Construction has stopped at the site of Google's planned data center campus in Van Buren Township, Michigan. The project has a township site-plan approval and a set of state-approved utility contracts. It now lacks a county construction permit.
In an order dated Nov. 20, Wayne County told Panattoni Development Company to stop work. Panattoni is managing construction of the campus, which is known as "Project Cannoli." According to The Arab American News, which reported the order on Nov. 26, the county cited work done without a required county construction permit, violations of county stormwater rules, obstructions in drains and work in areas reserved for drainage access. It also cited inadequate erosion controls, including silt fencing, that let sediment enter county drains, and unpermitted work in a county road right-of-way. County spokesperson Matt Allen confirmed on Nov. 24 that construction had stopped. He gave no timetable for a restart.
The order deals with permits and drainage. It does not cancel the project, and nothing in the record so far changes the township's site-plan approval or the state's ruling on the power contracts. It does put a county-level condition in front of any further work. That condition sits on top of a separate challenge to the electricity deal that the state attorney general filed in October.
What the County Found
Wayne County Public Services Director Oladayo Akinyemi said county inspectors found the drain obstructions, according to The Arab American News. Panattoni already held a soil erosion permit, but the report says that permit allowed only limited work such as tree trimming and grading. The county's order cites work without the construction permit the county requires.
The other violations in the order are all tied to drainage and county property. The county said crews failed to install adequate erosion controls, and sediment reached county drains. The order also cited work in areas set aside for drainage access and work in a county road right-of-way without a permit. Allen said work next to a county drain also requires a plan to manage runoff, particularly during heavy rain, when mud and silt can wash into the drainage system, according to the report.
Panattoni said it is working with county officials to address the issues raised in the order, according to the report.
The Project in Numbers
The figures below come from the developer and local officials, as cited in each source.
- Site: About 282 acres east of Haggerty Road and north of the I-94 North Service Drive, according to The Arab American News. Michigan Public describes the 282-acre site as lying between I-94 and I-275 and says it was already zoned industrial.
- Power: About 1 GW once operational, according to the developer's estimate as reported by The Arab American News.
- Water: 2 million to 3.6 million gallons per day, also a developer estimate reported by The Arab American News.
- Contracts and jobs: Panattoni data center executive Adam Kramer said site construction would bring $2 billion in contracts to Wayne County businesses and that the finished facility would have 50 to 200 on-site employees, Michigan Public reported.
- Tax terms: Officials with Wayne County and the township agreed to a $125 million tax break, and Google agreed to pay $15 million each to the county and the township, according to Michigan Public. County officials overrode a veto by County Executive Warren Evans at the start of October to approve the break.
Michigan Public reported that Google will own and operate the site and that Panattoni manages construction.
How the Project Got Here
The stop-work order follows several weeks of approvals and challenges at the state and local level.
Oct. 1: State regulators approve the power contracts. The Michigan Public Service Commission approved two contracts between DTE Electric and Google LLC in Case No. U-22058: a primary supply agreement and a clean capacity accelerator agreement. The approval came with conditions meant to keep the project's costs off other customers. The contracts run 20 years, compared with the 5 years normally required under DTE's D11 rate. They set minimum billing demand at 80%, compared with 50% to 65% in the general D11 rate. An early-termination payment covers at least 15 years of minimum monthly charges, and credit and collateral requirements apply.
Under the contracts, Google must pay for DTE to develop up to 1,600 MW of renewable energy and 480 MW of battery storage, according to the commission. DTE says the data center is expected to begin taking service in December 2027 and to reach maximum load by December 2028. The utility also contends the contracts will produce a $1.7 billion benefit to other customers over 20 years. The commission's release notes that its authority covers the contracts, not where the facility is sited or how it is built.
Oct. 14: The township approves the site plan. The Van Buren Township Planning Commission voted 5-1 to approve the final site plan, according to Michigan Public.
Oct. 30: The attorney general challenges the contracts. Michigan Attorney General Dana Nessel filed a petition for rehearing before the commission in case U-22058. Her office describes the deals as twenty-year, billion-dollar agreements. She argues that the commission applied incorrect standards of review and that the contracts risk shifting costs to DTE's other customers. She objects to what her office calls an "aggregation" approach, which weighs projected ratepayer benefits against actual costs over the full life of the contract. She also proposes stronger terms for cost recovery, for tracking costs and benefits, and for backstopping costs.
Nov. 20: The county issues the stop-work order. Wayne County ordered Panattoni to halt construction for the permitting and drainage reasons described above.
Nov. 24: The county confirms the work stoppage. Spokesperson Matt Allen confirmed that construction had stopped and gave no date for it to resume.
Three Approvals, Three Authorities
Each of the steps above was handled by a different public body with a different scope of authority.
The township planning commission ruled on the site plan for land already zoned industrial. The state utility commission ruled on whether DTE's power contracts with Google protect other ratepayers, and its release says that authority does not reach whether and where a data center locates. That ruling is now the subject of the attorney general's rehearing petition. Wayne County oversees drains, stormwater and its own road rights-of-way, and it is now the body holding up physical work on the site.
For communities following large campus proposals, the Van Buren case shows that a final site-plan approval does not settle every permit the project needs. In this case, the county's construction-permit, drain and stormwater requirements are what stopped work.
What Happens Next
According to The Arab American News, Panattoni must do three things before work can resume. It must obtain a county construction permit, fix the erosion-control violations, and reach an agreement with the relevant drainage districts or the Wayne County drain commissioner. The county has not given a restart date.
On the utility side, the attorney general's Oct. 30 petition for rehearing of the DTE-Google contracts is before the Michigan Public Service Commission in case U-22058. DTE's stated schedule calls for the data center to begin taking electric service in December 2027 and to reach maximum load by December 2028.
Sources
- Google data center paused over missing Wayne County permit (The Arab American News, Nov. 26, 2026)
- MPSC approves DTE Electric energy contracts for Google data center, protects other customers from the project's costs (Michigan Public Service Commission, Oct. 1, 2026)
- AG Nessel Challenges MPSC Approval of DTE's Google Data Center Contracts (Michigan Attorney General, Oct. 30, 2026)
- Google wins zoning approval for huge data center near Detroit airport (Michigan Public, Oct. 15, 2026)