Nine days after Trenton, Ohio, voters approved a city charter amendment barring data centers above 25 megawatts, the developer of an Amazon Web Services data center already under construction in the city has asked a federal court to keep the ban from reaching its project.
Prologis, the California-headquartered real estate company, filed suit on Thursday, Nov. 12, in the U.S. District Court for the Southern District of Ohio. The city of Trenton is the defendant, the Journal-News reported. A letter from the city's law director said Trenton will "actively defend this action."
The case raises a clear legal question. Can a municipality apply a voter-approved land-use restriction to a project it had already approved and permitted, and on which construction had already begun?
The Project and the Vote
The Journal-News describes the Prologis project as a 250-MW AWS data center of nearly 900,000 square feet. WVXU describes it as a data center of nearly 1 million square feet on Kennel and Woodsdale roads. The two outlets give different figures for the building's size.
On Nov. 3, Trenton voters decided Issue 17, a charter amendment prohibiting data centers larger than 25 MW within city limits. According to WVXU, about 80% of voters approved it, based on unofficial results from the Butler County Board of Elections.
Prologis argues that the ban applies to future projects of 25 MW or more, according to the Journal-News. "The city had already approved and permitted Prologis' data center project and the company has begun construction," the company said, the paper reported. "The city's approvals and Prologis' investment came before the Nov. 3 vote."
What Prologis Is Asking the Court to Do
According to WVXU, the complaint argues that the ban is unconstitutional and cannot lawfully be applied to what Prologis calls its "vested, permitted, and substantially constructed project." WVXU reported that the city issued zoning certificates and building permits months before the vote, and that Prologis says the city encouraged and authorized the project. Prologis is asking the court to declare the ban unconstitutional and to prevent the city from stopping the project, WVXU reported. The Journal-News described the request as one to protect the project's previous approvals and Prologis' investment, which it said was made under the rules in place before voters approved the amendment.
The law, Prologis argues, "does not permit the City to change the governing rules after the fact to revoke what it already authorized," WVXU reported.
Much of the account of the complaint describes how far the work has progressed. Per the Journal-News, Prologis cites an investment of $42.3 million. It says the project has received a zoning certificate and that about 325,000 cubic yards of soil had been moved by June 2026, along with near completion of the underground grounding system and cable trenching. WVXU reported the spending figure as more than $42 million.
A Separate Demand to Revoke the Zoning Certificate
Prologis is not the only party pressing the city. The Journal-News reported that lawyers for Conserve Ohio, who drafted the charter amendment, hand-delivered a letter to the city on Monday, Nov. 9, on behalf of Trenton electors and taxpayers. The letter asks Trenton to revoke the project's zoning certificate, arguing that the data center will require a monthly demand or peak load of more than 25 MW, above the amendment's limit. According to the Journal-News, the letter indicates the named taxpayers intend to sue the city to compel it to revoke the certificate.
The city's law director replied to the Conserve Ohio lawyers, according to the Journal-News, saying the Butler County Board of Elections had not yet certified the Nov. 3 results and that review of the letter was "underway."
That leaves Trenton with the developer asking a federal court to shield its project from the amendment, while the taxpayers' lawyers ask the city to apply the amendment to the project's zoning certificate.
How the Amendment Reached the Ballot
The measure reached voters only after a fight at the Ohio Supreme Court. In a per curiam opinion issued Sept. 1, 2026 (Case No. 2026-1035), the Court held that Trenton City Council had improperly refused to certify the charter amendment petition.
According to Court News Ohio's summary, the board of elections verified 336 valid signatures on the petition. Council had demanded 820 signatures, a number equal to 10% of the 8,197 registered voters. The Court held that the Ohio Constitution required only 128, because the threshold is tied to the total vote cast at the last general municipal election, in which 1,277 Trenton voters cast ballots in November 2025.
The Court also ruled that the Ohio Constitution did not require the city to place the amendment on the Nov. 3 general election ballot and that the city could instead set a special election within the 60- to 120-day timeframe set out in the Constitution. Chief Justice Kennedy and Justices Brunner, Deters, Hawkins and Shanahan joined the opinion. Justices Fischer and DeWine joined a portion of the opinion and concurred in the judgment.
Court News Ohio also noted that Trenton Data Center Campus, a construction company building a data center in Trenton, objected to the lawsuit and was allowed to intervene in the case. The amendment appeared on the Nov. 3 ballot, and Prologis filed suit nine days later.
What Happens Next
Neither the Journal-News nor WVXU reported a hearing date in the federal case. As of the Journal-News report on Nov. 13, the Butler County Board of Elections had not certified the Nov. 3 results, and the city's law director said review of the Nov. 9 revocation demand was underway. The city's law director has said Trenton will actively defend the federal action.
Sources
- Data center developer files federal lawsuit challenging ban in Trenton (Journal-News, Nov. 13, 2026)
- Developer sues Trenton over voter-approved data center ban (WVXU, Nov. 13, 2026)
- Trenton Must Place Data-Center-Ban Amendment on Special Election Ballot (Court News Ohio, Supreme Court of Ohio, Sept. 1, 2026)