On the evening of Nov. 18, 2026, the Stafford County, Va., Planning Commission held one combined public hearing on four data center applications along Kings Highway (State Route 3). All four were filed by the same applicant and owner, Real Estate Pursuits 2 LC. The hearing had been moved from October, and the county's planning staff had recommended denial of the rezonings in reports written for the earlier date.

According to WJLA 7News, more than 100 people came to the Stafford County Government Center. Staff and the developer presented for about two hours before public comment opened, and more than 130 people signed up to speak. None of the sources reviewed for this article reported a Planning Commission vote. This story covers the hearing and the record leading up to it.

What Is Proposed

The county's project page for the Route 3 data centers lists four separate applications. Its summary table gives these figures, which describe the proposed developments:

  • Forest Lane: 844.92 acres, about 6 million square feet, 26 data center buildings and 8 substations.
  • Simms Farm: 204.71 acres, about 500,000 square feet, 1 data center building and 2 substations.
  • Sisson North: 114.01 acres and 3 substations. The county describes it as a substation-only proposal.
  • Sisson South: 241.18 acres, about 2.5 million square feet, 10 data center buildings and 1 substation.

The county's table puts the combined total at 1,404.82 acres, about 9 million square feet, 37 data center buildings and 14 substations. WJLA described the project as four sites covering roughly 1,500 acres and about nine million square feet.

Earlier figures were larger. Potomac Local, writing about the staff reports prepared for October, reported the project at 48 buildings and about 11 million square feet. The county's current table lists 37 buildings and about 9 million square feet, so the proposal shown on the county's page is smaller than the version described in October.

Each application has its own case numbers. For Forest Lane, the county lists the rezoning as RC25156546 and the conditional use permit as CUP25156542.

Why Staff Recommended Denial

The hearing was first set for Oct. 14. Potomac Local reported that the staff reports prepared for that date recommended denial of the rezonings and of most of the conditional use permits. According to Potomac Local, staff cited several reasons:

  • Comprehensive Plan conflicts. The sites carry Agricultural/Rural or Mining designations in the county's Comprehensive Plan.
  • Building height. The buildings were proposed at 75 feet.
  • Substations. Staff raised concerns about how many substations were proposed and how large they would be.
  • Proffers. Staff said the applicant's proffers do not sufficiently preserve the area's rural and agricultural character or limit future uses strictly to data centers and related facilities.

Potomac Local also reported some details of the Forest Lane application. It sought to rezone land from A-1 and M-1 to M-2, with a conditional use permit for up to eight substations. For all of the applications together, Potomac Local reported that the applicant proposed to use only a future reuse-water system for industrial cooling, that pre-development sound studies showed projected noise levels generally within the county's 55 dBA daytime limit, and that proposed mitigations included setbacks, vegetated buffers and 20-foot berms.

The staff recommendation is advice to the commission. It does not decide the case. The sources reviewed do not say whether staff changed any recommendation after the hearing was postponed.

The Fiscal Claim

WJLA reported that an attorney with the project had told 7News previously that the area could generate $245 million a year, or just over 20 percent of the county budget. That figure is the project attorney's claim as WJLA reported it. None of the sources reviewed here include a county fiscal analysis that confirms it.

How the Hearing Was Run

The county's project page says the Oct. 14 hearing was moved by agreement of the applicant and county staff, and the Oct. 14 Planning Commission meeting was canceled. Potomac Local also reported the cancellation and the new Nov. 18 date.

The county set up one public hearing for all four applications, starting at 6:00 p.m. in the Board Chambers. Each speaker had up to three minutes, and the county says each application will be voted on individually. With more than 130 people signed up, as WJLA reported, public comment alone could run past six hours at that limit. Comment followed about two hours of presentations.

WJLA's account says many residents opposed the project during the meeting, while a handful of people, including union workers, spoke in support. In keeping with DataCenterFeed policy, this article does not name members of the public who spoke.

The Planning Commission makes recommendations. The Board of Supervisors makes the final decision on rezonings and conditional use permits. The county's page says the Board of Supervisors will use the same process: one public hearing covering all four applications, with three minutes per speaker.

What Happens Next

WJLA reported that the Stafford County Board of Supervisors could take up the Kings Highway applications at its Dec. 15 meeting. That date had not been confirmed as a scheduled hearing in the county material reviewed for this article. The county says the board hearing will follow the same format as the Planning Commission's: one combined hearing on all four applications, with three minutes per speaker. Readers should check the county's Route 3 data center page for the official date and for the Planning Commission's recorded action on each application.