Interstate pipeline capacity built specifically for a data center's power supply is now flowing in western Pennsylvania. In its annual report for the fiscal year ended Sept. 30, 2026, filed with the Securities and Exchange Commission on Nov. 20, National Fuel Gas Co. says its pipeline subsidiary placed the Shippingport Lateral in service on Nov. 1, 2026. The 10-K says the line delivers 205,000 dekatherms per day from the company's existing Line N to the Shippingport Power Station site in Beaver County, Pa., "which will support a co-located data center that is currently under development."
The filing is plain about what the gas is for. That makes the Shippingport Lateral one of the clearer examples in an SEC filing of a regulated gas pipeline expansion tied directly to on-site generation for a data center, a "bring your own energy" model that local officials in the region have discussed.
What the 10-K Says About the Lateral
According to the 10-K, the project's main parameters are:
- Length: about 7.5 miles, running from Line N to a direct interconnection with the power station.
- Capacity: 205,000 Dth per day.
- Cost: estimated capital cost of about $57 million. National Fuel reports $42.3 million capitalized as construction work in progress as of Sept. 30, 2026, about a month before the in-service date.
- Contracting: a precedent agreement with one developer for 100% of the capacity. The filing does not name the developer.
The project went through the Federal Energy Regulatory Commission quickly. The 10-K says the pipeline filed an application under FERC's prior notice regulations on Aug. 29, 2025, and received authorization on Nov. 7, 2025. By the filing's timeline, it took about 14 months to go from the FERC application to gas in service, and just under 12 months from authorization to service.
National Fuel also ties the lateral to its near-term outlook. The 10-K says the Shippingport Lateral and the company's Tioga Pathway project, both placed in service on Nov. 1, 2026, together are expected to add 380 MDth per day (380,000 Dth per day) of incremental contracted capacity in fiscal 2027 compared with fiscal 2026 levels.
A Second, Larger Expansion Into the Same Industrial Park
The lateral is not the only project aimed at Shippingport. The 10-K describes a separate Line N System Upgrade that would add about 294,000 Dth per day of capacity, including a new interconnection at the Shippingport Industrial Park. National Fuel says two shippers hold precedent agreements for 100% of that capacity, and it gives a projected in-service date of November 2028.
If the upgrade is built as described, the two projects together would bring National Fuel's contracted deliveries into the Shippingport area to roughly 499,000 Dth per day. That combined figure is DataCenterFeed's sum of the two capacities the company reports; National Fuel does not state it. The filing excerpts reviewed here do not say whether the upgrade's two shippers are connected to the data center development served by the lateral.
The Risks National Fuel Discloses
The same annual report that books the new data center load also warns investors about it. Among its risk factors, National Fuel cites organized opposition to the natural gas industry, including pipeline expansion projects that support data center development. That adds data center projects to the list of targets for opposition that the company discloses.
The company also flags counterparty risk, saying it has entered into commercial arrangements that expose it to counterparty risk, including long-term service commitments to support data center developers and other high-volume customers. In practical terms, a pipeline that builds capacity based on a precedent agreement with one developer depends on that developer's ability to keep paying. The Shippingport Lateral's capacity is fully contracted to a single developer, so for this project the exposure is concentrated in one customer rather than spread across several.
Beaver County's Place in the Buildout
The lateral serves a stretch of the Ohio River where data center investors have shown interest. In a Feb. 17, 2026 report, KDKA (CBS Pittsburgh) said investors have been drawn to brownfield sites in the Beaver Valley, where there is abundant natural gas to power data centers and water from the Ohio River to cool them. The president of the Beaver County Corporation for Economic Development told the station that "bringing your own energy to the table is the number one issue that we have with any of the hyper-scalers."
The KDKA report described several projects. Aligned said it plans two natural-gas generating stations to power two or more data center buildings near Shippingport. Separately, Meta signed a 20-year agreement with Vistra to buy power generated by the Beaver Valley nuclear station.
Data Center Frontier, in a Sept. 30, 2026 analysis of two former coal-generation sites in western Pennsylvania, described Aligned's planned 2-gigawatt Project Phoenix campus in Shippingport. The publication said the project redevelops a legacy industrial site into three data center facilities supported by dedicated onsite power, which it described as natural-gas fuel cells. It contrasted that approach with the centralized multi-gigawatt gas generation and proposed Amazon Web Services campus at Homer City.
National Fuel's 10-K, in the passages reviewed, does not identify the developer behind the Shippingport Power Station or its co-located data center, and it does not mention Aligned. Readers should not assume that the lateral's contracted shipper and Project Phoenix are the same, because none of the sources here make that link.
Why the Numbers Matter
The filing is a documented case of a data center developer's power supply being tied to a dedicated pipeline lateral, with gas-fired generation at the site, rather than relying only on grid interconnection. The lateral's prior-notice authorization on Nov. 7, 2025 and its single fully contracted customer are the facts the filing supplies about how it was built.
National Fuel's own risk disclosures point to where that model could run into trouble: organized opposition to pipeline projects that support data center development, and counterparty risk from long-term commitments to data center developers.
What Happens Next
According to the 10-K, the Shippingport Lateral was placed in service on Nov. 1, 2026, and National Fuel expects it and the Tioga Pathway project to add 380 MDth per day of contracted capacity during fiscal 2027. The next scheduled milestone in Shippingport is the Line N System Upgrade. The company projects that the roughly 294,000 Dth-per-day expansion will enter service in November 2028, with two shippers holding all of its incremental capacity. The filing does not give a schedule for the co-located data center itself.
Sources
- National Fuel Gas Co. Form 10-K for fiscal year ended Sept. 30, 2026 (SEC EDGAR)
- Data Center Frontier: From Coal to Compute: How Pennsylvania Is Rebuilding Power for AI Data Centers (Sept. 30, 2026)
- CBS Pittsburgh (KDKA): Beaver Valley could become center of AI infrastructure for region (Feb. 17, 2026)