The head of Vistra, one of the largest independent power producers in the U.S., says the November elections settled some of the uncertainty around data center development. He also says the interconnection queues that have driven forecasts of large load growth are bigger than the demand that will actually arrive.
Vistra CEO James Burke spoke on the company's third-quarter earnings call on Nov. 6. Utility Dive reported his remarks on Nov. 24. According to that report, Burke said that before the elections there were concerns in many markets about how the public was reacting to the pace of data center development, who had control over those decisions, and what impact it could have on electric prices and water. "Moving past this election is a positive just in terms of being able to understand what's at stake, and now how do we move forward?" he said.
He also said the load queues that utilities and grid operators have been reporting overstate real demand. "As we've said for some time, load interconnect queues were overstated across the country and especially in [the Electric Reliability Council of Texas footprint], driven by speculation from developers," Burke said, as quoted by Utility Dive.
Guardrails, Not a Reversal
Utility Dive reported that Burke said the key messages so far from Texas Gov.-elect Gina Hinojosa have been "very similar to some of the key messages that Governor Abbott had expressed" and consistent with Vistra's own message that "there has to be some guardrails on this development."
For Vistra, guardrails mean stricter rules for large loads that want to connect to the grid. According to Utility Dive, Burke said Vistra wants tougher requirements for data center interconnection, including higher collateral requirements and take-or-pay agreements for transmission charges. Under a take-or-pay structure, a customer pays for transmission capacity it reserves even if it uses less.
Load Growth Forecast Holds
Burke's doubts about the queues did not change Vistra's growth outlook. Through 2030, Vistra expects load growth of 4% to 6% a year in ERCOT, the Texas grid, and 2% to 3% a year in the PJM Interconnection footprint, Utility Dive reported. Zacks' summary of the call reports the same ranges.
Burke also addressed recent softness in Texas power prices. Utility Dive reported that ERCOT prices have been trending lower, which Burke attributed to some crypto-mining facilities coming offline so they can convert into data centers, and to the state's data center audit and permitting pause. "We do not see this as a long-term impact," Burke said. Utility Dive noted that Burke cited a 91 GW peak demand record in ERCOT this year.
Utility Dive also reported that the year-to-date third-quarter capacity factor of Vistra's combined cycle fleet in ERCOT was 65%, up from 59% in the same period last year.
Zacks' summary of the call says that management addressed slower data center connections in Texas and regulatory uncertainty. Stacey Dore, Vistra's chief strategy and sustainability officer, said grid interconnection delays complicate gas-related contracts. According to Zacks, she said some customers are willing to pay for temporary behind-the-meter power until grid service becomes available. Zacks also reported that Burke said increased scrutiny of data center projects predates the election and favors tighter qualification standards rather than a blanket moratorium.
A Bigger Gas Fleet
Vistra's fleet has grown to about 50 GW with its Oct. 30 Cogentrix acquisition, according to Utility Dive. The company's Form 10-Q for the quarter ended Sept. 30 says the Cogentrix deal added 10 natural gas generation facilities totaling approximately 5,500 MW.
Zacks reported that Vistra posted record quarterly adjusted EBITDA of $2.378 billion. It narrowed its 2026 ongoing operations adjusted EBITDA guidance to $7.1 billion to $7.5 billion and gave initial 2027 guidance of $7.7 billion to $8.5 billion, which Zacks says Burke described as including Cogentrix and the Meta agreement at the Perry nuclear plant. The 10-Q says Vistra's board authorized an incremental $1.5 billion for share repurchases on Oct. 29.
Utility Dive reported that Vistra's share price was $120 on Nov. 24, down 14% from about $140 on Nov. 3, Election Day.
The Meta Nuclear Contracts
Vistra's contracts with Meta are 20-year nuclear power purchase agreements in PJM. According to the 10-Q, Vistra announced in January 2026 that it had agreed to supply Meta with a total of 2,609 MW of carbon-free power and capacity from its PJM nuclear power plants. That total breaks down as follows:
- 1,268 MW from Perry
- 908 MW from Davis-Besse
- Uprate capacity of 213 MW at Perry, 80 MW at Davis-Besse and 140 MW at Beaver Valley
Utility Dive put the planned nuclear uprates at 433 MW, which matches the sum of the three uprate figures in the 10-Q. The 10-Q says Vistra expects to incur capital expenditures on the uprates from 2026 through 2034, with less than 20% of the aggregate spend projected by year-end 2028.
Zacks reported that Dore identified Beaver Valley and part of Comanche Peak as remaining nuclear contracting opportunities.
Investing Upstream: The KKR Helix Fund
Vistra has also invested in a fund aimed at AI infrastructure. According to the 10-Q, in June 2026 Vistra entered into the limited partnership agreement for KKR Helix C L.P., an open-ended fund managed by affiliates of KKR, and committed up to $1 billion as a founding investor. The Helix Fund will seek to invest in and manage assets critical to enabling AI, including hyperscale data center development and operations, baseload and flexible power generation, transmission and distribution infrastructure, and fiber and connectivity infrastructure.
The commitment has two parts: an initial $500 million, plus another $500 million that is subject to the fund meeting certain commercial power supply milestones for Vistra's existing generation assets or, at Vistra's election, regardless of whether those milestones are achieved. The 10-Q says Vistra will not consolidate the fund and will account for the investment under the equity method.
What Happens Next
Vistra's 10-Q sets out these anticipated dates for the Meta contracts:
- Delivery of a portion of the operating energy and capacity begins in late 2026.
- Full delivery of the operating energy and capacity from Perry and Davis-Besse is anticipated by year-end 2027.
- Delivery of a portion of the uprate energy and capacity is anticipated by 2031, with full uprate delivery by year-end 2034.
Vistra's initial 2027 guidance, as reported by Zacks, includes Cogentrix and the Meta agreement at Perry.
The sources do not give a date for the interconnection rule changes Vistra wants, such as higher collateral or take-or-pay transmission charges, or for the end of the Texas data center permitting pause and audit.