Olyphant Borough Council in Lackawanna County, Pa., has settled a lawsuit brought by data center developer ERCOR Triboro LLC. According to The Center Square, the settlement does away with the conditional-use public hearing process that would otherwise have applied to the company's Project Triboro proposal. In the nine days since the vote, county commissioners have rescinded a tax break tied to the site and the local school district has said it has gone to court to intervene in the case. Separately, borough police have arrested a man accused of threatening officials.

The council took two separate votes on Nov. 17, both 5-2, according to The Center Square. The first ratified the settlement with Ercor Triboro, which "does away with" the traditional conditional-use process involving a public hearing. The second approved a community benefits agreement (CBA) that The Center Square says would pay out "$100 million-plus" to the community over 15 years. WVIA News puts the CBA at $101 million and reports that the votes came at the end of a three-hour public meeting. Five of the seven council members voted for both measures, WVIA reports, without explanation. WVIA also reports that residents, one after another, had asked the council not to settle.

What the Settlement Allows

The Times-Tribune reports that the settlement allows ERCOR Triboro to move forward with plans to develop seven data centers and a substation. They would sit within the footprints of four previously approved warehouses off Marshwood Road and Route 247. None of the sources reviewed for this article give the campus's power capacity, its water use, the size of the buildings or a jobs estimate.

The borough posted a notice of a special meeting on its website. It is titled "Notice of Special Meeting on November 5, 2026" and sets the meeting for 6:00 p.m. at The Regal Room, 214 East Lackawanna Avenue, Olyphant. The notice lists two items: a resolution "to resolve the Ercor Lawsuit filed against Olyphant Borough" and consideration and approval of a Community Benefit Agreement between Ercor and the borough. It is signed by the borough secretary. The news reports reviewed here place the council's votes on Nov. 17, not Nov. 5, and none of them explains the difference in dates. The notice does not state terms of the settlement or the agreement, and DataCenterFeed did not find minutes of the Nov. 17 vote on the borough's meetings page.

State records show the developer has also been working through state permitting. A notice in the Pennsylvania Bulletin (Vol. 56, No. 19, May 9, 2026) lists a PAG-02 general permit, number PAC350120, as issued to ERCOR Triboro, LLC, of Victor, N.Y. The permit covers Jessup, Olyphant and Throop boroughs in Lackawanna County, and the Lackawanna County Conservation District is listed as the reviewing office. The Bulletin entry does not mention the lawsuit, the settlement or the CBA.

Why the Hearing Matters

Under the settlement, the conditional-use public hearing process will not take place for Project Triboro, according to The Center Square. Mid Valley School District Superintendent Patrick Sheehan told the outlet that the district would have carried out its obligation to protect "the health, safety, and welfare of the students and staff" by taking part in the public hearing process that has been scrapped.

State Rep. Kyle Mullins, a Democrat whose district includes Olyphant, objected in The Center Square's coverage. "Residents deserve to have a voice in these decisions and any move to foreclose on that process is wrong," he said. Mullins said the site was originally supposed to be developed with warehouses with "thousands of jobs" and that the switch to data centers means public hearings are necessary. He also called for urgent action to change state law on data centers. The Center Square article was mainly about statewide attitudes toward data centers. Chris Borick, director of the Lehigh University Opinion Observatory, told the outlet that the center expects to release data on a data-center poll by mid-December.

Threats, an Arrest and Six Others Under Investigation

Olyphant police say they are investigating threats directed at borough officials amid the debate over the project. FOX56 reports that, according to a criminal complaint, police arrested a Taylor man who allegedly wrote in a Facebook post that he would "show up with shotguns and resolve the situation" if Olyphant Borough Council voted to settle the Project Triboro suit and accept the $101 million CBA. FOX56, citing the Times-Tribune, reports that Police Chief James DeVoe said police are investigating six other people over threats. The station also reports that the arrested man remains in jail without bail after allegedly making additional threats toward the presiding magistrate at his arraignment. DataCenterFeed is not naming him; the reports describe the allegations as coming from a criminal complaint.

DeVoe told the Times-Tribune that conduct crossing from free speech into criminal threats, including threats aimed at council members' families, homes, businesses or workplaces, will result in arrest and charges. He also said the threats have come exclusively from people outside the area and not from Olyphant residents, whom he described as having raised their voices but stayed respectful.

The County Pulls a 2019 Tax Break

On Nov. 18, the day after the council vote, all three Lackawanna County commissioners voted to rescind a 2019 tax break, WVIA reports. WVIA describes the break as intended originally for a proposed warehouse development, and says the owner of the proposed Olyphant data centers will not get a break on property taxes from the county. WVIA's report does not give the value of the abatement.

The School District Goes to Court

Mid Valley School District is also trying to get involved. Its superintendent told The Center Square that the district has gone to court to intervene in the case. According to that report, the district's cluster of buildings is 1.5 miles from the site, and about 2,000 students as young as five and about 200 staffers are on the campus during the day. The district is also seeking proposals for noise and environmental studies to be done at the proposed data center site.

According to The Center Square, a hearing on the district's participation is scheduled for Dec. 7 in Lackawanna County Court.

Discrepancies in the Record

News reports do not agree on every detail. The Times-Tribune, published Nov. 21, says council members voted 5-2 "on Tuesday," which is consistent with Nov. 17, the date given by The Center Square. WVIA, FOX56 and the Times-Tribune report the benefits agreement as $101 million, while The Center Square describes it as "$100 million-plus" over 15 years. FOX56's summary line reads "over $2100 million," which appears to be a typo, since the body of the same story says $101 million. As noted above, the borough's notice is for a Nov. 5 special meeting, while the reports place the votes on Nov. 17. The text of the CBA and the settlement terms were not among the documents available for this article.

What Happens Next

A hearing on Mid Valley School District's request to participate in the case is set for Dec. 7 in Lackawanna County Court, according to The Center Square. Olyphant police say their investigation of six other people over threats is ongoing. Separately, the Lehigh University Opinion Observatory expects to release its data-center polling by mid-December, according to Borick.