined only by megawatts and not square footage. That would mean a facility in that category is classified by its power demand rather than the size of its building.
What Happens Next
Council will take up the amended data center definitions at its Nov. 30 meeting, according to KY3. That version includes the mayor's change to define the large-load category by megawatts only. Under the extension council approved Nov. 16, the city will not consider data center plans until after Feb. 24, 2027. The city said in its Oct. 5 release that it will continue to monitor state and federal action on what local governments may adopt.
Sources
- KY3: Springfield City Council extends data center moratorium (Nov. 17, 2026)
- City of Springfield: City proposes next steps in data center review (Oct. 5, 2026)
- KY3: Springfield City Council hears from the public on its proposed administrative delay extension and definitions of data centers (Oct. 27, 2026)
- KY3: Judge denies company's request to end Springfield's data center moratorium (Nov. 10, 2026)
- KSMU: Springfield City Council considers a temporary pause on data center applications (June 23, 2026)