A complaint before the Pennsylvania Public Utility Commission asks a basic question about the state's data center boom: when a hyperscale campus needs new grid infrastructure, who pays for it? Pennsylvania's Office of Consumer Advocate (OCA) says that under PPL Electric Utilities' current large-load tariff, most of the bill goes to everyone else.
The case, PUC docket C-2026-3065756, was filed on Oct. 2, 2026, and the OCA later filed an amended complaint. The docket lists the case as active, with two administrative law judges assigned. Gov. Josh Shapiro has petitioned to intervene. PPL's Answer and New Matter to the amended complaint was posted to the docket on Nov. 18. Spotlight PA reports that a final commission decision is not due until next July.
What the Complaint Alleges
TechTarget reported that the complaint challenges protections in PPL's existing large-load tariff, Rate LP-6. According to the governor's office, the OCA argues that PPL's current rates, service classifications and procedures do not adequately protect existing customers from paying costs caused by large data centers, or from potential outages. Spotlight PA reported that PPL's current rules were updated as part of a rate-case settlement that state regulators approved in June, and that the consumer advocate argues they still allow other customers to share increased transmission costs caused by data centers.
The OCA's main example is a single project. TechTarget reported that the amended complaint cites about $178.4 million in proposed network upgrades for a hyperscale data center campus. According to TechTarget, the OCA alleges that $21.5 million of that would be assigned to the data center customer and $156.9 million to other ratepayers. TechTarget noted that this allocation is an allegation in the complaint, not a finding by the commission.
Spotlight PA, in a report published by the Williamsport Sun-Gazette, described the same dispute as a planned transmission line in Luzerne County needed to serve a potential data center campus. It reported that the upgrades will cost about $178 million, according to legal filings, and that PPL plans to recover only 12% of that from the data center itself. Without changes to PPL's rules, the consumer advocate argues, existing customers will pay the remaining $157 million.
The OCA also points to the size of PPL's pipeline. TechTarget reported that the complaint cites an advanced-stage data center pipeline of approximately 31.8 GW through 2034. It also identifies a change in PPL's 2030 large-load forecast adjustment, from 13,343 MW in an earlier annual submission to 12,764 MW in a September 2026 submission. Spotlight PA reported that, according to the complaint, PPL has forecast more demand from data centers than any other electric company in Pennsylvania. Spotlight PA also reported that, according to the complaint, demand in Pennsylvania is projected to increase by more than 18% by 2030, driven almost entirely by data centers.
What the OCA Is Asking For
The complaint asks for more than a different split of one project's costs. Based on the source reporting, the OCA is seeking:
- Mandatory interruptible service. TechTarget reported, citing an analyst's review of the complaint, that it seeks mandatory interruptible service, which can require large customers to reduce electricity consumption under specified conditions.
- Reduced service when the grid is stressed. Spotlight PA reported that the complaint warns that all of PPL's customers could experience "forced" outages if data centers are added without enough new supply or ways to cut back usage, and that the consumer advocate wants data centers' service reduced if the grid becomes overwhelmed, or before, if needed to avoid an emergency.
- Low-income program contributions tied to load. Spotlight PA reported that the complaint seeks to increase data center contributions to PPL's assistance programs for low-income customers, which were set at $11 million per year in the earlier settlement. The consumer advocate argues the amount should be tied to the amount of power data centers use rather than fixed.
The complaint is set against guidance the PUC issued in May. Spotlight PA reported that in this guidance, regulators concluded that if network upgrades would not have been necessary "but for" the interconnection of a data center, the data center should pay for them, even if other customers also benefit. Spotlight PA also reported that the guidance is not binding, and that the consumer advocate says PPL's current rules still allow other customers to share data center transmission costs.
The Governor's Intervention
On Oct. 15, Shapiro filed a petition to intervene in the OCA's proceeding. His office said the petition marks the first time in at least 15 years that a governor has intervened in a PUC proceeding. The office said the petition advances Executive Order 2026-05, which Shapiro signed in August.
According to the governor's office, Shapiro will advocate for several things, among other measures:
- a separate customer class for large data centers
- allocating costs caused by their electricity demand to that class
- stronger requirements for data center-related transmission upgrades
- safeguards that protect existing customers if electricity supply cannot meet demand
PPL's Response
PPL's Answer and New Matter to the amended complaint was posted to the docket on Nov. 18. The PUC website marks it as restricted, so its contents are not publicly available there. In a statement reported by Spotlight PA, a PPL spokesperson said the company is "committed to protecting customers, maintaining reliability and ensuring that large-load customers pay the costs associated with their projects." Spotlight PA also reported that PPL has proposed its own changes to how transmission costs are allocated, which the company says would make it possible to assign them directly to data centers, and that the consumer advocate argued more details are needed.
Who Else Is in the Case
The docket shows other parties getting involved. On Nov. 12, the Data Center Coalition filed a motion for admission pro hac vice for two attorneys, which lets attorneys not licensed in Pennsylvania appear in the case. On Nov. 19, CAUSE-PA and the environmental intervenors filed certificates of service for Set I interrogatories to PPL, a sign that discovery is underway. The OCA also filed a letter about the litigation schedule on Nov. 12, and the docket shows a scheduling order made public on Nov. 10.
The judges assigned to the case, John M. Coogan and Erin L. Gannon, held an initial prehearing conference on Nov. 3, 2026, according to the docket. Prehearing memoranda were also filed in early November by parties including the governor, Amazon Data Services Inc., and the PP&L Industrial Customer Alliance.
Why It Matters Beyond PPL
Spotlight PA reported that the consumer advocate described the case as one that "should pretty much set the guiding principles for everyone else." Spotlight PA also reported that PPL has forecast more data center demand than any other Pennsylvania utility, according to the complaint.
Several questions are open in the case: whether large data centers should be a separate rate class, whether interruptible service should be mandatory, and how low-income contributions should be set. The governor's office and the OCA have each stated their positions, and PPL has said it is committed to ensuring large-load customers pay the costs of their projects. The commission has made no finding on the allegations.
What Happens Next
The case is listed as active and assigned to Administrative Law Judges Coogan and Gannon, according to the PUC docket. Intervenors filed certificates of service for Set I interrogatories to PPL on Nov. 19, and the OCA filed a letter about the litigation schedule on Nov. 12. Spotlight PA reports that the case, which will include public hearings as well as extensive testimony, is still in its early stages, and that a final decision from the commission is not due until next July.
Sources
- Pennsylvania PUC docket C-2026-3065756: OCA v. PPL Electric Utilities Corp.
- Office of the Governor: Governor Shapiro files intervention petition in PUC case (Oct. 16, 2026)
- TechTarget: Pennsylvania complaint challenges PPL's ratepayer protections (Oct. 27, 2026)
- Spotlight PA via Williamsport Sun-Gazette: State consumer advocate files complaint against data centers (Nov. 21, 2026)