The Public Service Commission of Wisconsin has approved the final version of its 2026-2032 Strategic Energy Assessment (Docket 5-ES-113). The document's central finding is that a few large data center campuses now drive the state's electricity planning outlook. According to the final assessment, Wisconsin's peak load is expected to grow from approximately 14.2 gigawatts in 2026 to 20 GW by 2032. That is an increase of nearly 5.8 GW, or over 40 percent.
The commission says most of that growth comes from three projects. "Approximately 4.12 GW, or approximately 71 percent" of the increase is associated with three active data center developments in the service territories of Wisconsin Power and Light and Wisconsin Electric Power Company, the final assessment states. Wisconsin Public Radio reported that the commission approved the assessment on Thursday and identified the three projects as data center developments in Mount Pleasant, Port Washington and Beaver Dam.
The numbers, and how they moved from the draft
The commission released a draft of the assessment for public comment before the final. In its Aug. 17 press release, which said the draft was open for comment, the commission said it had requested updated actual and forecasted information from electric providers for the final version. Construction Owners, reporting on the draft in July, said it attributed about 4.17 GW, roughly 72 percent, of the growth to hyperscale projects in Beaver Dam, Port Washington and Mount Pleasant, in Alliant Energy and WEC Energy Group territories. The final document puts the figure at approximately 4.12 GW, or approximately 71 percent, a slightly lower share. The overall trajectory of about 14.2 GW to 20 GW by 2032 is the same in both versions.
The final assessment cites two sources for the data center load figures: Wisconsin Power and Light's application for an Individual Contract Rate Electric Service Agreement (PSC REF#: 589144) and WEC Energy Group's second-quarter 2026 earnings call. The footnote to the assessment's 4.12 GW figure points to the stated maximum contract demand in the Wisconsin Power and Light filing.
The commission also says the forecast may not include all future demand. According to the assessment, utilities report that developers are considering additional prospective data centers that could add load beyond what the forecast includes.
What utilities say they will build
WPR reported that utilities plan 14.4 GW of new generation over the assessment period. According to WPR, the plans include 5.8 GW of solar and 5.2 GW of natural gas, with the rest made up of wind and storage. The utilities pointed to a North American Electric Reliability Corporation warning of elevated shortage risk in the Midwest beginning in 2028, WPR reported.
The 14.4 GW of planned generation WPR reported is larger than the forecast peak-load increase of about 5.8 GW, though the two figures measure different things. The assessment does not decide which of these resources get built. In its August release, the commission said Wisconsin has no integrated resource planning (IRP) process and that the commission does not prescribe which generation providers build or retire. The Strategic Energy Assessment is a biennial report built on data that ten electric providers submitted in November 2025. It describes the outlook the utilities have reported. It does not approve any plant.
"A massive number"
Commission Chair Summer Strand spoke about the scale of the growth at the meeting where the assessment was approved. "40 percent is a massive number," Strand said, according to WPR. She also said she was concerned that regulators may lack the tools under state law to plan for demand growth of that size, WPR reported.
WPR reported that Strand said that under current state law the commission approves generation projects case by case as utilities or developers file applications, and that the assessment is the commission's primary planning tool. "The SEA has no teeth. It's more of a report," she said, according to WPR. The August release likewise says Wisconsin has no IRP process.
Climate goals and the wider context
WPR reported that environmental groups are concerned about how the planned buildout, particularly the 5.2 GW of gas, fits with Wisconsin's goal of carbon-free electricity by 2050. According to WPR, no legal mechanism requires utilities to meet that goal.
WPR also cited a Harvard study of 403 hyperscale data centers. The outlet reported that the study found those facilities accounted for 1.8 percent of U.S. electricity use and about 25.7 million metric tons of carbon dioxide emissions.
Why three projects matter so much
The assessment's main finding is how concentrated the demand is. According to the commission, roughly seven of every ten megawatts of expected new peak demand in the state through 2032 are linked to three developments in two utility territories.
The final assessment also says utilities indicate that additional prospective data centers could raise peak load beyond the forecast if those projects proceed to construction.
What Happens Next
The sources do not name a scheduled next step for the assessment itself, which was approved in its final form. Wisconsin Public Radio reported that Strand said the commission approves generation projects case by case as applications are filed, and that the assessment gathers and publishes data rather than approving a comprehensive plan. The final assessment cites Wisconsin Power and Light's application for an Individual Contract Rate Electric Service Agreement (PSC REF#: 589144) for the stated maximum contract demand behind its data center figure. The commission prepares the Strategic Energy Assessment every two years, according to its August release.
Sources
- Public Service Commission of Wisconsin: Final Strategic Energy Assessment 2026-2032, Docket 5-ES-113 (PDF)
- WPR: Report: 3 Wisconsin data centers account for 70 percent of growth in peak electricity demand
- Public Service Commission of Wisconsin press release, Aug. 17, 2026: Draft Strategic Energy Assessment open for comment (PDF)
- Construction Owners: Wisconsin PSC forecasts sharp power demand growth as data center construction expands